Shelton Engineering Contractors, Ltd. v. Hawaiian Pacific Industries, Inc.

456 P.2d 222, 51 Haw. 242, 1969 Haw. LEXIS 109
CourtHawaii Supreme Court
DecidedJune 13, 1969
Docket4690, 4691
StatusPublished
Cited by18 cases

This text of 456 P.2d 222 (Shelton Engineering Contractors, Ltd. v. Hawaiian Pacific Industries, Inc.) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shelton Engineering Contractors, Ltd. v. Hawaiian Pacific Industries, Inc., 456 P.2d 222, 51 Haw. 242, 1969 Haw. LEXIS 109 (haw 1969).

Opinion

*243 OPINION OF THE COURT BY

RICHARDSON, C.J.

Shelton Engineering Contractors, Ltd., subcontractor, filed an assumpsit action against Mark Construction, Inc., the prime contractor, and Bank of Hawaii, garnishee, on November 4, 1966. Five months later, the subcontractor filed a notice of mechanic’s and materialman’s lien affecting forty-four lots in the Enchanted Hill Estates, Unit VII, and subsequently filed a suit to foreclose the lien against Hawaiian Pacific Industries, Inc., the owner. Although Mark Construction had no alleged interest in the land as an owner, it was made a party to the action as prime contractor. The single underlying debt was alleged to be $14,500 in the assumpsit action and $14,714.34 in the suit to foreclose the mechanic’s lien.

The following facts are crucial to the appeals in both cases:

1. Pursuant to a stipulation in the assumpsit action by Shelton Engineering Contractors, Ltd. and Mark Construction, Inc., the trial court issued on November 14, 1966, an order directing the garnishee to withhold the sum of $18,000 and authorizing the release of the balance of the fund.

2. The prime contractor filed a counterclaim in the assumpsit action alleging that the subcontractor had (a) failed to complete the contract thereby owing the prime contractor an unascertainable amount incurred in completing the job; (b) committed negligence on the job for which the prime contractor would have to expend some *244 money; and (e) failed to complete the job in the stated time and theréfore was liable for liquidated damages.

3. On June 22, 1967, the prime contractor filed a motion for attachment with affidavit stating the subcontractor was indebted to the prime contractor in the sum of $20,000 over and above all just credits and offsets, and filed a bond in the amount of $40,000.

The writ of attachment was issued on June 22, 1967.

4. On June 29, 1967, the subcontractor filed a motion to strike the affidavit of attachment and to vacate and set aside the attachment asserting that (a) the affidavit of George R. Ariyoshi, Esq., was invalid because it was in violation of Rule 11 of the Hawaii Rules of Civil Procedure; (b) exempt property had been wrongfully attached; (c) the value of the attached property was far in excess of the claim by the prime contractor; and (d) the prime contractor’s claim was unliquidated and sounded in tort so that attachment should not have been available to him under R.L.H. 1955, § 233-2 (HRS § 651-2).

The court denied this motion on July 19, 1967.

5. The sheriff executed the writ of attachment on July 25, 1967.

6. On June 14, 1967, in the mechanic’s lien proceeding, the prime contractor deposited $29,428.68 to discharge the lien on the property pursuant to R.L.H. 1955, § 193-43.1 (1965 Supp.) (HRS § 507-45), and by order of the court, the lien was discharged.

7. On June 28, 1967, Hawaiiafi Pacific Industries, the owner, moved to dismiss the complaint against it inasmuch as the lien had been discharged.

8. On the same date, the prime contractor moved to dismiss the foreclosure of lien complaint against it on the ground that since an assumpsit action supported by adequate garnished funds was pending, the foreclosure action should be abated and the cash deposit returned.

*245 9. The subcontractor then filed a memorandum in opposition to the motions to dismiss the complaint stating (a) that the motions were defective because of failure to comply with the Hawaii Rules of Civil Procedure in that it was unsupported by a memorandum of authorities; that it failed to comply with the ten-day notice requirement for summary judgments under Rule 56; and that the prime contractor and owner had not marshalled a record to show there was no genuine issue as to material fact; (b) that the deposit of money did not destroy the subcontractor’s right to action in the foreclosure suit.

10. The court granted the motions to dismiss on July 10,1967, and directed that the bond be substituted for the amount garnished.

11. The prime contractor and owner filed a memorandum in support of the motions to dismiss on July 12,1967.

12. Pursuant to its decision in the suit to enforce the mechanic’s lien, the court ordered release of the $18,000 previously garnished in the assumpsit action.

The subcontractor appeals from (1) the order granting the motions to dismiss the complaint in the action to enforce the mechanic’s lien (#10); (2) the order substituting the deposit bond for the garnishment fund and the subsequent release of the amount held by the garnishee (#10 and #12), and (3) the order denying his motion to strike the attachment affidavit and to vacate the writ of attachment (#4).

I. The Order Dismissing the Complaint in the Action to Enforce the Mechanic’s Lien.

A. The motion to dismiss as to Hawaiian Pacific Industries, Inc., the owner.

The affidavit accompanying this motion indicates that it was intended to be a motion under H.R.C.P., Rule 12 (b) because the movant was asserting that since the lien had been discharged by the prime contractor, the owner had *246 no interest to defend and therefore no relief conld he granted against it on any claim.

The parties do not dispute that the motion, accompanied by the affidavit which was not excluded by the court, was to be disposed of under H.E.C.P., Eule 56. That rule states in part that “the motion shall be served at least 10 days before the time fixed for the hearing. The adverse party prior to the day of hearing may serve opposing affidavits. The judgment sought shall be rendered forthwith if the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.”

The subcontractor, appellant herein, complains that the motion should be stricken because it was served on June 28, 1967, only five days before the date set for the hearing. Although movant did not comply with the literal requirement of the rule, we think that he complied substantially with the notice requirement of the rule as expressed in Clarke v. Civil Service Commission, 50 Haw. 169, 434 P.2d 312 (1967). This court invalidated summary judgment in that case because a time for hearing had not been fixed, the adverse party had no notice of a hearing, and no hearing had in fact been held. Appellant herein had notice of a hearing and had the opportunity to be heard; he has not demonstrated he has been harmed by not having a full ten days of notice. We are reluctant to strike a motion for that reason alone even though we sympathize with the fact that he was under great pressure to submit opposing memorandum.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ito v. Investors Equity Life Holding Company.
346 P.3d 118 (Hawaii Supreme Court, 2015)
Bank of Hawaii v. Shinn
200 P.3d 370 (Hawaii Supreme Court, 2008)
County of Hawai'i v. C & J Coupe Family Ltd. Partnership
198 P.3d 615 (Hawaii Supreme Court, 2008)
Querubin v. Thronas
109 P.3d 689 (Hawaii Supreme Court, 2005)
Matsushita v. Container Home Supply, Inc.
726 P.2d 273 (Hawaii Intermediate Court of Appeals, 1986)
Kau v. City and County of Honolulu
722 P.2d 1043 (Hawaii Intermediate Court of Appeals, 1986)
Lussier v. Mau-Van Development, Inc. I
667 P.2d 804 (Hawaii Intermediate Court of Appeals, 1983)
Guaschino v. Eucalyptus, Inc.
658 P.2d 888 (Hawaii Intermediate Court of Appeals, 1983)
Frontier Rock & Sand, Inc. v. Heritage Ventures, Inc.
607 P.2d 364 (Alaska Supreme Court, 1980)
Reliable Collection Agency, Ltd. v. Aquarius Industries, Inc.
535 P.2d 129 (Hawaii Supreme Court, 1975)
Jensen v. Pratt
491 P.2d 547 (Hawaii Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
456 P.2d 222, 51 Haw. 242, 1969 Haw. LEXIS 109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shelton-engineering-contractors-ltd-v-hawaiian-pacific-industries-inc-haw-1969.