Industrial Power & Lighting Corp. v. Western Modular Corp.

623 P.2d 291, 1981 Alas. LEXIS 415
CourtAlaska Supreme Court
DecidedJanuary 9, 1981
Docket4163, 4176
StatusPublished
Cited by20 cases

This text of 623 P.2d 291 (Industrial Power & Lighting Corp. v. Western Modular Corp.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Power & Lighting Corp. v. Western Modular Corp., 623 P.2d 291, 1981 Alas. LEXIS 415 (Ala. 1981).

Opinions

OPINION

MATTHEWS, Justice.

On or about August 1, 1975, Western Modular Corporation and Industrial Power & Lighting Company made a contract under which Western Modular was to manufacture and sell twenty modular homes to Industrial Power. The total purchase price was $517,270.00. Delivery was to take [293]*293place on or before October 1,1975, and was to be accomplished by presentation to Industrial Power of a final inspection and approval notice issued by the State of Washington, Department of Labor and Industries Factory Built Housing and Commercial Structures Section. Under the contract Western Modular was responsible for the transportation of the modular homes from its factory in Kent, Washington to the dock at Seattle. Industrial Power had the responsibility of arranging for and paying for transportation from the Seattle dock to the homes’ final destination in Fairbanks. Industrial Power was to be responsible for all on-site construction. However, Western Modular did warrant the structures to be free from substantial defects and agreed to repair any such defects for a period of one year following delivery.

All twenty of the units were delivered, but Industrial Power did not accept five of them, alleging delivery delay. Western Modular did not receive payment under the contract as scheduled and on April 19,1976, filed a lien in the total amount of $229,-551.11 against the fifteen lots in Fairbanks where the modular units which had been accepted by Industrial Power had been placed, as well as the five additional lots on which the modular units which had been rejected were to have been placed. This lawsuit soon followed.

While the suit was in its preliminary stages, the parties reached an agreement that was to resolve their dispute. Under the agreement of August 18,1976, Industrial Power acknowledged indebtedness to Western Modular in the sum of $236,198.29, subject to unresolved back charges claimed by Industrial Power in the amount of $18,-524.04. Further, Industrial Power was to pay Western Modular $25,000.00 at the time the agreement was signed, and deliver a promissory note signed by Industrial Power and co-signed by one Frank McGuire in the amount of $211,198.29 payable with interest on or before October 27, 1976. The note was to be secured by the lien claims filed by Western Modular and by a security interest in the five units that had been rejected by Industrial Power. As to the latter, Industrial Power agreed to accept delivery at Seattle for shipment to Anchorage at Industrial Power’s expense. Provision was made in the agreement for release and amendment of Western Modular’s claim of lien upon receipt of further payment.

Western Modular received some payments under the promissory note which was part of the August 1976 agreement. However, Western Modular claimed that $85,-945.22 in principal was not paid and sought this amount in an amended complaint.

In its defense to the amended complaint, Industrial Power claimed that the settlement agreement was the product of duress and is therefore unenforceable. In addition, Industrial Power claimed several other affirmative defenses including an allegation that Western Modular was an unregistered contractor that could not maintain the action. Further, Industrial Power asserted a seven-count counterclaim. The first count asserted a claim for breach of contract by delivery delay. Counts II through VII claimed disparagement of title and credit, by reason of defects in the claims of lien, and damages because of noncompliance with various provisions of the Alaska lien statutes.

Industrial Power filed a motion for a judgment on the pleadings and for partial summary judgment based on the fact that Western Modular was not registered as a contractor in the State of Alaska. The court eventually granted summary judgment on that issue and ordered Western Modular’s complaint dismissed.

Western Modular then moved for summary judgment dismissing all of Industrial Power’s counterclaims because Industrial Power was itself not a registered contractor. The court granted Western Modular’s motion, thus effecting a complete dismissal of the case. Both parties have appealed.

Chapter 18, Article I of Title 8 of the Alaska Statutes deals with the registration requirement for construction contractors. Registration is accomplished by submitting an application form to the Department of [294]*294Commerce together with a registration fee,1 a surety bond2 and evidence of public liability and property damage insurance.3 There are no competence or experience requirements, except in the case of electrical contractors.4 It is unlawful to submit a bid or to work as a contractor unless registration has been accomplished,5 and,

[n]o person acting in the capacity of a contractor may bring an action in a court of this state for the collection of compensation for the performance of work or for breach of a contract for which registration is required under this chapter without alleging and proving that he was a registered contractor at the time he contracted for the performance of the work.

AS 08.18.151. A contractor is defined as:

[A] person who, in the pursuit of an independent business, undertakes or offers to perform, or claims to have the capacity to perform, or submits a bid for a project to construct, alter, repair, move or demolish a building, highway, road, railroad, or any type of fixed structure, including excavation and site development and erection of scaffolding; a “general contractor” is a contractor whose business operations require the use of more than two distinct trades whose work the general contractor superintends; the terms “general contractor” and “builder” are synonymous; a “specialty contractor” is a contractor whose operations do not fall within the definition of “general contractor.”

AS 08.18.171(2). Section 08.18.161 enumerates fourteen exceptions to the application of Chapter 18. Those relevant to Western Modular’s appeal are (5), (6) and (8):

This chapter does not apply to:
(5) the sale or installation of finished products, materials or articles of merchandise which are not actually fabricated into and do not become a permanent, fixed part of a structure;
(6) construction, alteration, or repair of personal property;
(8) a person who only furnished materials, supplies or equipment without fabricating them into, or consuming them in the performance of, the work of the contractor;

AS 08.18.151 causes the forfeiture of an otherwise valid claim. Because of this, courts have not given similar provisions broad or liberal constructions. Latipac, Inc. v. Superior Court, 64 Cal.2d 278, 49 Cal.Rptr. 676, 678, 411 P.2d 564, 566 (1966); Walker v. Thornsberry, 97 Cal.App.3d 842, 158 Cal.Rptr. 862, 863 (1979); Jackson v. Pancake, 266 Cal.App.2d 307, 72 Cal.Rptr. 111, 113-14 (1968). We agree with those authorities and decline to give the statute an expansive reading.

We believe that the eighth clause listed in AS 08.18.161 exempts Western Modular from registration for the contract in question. The clause exists in substantially identical form in statutes in California 6 and Washington,7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daggett v. Feeney
397 P.3d 297 (Alaska Supreme Court, 2017)
Cornelison v. TIG Insurance
376 P.3d 1255 (Alaska Supreme Court, 2016)
Brandner v. Agre
80 P.3d 691 (Alaska Supreme Court, 2003)
Pepperell Trust Co. v. Mountain Heir Financial Corp.
1998 ME 46 (Supreme Judicial Court of Maine, 1998)
Hale v. Vitale
751 P.2d 488 (Alaska Supreme Court, 1988)
Stephens v. State, Department of Revenue
746 P.2d 908 (Alaska Supreme Court, 1987)
Verchinski v. Klein
732 P.2d 863 (New Mexico Supreme Court, 1987)
Hazen v. Municipality of Anchorage
718 P.2d 456 (Alaska Supreme Court, 1986)
Gross v. Bayshore Land Co.
710 P.2d 1007 (Alaska Supreme Court, 1986)
Jones v. Short
696 P.2d 665 (Alaska Supreme Court, 1985)
State for Use of Smith v. Tyonek Timber, Inc.
680 P.2d 1148 (Alaska Supreme Court, 1984)
Fomby v. Whisenhunt
680 P.2d 787 (Alaska Supreme Court, 1984)
Alaska Protection Services, Inc. v. Frontier Colorcable, Inc.
680 P.2d 1119 (Alaska Supreme Court, 1984)
Industrial Power & Lighting Corp. v. Western Modular Corp.
623 P.2d 291 (Alaska Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
623 P.2d 291, 1981 Alas. LEXIS 415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-power-lighting-corp-v-western-modular-corp-alaska-1981.