OPINION
RABINOWITZ, Justice.
This appeal arises from a dispute over the validity of a mechanic’s lien filed by Tork-ko/Korman/Engineers (TKE) against an undeveloped parcel of land in Anchorage leased by Penland Ventures (Penland) from the State of Alaska. The superior court, ruling on the validity of the lien during foreclosure proceedings, held that TKE’s lien was untimely and therefore a nullity. Final judgment was entered in favor of Penland and this appeal followed. We affirm, but on an alternative ground.
I.
In July 1971, Robert C. Penney executed on behalf of Penland, Inc. a lease with the State of Alaska for a 162-acre parcel of land in northeast Anchorage. The lease stipulated that Penland, Inc. would develop the property “in whole or in part” as a Planned Unit Development (PUD). A PUD plan for the property was adopted.
Penland, Inc. subsequently assigned its interest to Penland Ventures (Penland).
In 1973, Penland successfully sought several amendments to the PUD plan for the entire 162-acre area. One of Penland’s requests was that the density restrictions on tracts B-2 through B-5 (which comprise the 11.3 acres at issue here) be revised to permit townhouse condominiums as well as single-family residences. The Greater Anchorage Area Borough (GAAB) Planning and Zoning Commission subsequently gave “concept approval” to a density of fifteen units per acre on tracts B-2 through B-5. Final approval for the townhouse units was requested and received.
In April 1974, Penland granted to Polar Bear Builders, Inc. (Polar Bear) an option to sublease tracts B-2 through B-5. The contract contemplated that Polar Bear would perform actual construction on the property in accordance with the PUD plan.
During March 1974, Robert Sowash, president of Polar Bear, hired TKE to prepare the plans for the condominium project. TKE employed the California architectural firm of Kamnitzer, Marks, Lappin and Vreeland, Inc. (KMLV) to assist in this work. TKE and KMLV prepared the drawings and plans necessary for obtaining “final approval” from the GAAB Planning and Zoning Commission for a PUD on tracts B-2 through B-5. In late May of 1974 final approval was granted.
On June 15, 1974, TKE and Polar Bear entered into a written contract delineating their respective responsibilities during execution of the condominium project. Specific services were expressly included, and others excluded, from the scope of TKE’s responsibilities. The project was divided into four phases, and fees were allocated accordingly, although the contract specifically stated that “[TKE’s] fee is based upon the continuous involvement in the total project.” Phase I fees were set at $58,500 and were due on September 1,1974, regardless of whether Polar Bear had received a construction draw by that time.
After preparing the preliminary drawings and plans that enabled Polar Bear to obtain final approval for the project from the GAAB Planning and Zoning Commission, TKE and its subcontractors completed by July 1974 the detailed drawings and plans necessary for obtaining building permits and beginning construction.
Construction never began. In August 1974, TKE learned that the anticipated source for construction financing had declined to underwrite the project. TKE then wrote to Polar Bear concerning various possible means of securing payment of the Phase I fees. No agreement was reached. Thus, on September 1,1974, TKE sent Polar Bear a statement of fees earned and due as of that date. The outstanding balance of $58,517.29 was for work done prior to September 1, 1974.
Polar Bear did not pay the bill. Charles Torkko of TKE moved the TKE offices to his home and took a full time position with another firm.
At Mr. Sowash’s request, TKE and KMLV began canvassing developers for financing. In early 1975, Torkko personally discussed financing of the project with Mike Barry, a Penland general partner. On March 14,1975, Torkko agreed to defer Phase I fees “until the new Owner/Developer/Contractor is able to make this lump sum payment” but no later than August 31, 1975. Throughout early 1975, Torkko devoted an average of four to five hours per week to meetings, conferences, and correspondence with potential sources
of financing for the project.
All efforts to salvage the project failed. No site preparation, excavation or other physical preparatory work was ever started. Design of Phase II was never begun. Thus, in February 1975, Penland sued Polar Bear for breach of the first parcel sublease agreement. On July 31,1975, the sublease agreement was formally terminated.
KMLV filed and recorded a claim of lien against tracts B-2 through B-5 on April 25, 1975, claiming $33,597.72 due for labor and materials expended on the project.
TKE filed its claim of lien against the property on May 2, 1975. The claim stated that $58,517.29 was due TKE, an amount equal to the sum billed on September 1, 1974 which included the monies due KMLV.
KMLV filed suit to foreclose its lien, naming
inter alia
TKE and Penland as defendants. TKE answered and cross-claimed for foreclosure of its lien. TKE at this time also brought a third-party complaint against Polar Bear. KMLV voluntarily dismissed its complaint, and the case proceeded on the cross-claim and third-party complaint. On the eve of trial, Polar Bear confessed judgment in favor of TKE in the principal amount of $24,919.57 and the case went to trial with Penland as the sole defendant.
The superior court held that the ninety-day statutory period for filing a lien commenced to run on September 1, 1974, and that efforts expended by TKE after that date were beyond the scope of the contract with Polar Bear and therefore gratuitous. The superior court further concluded that the lien was a nullity because it was filed more than ninety days after TKE’s contractual obligations were fulfilled.
II.
On appeal, Penland contends that TKE’s lien should be invalidated because no work was commenced on the project at the 11.3-acre site.
Penland argues that the language of former AS 34.35.050
and the
“majority rule” in other jurisdictions support its assertion that a mechanic’s lien will extend only to land upon which a building is constructed or other visible improvement effected. We find Penland’s argument persuasive and affirm the superior court’s judgment on this ground.
AS 34.35.050 provided, in pertinent part, that an engineer furnishing design services preliminary to site preparation or the construction of a building has “a lien on it for work done.”
See supra
n. 7. The parties join issue over the meaning of the word “it.” Penland argues that “it” refers only to the visible product of such labor and that no lien may arise before “it” materializes.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
RABINOWITZ, Justice.
This appeal arises from a dispute over the validity of a mechanic’s lien filed by Tork-ko/Korman/Engineers (TKE) against an undeveloped parcel of land in Anchorage leased by Penland Ventures (Penland) from the State of Alaska. The superior court, ruling on the validity of the lien during foreclosure proceedings, held that TKE’s lien was untimely and therefore a nullity. Final judgment was entered in favor of Penland and this appeal followed. We affirm, but on an alternative ground.
I.
In July 1971, Robert C. Penney executed on behalf of Penland, Inc. a lease with the State of Alaska for a 162-acre parcel of land in northeast Anchorage. The lease stipulated that Penland, Inc. would develop the property “in whole or in part” as a Planned Unit Development (PUD). A PUD plan for the property was adopted.
Penland, Inc. subsequently assigned its interest to Penland Ventures (Penland).
In 1973, Penland successfully sought several amendments to the PUD plan for the entire 162-acre area. One of Penland’s requests was that the density restrictions on tracts B-2 through B-5 (which comprise the 11.3 acres at issue here) be revised to permit townhouse condominiums as well as single-family residences. The Greater Anchorage Area Borough (GAAB) Planning and Zoning Commission subsequently gave “concept approval” to a density of fifteen units per acre on tracts B-2 through B-5. Final approval for the townhouse units was requested and received.
In April 1974, Penland granted to Polar Bear Builders, Inc. (Polar Bear) an option to sublease tracts B-2 through B-5. The contract contemplated that Polar Bear would perform actual construction on the property in accordance with the PUD plan.
During March 1974, Robert Sowash, president of Polar Bear, hired TKE to prepare the plans for the condominium project. TKE employed the California architectural firm of Kamnitzer, Marks, Lappin and Vreeland, Inc. (KMLV) to assist in this work. TKE and KMLV prepared the drawings and plans necessary for obtaining “final approval” from the GAAB Planning and Zoning Commission for a PUD on tracts B-2 through B-5. In late May of 1974 final approval was granted.
On June 15, 1974, TKE and Polar Bear entered into a written contract delineating their respective responsibilities during execution of the condominium project. Specific services were expressly included, and others excluded, from the scope of TKE’s responsibilities. The project was divided into four phases, and fees were allocated accordingly, although the contract specifically stated that “[TKE’s] fee is based upon the continuous involvement in the total project.” Phase I fees were set at $58,500 and were due on September 1,1974, regardless of whether Polar Bear had received a construction draw by that time.
After preparing the preliminary drawings and plans that enabled Polar Bear to obtain final approval for the project from the GAAB Planning and Zoning Commission, TKE and its subcontractors completed by July 1974 the detailed drawings and plans necessary for obtaining building permits and beginning construction.
Construction never began. In August 1974, TKE learned that the anticipated source for construction financing had declined to underwrite the project. TKE then wrote to Polar Bear concerning various possible means of securing payment of the Phase I fees. No agreement was reached. Thus, on September 1,1974, TKE sent Polar Bear a statement of fees earned and due as of that date. The outstanding balance of $58,517.29 was for work done prior to September 1, 1974.
Polar Bear did not pay the bill. Charles Torkko of TKE moved the TKE offices to his home and took a full time position with another firm.
At Mr. Sowash’s request, TKE and KMLV began canvassing developers for financing. In early 1975, Torkko personally discussed financing of the project with Mike Barry, a Penland general partner. On March 14,1975, Torkko agreed to defer Phase I fees “until the new Owner/Developer/Contractor is able to make this lump sum payment” but no later than August 31, 1975. Throughout early 1975, Torkko devoted an average of four to five hours per week to meetings, conferences, and correspondence with potential sources
of financing for the project.
All efforts to salvage the project failed. No site preparation, excavation or other physical preparatory work was ever started. Design of Phase II was never begun. Thus, in February 1975, Penland sued Polar Bear for breach of the first parcel sublease agreement. On July 31,1975, the sublease agreement was formally terminated.
KMLV filed and recorded a claim of lien against tracts B-2 through B-5 on April 25, 1975, claiming $33,597.72 due for labor and materials expended on the project.
TKE filed its claim of lien against the property on May 2, 1975. The claim stated that $58,517.29 was due TKE, an amount equal to the sum billed on September 1, 1974 which included the monies due KMLV.
KMLV filed suit to foreclose its lien, naming
inter alia
TKE and Penland as defendants. TKE answered and cross-claimed for foreclosure of its lien. TKE at this time also brought a third-party complaint against Polar Bear. KMLV voluntarily dismissed its complaint, and the case proceeded on the cross-claim and third-party complaint. On the eve of trial, Polar Bear confessed judgment in favor of TKE in the principal amount of $24,919.57 and the case went to trial with Penland as the sole defendant.
The superior court held that the ninety-day statutory period for filing a lien commenced to run on September 1, 1974, and that efforts expended by TKE after that date were beyond the scope of the contract with Polar Bear and therefore gratuitous. The superior court further concluded that the lien was a nullity because it was filed more than ninety days after TKE’s contractual obligations were fulfilled.
II.
On appeal, Penland contends that TKE’s lien should be invalidated because no work was commenced on the project at the 11.3-acre site.
Penland argues that the language of former AS 34.35.050
and the
“majority rule” in other jurisdictions support its assertion that a mechanic’s lien will extend only to land upon which a building is constructed or other visible improvement effected. We find Penland’s argument persuasive and affirm the superior court’s judgment on this ground.
AS 34.35.050 provided, in pertinent part, that an engineer furnishing design services preliminary to site preparation or the construction of a building has “a lien on it for work done.”
See supra
n. 7. The parties join issue over the meaning of the word “it.” Penland argues that “it” refers only to the visible product of such labor and that no lien may arise before “it” materializes. TKE contends that “it” refers to the raw land as well as any improvements made upon that land. TKE argues that since the statute permits liens to be filed for engineering services preliminary to land clearing, grading, excavating, landscaping or the installation of water and sewer lines, “it” must refer to the ground on which the activity takes place. Furthermore, Torkko contends that since buildings become realty by virtue of the doctrine of annexation of fixtures, Penland’s attempt to argue that “improvements” rather than land are liena-ble is legally untenable.
We find TKE’s position unpersuasive. The plain meaning of the statute supports Penland’s interpretation. The statute refers to construction of a building or structure or superstructure, and only then discusses the “clearing, grading, draining, excavating or landscaping of the ground upon which
it
is constructed.” The word “it” clearly refers to a building, structure or superstructure. The statute then notes that the engineer “has a lien on
it.”
“It” again refers to improvements that have been constructed upon the ground. All improvements contained in the statute are “visible” improvements. Since statutory liens are derived entirely from the legislative acts creating them,
Goebel v. National Exchangors, Inc.,
88 Wis.2d 596, 277 N.W.2d 755, 760 (1979), our interpretation of AS 34.35.050 must comport with the express language of that provision.
Since TKE’s efforts did not result in the visible improvements to the land contemplated un
der AS 34.35.050, there cannot be a lien upon it.
Authority from jurisdictions governed by lien statutes similar to former AS 34.35.050 supports our conclusion .that physical construction must begin on property before architects and engineers aiding in the design of improvements are permitted to file liens.
One rationale for such an interpretation of lien statutes is apparent from our decision in
Frontier Rock & Sand v. Heritage Ventures,
607 P.2d 364 (Alaska 1980):
The philosophy [of lien statutes] is that a materialman or workman may reach the property which he has benefited to satisfy his claim for the benefit even when there is no direct contractual relationship between him and the owner of the property, and regardless of who the owner might be.
Id.
at 367 (footnotes omitted). Under this view a mechanic’s lien may attach to a property only after the services giving rise to the right result in a tangible improvement. Thus, the addition of value to land is the precondition to an attachment of a lien. Secondly, as the Iowa Supreme Court observed in
Gollehon,
268 N.W.2d at 202 n. 13, a requirement that the land be visibly improved protects the rights of third party purchasers who are thereby put on notice that lienable claims may exist. 268 N.W.2d at 202.
It is likely that the legislature was aware of these interpretations of similar statutes when it amended former AS 34.35.-050 to allow explicitly for liens in this situation.
An amendment to an unambiguous
statute
is generally presumed to indicate a substantive change in the law,
City of Anchorage v. Thomas,
624 P.2d 271, 273 (Alaska 1981). We therefore conclude that the legislature intended to confer additional rights upon architects and engineers when it amended AS 34.35.050 to allow liens for work done in the preparation of plans “whether or not [they were] actually implemented.” AS 34.35.050(5). Thus, we interpret the prior version of the statute to prohibit the creation of a valid lien prior to the commencement of work on the site and the effectuation of visible improvements to the property.
The superior court’s judgment is AFFIRMED.
MOORE, J., not participating.