Frontier Rock & Sand, Inc. v. Heritage Ventures, Inc.

607 P.2d 364, 1980 Alas. LEXIS 523
CourtAlaska Supreme Court
DecidedFebruary 29, 1980
Docket4000
StatusPublished
Cited by10 cases

This text of 607 P.2d 364 (Frontier Rock & Sand, Inc. v. Heritage Ventures, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frontier Rock & Sand, Inc. v. Heritage Ventures, Inc., 607 P.2d 364, 1980 Alas. LEXIS 523 (Ala. 1980).

Opinions

OPINION

MATTHEWS, Justice.

Frontier Rock and Sand, Inc. recorded a lien against Lot 1, Block 60, Dead Horse Airport for labor and materials furnished to that property at the request of A & P Griswold Expediters, Inc. Griswold held a lease on the property from the State of Alaska when the work was done, but the state had terminated the lease before the lien was recorded. The question in this case is whether Frontier can recover the value of its work from the state, or from the subsequent lessees of the same property from the state.

There is little dispute over facts. The State of Alaska, Department of Public Works, Division of Aviation, leased property at the Dead Horse Airport to Griswold. The lease agreement required that Griswold construct employee living quarters and a freight warehouse on the site. Frontier Rock and Sand was hired by Griswold to provide the gravel and excavation work required. It completed its work on or before August 27, 1975, but Griswold failed to pay as promised.

Griswold had also failed to comply with a lease requirement that it obtain liability insurance to cover the site. In five letters sent over a four month period, the state notified Griswold of this failure and warned that it would result in cancellation of the lease. Finally, and with ample notice to Griswold, the state terminated the lease as of January 19, 1976. On April 5, 1976, Frontier recorded its claim of lien pursuant to AS 34.35.070.1 On June 16, 1976, the [366]*366state entered into a second lease for the property with Coor and Heritage Ventures.

Frontier filed suit to recover against the state, Coor,. and Heritage Ventures. After Frontier’s motion for partial summary judgment on the issue of liability was denied, the parties stipulated to judgment in favor of the defendants and that Frontier would be entitled to damages of $53,136 if it prevailed on appeal. The superior court approved this stipulation and this appeal followed.

Three basic issues have been raised. Frontier maintains that it had a valid lien against the Griswold leasehold. It contends that this lien was not extinguished by the state’s termination of the Griswold lease, and that the new lease is therefore subject to the lien. Alternatively Frontier argues that cancellation of Griswold’s lease without notification to Frontier deprived it of the lien and therefore of a property right without due process of law. And finally Frontier argues that it should be able to recover on a theory of quasi-contract to prevent unjust enrichment of the state.

The defendants’ first contention is that Frontier filed its lien too late. Resolution of this question requires a discussion of the terms of AS 34.35.070 as it existed in 1975 and 1976. Frontier’s lien was filed more than ninety days after it completed its contract and therefore was. too late under part (b) of the statute. However, no notice of completion was recorded by the lessee, who is the “owner” for .the purpose of subsection (d).2 Frontier argues that because of this its lien was timely, since its lien claim was filed “no later than 90 days after the notice of completion has been recorded” as prescribed by part (d).

Parts (d) through (f) of AS 34.35.070 were added to our lien law by chapter 89 of the 1974 session laws. Frontier contends that the language of subsection (d) augments and expands the time period provided in subsection (b) and that, if the provisions are contradictory, subsection (d) impliedly repealed inconsistent portions of subsection (b). The appellees, on the other hand, contend that the only consistent reading of subsections (b) and (d) is that (d) only applies where a notice of completion has been recorded within ten days after completion of an improvement.

We agree with the appellees’ interpretation. Reading subsection (d) as Frontier suggests would result essentially in an unlimited time, or a time limited only by statutes of limitations or laches, within which a materialman’s or mechanic’s lien might be filed where the owner has neglected to record a notice of completion. Such a result would clearly be inconsistent with the strict deadlines which the legislature has seen fit to observe elsewhere in the lien foreclosure statute. Thus, in addition to the ninety day deadline provided by AS 34.35.070(b) for filing a lien, a lien, once it is filed, is not binding for more than six months unless suit is commenced Or unless one six month extension is recorded within the initial six month period.3 Similarly, an owner is free [367]*367to pay a prime contractor his full contract price after ninety days has elapsed from the completion of the improvement without risking the burden of double payment if no liens are by then filed.4 Moreover, the general philosophy of lien statutes is consistent with a system of distinct deadlines for lien filings and inconsistent with open-ended ones. That philosophy is that a material-man or workman may reach the property which he has benefited to satisfy his claim for the benefit even when there is no direct contractual relationship between him and the owner of the property,5 and regardless of who the owner might be.6 However, because of the extensive uncertainty to titles that this broad remedy entails it has been thought necessary to construe time limitations for its exercise rather narrowly.7

Further, under Frontier’s interpretation, subsection (d) would have to be read as applying a ninety day deadline to an event which might never occur. This strikes us as an unnatural use of the language. Beyond that, we observe that part (d) requires the owner in mandatory language to record a notice of completion within ten days after completion. Part (f) provides for what shall happen when the owner fails to do this. He is placed in the “position of guarantor regarding another person who suffers damages which are proximately caused” by his failure.8 Placing personal liability on the owner who fails to file a notice of completion does give the lienor who does not have a contractual relationship with the owner an added remedy, and it does so without clouding titles and thus potentially [368]*368working prejudice to the rights of innocent third parties. This is the only consequence which the legislature has specified as flowing from an owner’s failure to record a notice of completion within ten days, and we think it was the only one that was intended.

We observe finally that the legislature amended subsection (d) in 1977 to provide as follows:

The owner of land which may be subject to a lien created under §§ 50-120 of this chapter may, within 10 days after completion of a building or other improvement, record a notice of completion of the building or other improvement. In order to claim the benefit of §§ 50-120 of this chapter, every lien claimant shall record his claim of lien no later than 90 days after the notice of completion has been recorded or within 90 days of the last occurrence of any event set out in (b) of this section, whichever is earlier. (Emphasis added.)

In 1978 subsection (d), along with subsection (e), was repealed entirely. While it is always debatable whether a legislative change is a clarification or a change in substantive law, see Laborers and Hod Carriers Local 341 v. Groothuis,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

3-D & Co. v. Tew's Excavating, Inc.
258 P.3d 819 (Alaska Supreme Court, 2011)
D.H. Blattner & Sons, Inc. v. N.M. Rothschild & Sons, Ltd.
55 P.3d 37 (Alaska Supreme Court, 2002)
Nystrom v. Buckhorn Homes, Inc.
778 P.2d 1115 (Alaska Supreme Court, 1989)
Sparks v. Gustafson
750 P.2d 338 (Alaska Supreme Court, 1988)
Torkko/Korman/Engineers v. Penland Ventures
673 P.2d 769 (Alaska Supreme Court, 1983)
Industrial Power & Lighting Corp. v. Western Modular Corp.
623 P.2d 291 (Alaska Supreme Court, 1981)
Brooks v. R & M CONSULTANTS, INC.
613 P.2d 268 (Alaska Supreme Court, 1980)
Frontier Rock & Sand, Inc. v. Heritage Ventures, Inc.
607 P.2d 364 (Alaska Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
607 P.2d 364, 1980 Alas. LEXIS 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frontier-rock-sand-inc-v-heritage-ventures-inc-alaska-1980.