Weather Engineering & Manufacturing, Inc. v. Pinon Springs Condominiums, Inc.

563 P.2d 346, 192 Colo. 495
CourtSupreme Court of Colorado
DecidedMarch 28, 1977
Docket27019
StatusPublished
Cited by14 cases

This text of 563 P.2d 346 (Weather Engineering & Manufacturing, Inc. v. Pinon Springs Condominiums, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weather Engineering & Manufacturing, Inc. v. Pinon Springs Condominiums, Inc., 563 P.2d 346, 192 Colo. 495 (Colo. 1977).

Opinion

MR. JUSTICE LEE

delivered the opinion of the Court.

This case involves a priority dispute between Dovenmuehle, Inc., beneficiary of a deed of trust, and several mechanics’ lien claimants. The El Paso County District Court held the interests of all lien claimants superior to the interest of the trust deed beneficiary and entered judgment with interest in favor of the lien claimants. We affirm the judgment decreeing the priority of the various interests but reverse the district court’s award of interest.

Pinon Springs Condominiums, Inc., the project owner, hired Design Group Architects in August 1972 to prepare plans and specifications for the proposed construction project. Final working drawings were completed on March 5, 1974, although Design Group worked through August 1974.

On February 11, 1974, the general contractor for the project, Urban Development & Construction Corporation, orally contracted with Gerald J. Weiss for surveying services. Weiss began work on February 14, preparing a certified boundary survey. The perimeter lot boundaries were established and staked on February 18. The building corners were staked on March 22, 1974.

Having recieved approval of its plans, Pinon Springs executed a deed of trust in favor of Dovenmuehle, Inc., as security for the construction loan from Dovenmuehle. The deed was executed and recorded on March 15, 1974.

On March 20, 1974, the construction agreement between Pinon Springs, the owner, and Urban Development & Construction Corporation, as general contractor for the project, was reduced to writing. This contract was not recorded until April 9, 1974.

Work on the project was discontinued on August 7, 1974. To that date, Dovenmuehle had advanced $2 million in funds. El Paso County Lumber Company and Continental Drywall, Inc., two lien claimants, recorded their lien statements on August 21, 1974. Both lien statements were served on Pinon Springs on August 23. On that same day, Weather Engineering and Manufacturing, Inc., another lien claimant, brought a foreclosure action against Pinon Springs, Urban Development, Dovenmuehle, and the other lien claimants. With Pinon Springs in default on its loan obligations, Dovenmuehle foreclosed its deed of trust and acquired title to the property by public trustee’s deed dated February 7, 1975.

In response to motions for summary judgment filed by several parties, the court on September 16, 1975, entered an “Order Granting Partial Summary Judgment.” The court held that the survey by Weiss on *499 February 18, 1975, constituted commencement of the work and set that day as the priority date to which all valid mechanics’ liens related back. Since Dovenmuehle recorded its deed of trust after that date, its interest was decreed to be junior to that of the lien claimants.

On October 22, 1975, the court entered its order and judgment in favor of all lien claimants except El Paso County Lumber and Continental Drywall. The court took under advisement the question of whether these two claimants had perfected their liens. The other claimants were awarded interest on their judgments, as follows: 6% from the date their accounts came due through June 30, 1975; 8% from July 1, 1975, to the date of the decree; and 12% thereafter. Finally, the court rejected Douvenmuehle’s challenge to the constitutionality of the mechanics’ lien statutes.

On November 7, 1975, judgment was entered in favor of El Paso County Lumber and Continental Drywall. The court ruled that as a result of the failure of Pinon Springs and Urban Development to execute and file a written contract prior to the date of commencement of work by Weiss on February 18, 1974, El Paso County Lumber and Continental Drywall were deemed to be principle contractors, relieving them of the requirement to serve notice of their liens on the project owner at or before filing thereof.

Dovenmuehle appeals the decision of the district court. Dovenmuehle contends (1) the district court erred in ruling that the interests of the mechanics’ lien claimants were superior to its own interest under its deed of trust; (2) the court erred in ruling that El Paso County Lumber and Continental Drywall had perfected their liens; (3) Colorado’s mechanics’ lien statutes violate due process; and (4) the court erred in its interest awards.

I.

Section 38-22-106(1), C.R.S. 1973, provides:

“All liens established by virtue of this article shall relate back to the time of the commencement of work under the contract between the owner and the first contractor, or, if said contract is not in writing, then such liens shall relate back to and take effect as of the time of the commencement of the work upon the structure or improvement * * *.”

Dovenmuehle argues that the mechanics’ liens cannot relate back to February 18, 1974, because Weiss’ survey and staking on that date did not constitute “commencement of the work upon the structure or improvement” under the statute quoted above.

This contention was recently answered contrary to appellant’s position in Bankers Trust Company v. El Paso Pre-Cast Co., 192 Colo. 468, 560 P.2d 457. There, we held the preliminary work of an architect or engineer [surveyor] does constitute “commencement of the work upon the structure or improvement.” Since Dovenmuehle’s deed of trust was recorded March 15, 1974, the court correctly found the lien claimants’ interests senior to Dovenmuehle’s interest.

*500 II.

Next, Dovenmuehle claims that El Paso County Lumber and Continental Drywall failed to perfect their liens. Specifically, Dovenmuehle contends that these claimants failed to comply with section 38-22-109(3), C.R.S. 1973, 1 which provides:

“In order to preserve a lien for work performed or materials furnished by a subcontractor, there must be served upon the owner or reputed owner of the property or his agent, at or before the time of filing with the county clerk and recorder the statement provided for in this section, a copy of such statement * *

It is undisputed that El Paso County Lumber and Continental Drywall did not serve Pinon Springs with lien statements until after the statements had been filed. The issue, therefore, is whether these two lien claimants were subcontractors, to whom this statute applies.

The district court ruled that they were not. The court first looked to section 38-22-108(1), C.R.S. 1973, which defines a principal contractor as “[e]very person given a lien by this article whose contract, either express or implied, is with the owner or reputed owner or his agent or other representative * * *.”

Next, the court applied section 38-22-101(3), which requires that the contract (when the amount thereunder exceeds five hundred dollars) between the owner and a contractor be filed by the owner in the office of the county clerk and recorder before the work is commenced under the contract. That section further provides that if the contract is not so filed the labor and materials furnished by all persons shall be deemed to have been furnished at the personal instance of the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weize Co. v. Colorado Regional Construction, Inc.
251 P.3d 489 (Colorado Court of Appeals, 2010)
Merrick & Co. v. Estate of Verzuh
987 P.2d 950 (Colorado Court of Appeals, 1999)
KETCHUM, KONKEL v. Heritage Mt.
784 P.2d 1217 (Court of Appeals of Utah, 1989)
Grasseschi v. Smiley
776 P.2d 1136 (Colorado Court of Appeals, 1989)
Alfred Brown Co. v. Johnson-Gibbons & Reed Western Paving-Kemper
695 P.2d 746 (Colorado Court of Appeals, 1984)
Seracuse Lawler & Partners, Inc. v. Cooper Mountain
654 P.2d 1328 (Colorado Court of Appeals, 1982)
Thirteenth Street Corp. v. A-1 Plumbing & Heating Co.
640 P.2d 1130 (Supreme Court of Colorado, 1982)
State, Motor Vehicle Div. v. Dayhoff
609 P.2d 119 (Supreme Court of Colorado, 1980)
A-1 Plumbing & Heating Co. v. Thirteenth Street Corp.
616 P.2d 141 (Colorado Court of Appeals, 1980)
Daniel v. MJ Development, Inc.
603 P.2d 947 (Colorado Court of Appeals, 1979)
Ciancio v. Serafini
574 P.2d 876 (Colorado Court of Appeals, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
563 P.2d 346, 192 Colo. 495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weather-engineering-manufacturing-inc-v-pinon-springs-condominiums-colo-1977.