State for Use of Smith v. Tyonek Timber, Inc.

680 P.2d 1148, 39 U.C.C. Rep. Serv. (West) 108, 1984 Alas. LEXIS 289
CourtAlaska Supreme Court
DecidedApril 6, 1984
Docket7170, 7256
StatusPublished
Cited by27 cases

This text of 680 P.2d 1148 (State for Use of Smith v. Tyonek Timber, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State for Use of Smith v. Tyonek Timber, Inc., 680 P.2d 1148, 39 U.C.C. Rep. Serv. (West) 108, 1984 Alas. LEXIS 289 (Ala. 1984).

Opinion

OPINION

MOORE, Justice.

This appeal involves contract and negligence claims by appellant Fred L. Smith (Smith), a concrete subcontractor, against appellees Tyonek Timber, Inc. (Tyonek), the manufacturer and supplier of concrete, H & S Construction, Inc. (H & S), the general contractor, and its surety, Maryland Casualty Co. (Maryland) for the replacement costs of a defective concrete floor slab.

The primary issues presented on this appeal are whether the trial court erred (1) in granting a directed verdict in favor of Tyo-nek precluding recovery for economic loss based on a negligence cause of action absent physical injury or property damage; (2) in granting summary judgment in favor of H & S and Maryland dismissing Smith’s contract claims because he was an unregistered contractor in violation of AS 08.18.-011-.171; and (3) in holding that the Little Miller Act, AS 36.25.020, did not authorize an independent right of recovery for an unregistered contractor because AS 08.18.-151 barred such an action.

I. FACTUAL AND PROCEDURAL BACKGROUND

On March 8, 1976, the Kenai Peninsula Borough contracted with H & S for the construction of an addition to the Bob Bartlett School in Tyonek, Alaska. H & S, in turn, awarded the subcontract for completion of the concrete and masonry work on the project to Smith.

The Tyonek school project was a public works project owned by the Kenai Peninsula Borough. Accordingly, H & S secured performance and payment bonds pursuant to AS 36.25.010, the Little Miller Act. Maryland was the named surety.

About the time of submission of his bid to H & S (February 1976), Smith requested that Homestate Insurance, an insurance and bonding agency in Anchorage, Alaska, “aid me in getting registered as a licensed and bonded contractor pursuant to AS 08.-18.011 et seq.” Smith stated that he proceeded to enter into the subcontract with H & S in reliance upon Homestate’s indication to him that it would secure his certificate of registration.

Smith began work on the Tyonek project in late April, 1976. He stated that in September 1976, near the completion of the Tyonek project, Homestate “indicated that for some unknown reason the application had simply been overlooked and had not gone forward as I had earlier requested.” Smith did not become a licensed contractor until November 1, 1976.

In March 1976, H & S tentatively decided to try to procure pre-mixed concrete for Smith’s work from Tyonek Timber, Inc. In early May, Tyonek quoted a price of $180 per yard, which was subsequently lowered to $165 per yard. Smith’s original overall bid price for the concrete and masonry work contemplated concrete supplied at $100 per yard. If concrete provided by someone other than himself exceeded $100 per yard, H & S was to pay for the excess in cost. Consequently, Tyonek’s offer was rejected and Smith and H & S agreed that Smith would mix his own concrete for the project. From May through early July 1976, Smith mixed the concrete himself and *1150 poured the foundation footings and block walls satisfactorily.

From July 7 to July 9, 1976, Tyonek delivered concrete to the project site. 1 Smith used this concrete; however, the concrete Tyonek provided later proved defective. In September, 1976, Smith performed the necessary remedial work. Tyo-nek later billed Smith at $165 per yard for the concrete it had delivered. Smith did not pay this bill but did charge H & S for the cost of the concrete in excess of $100 per yard.

Thereafter, Smith and H & S exchanged a series of invoices in which each party billed the other for the extra costs attributable to the delivery of the defective concrete and the subsequent replacement costs. In November 1976, Smith sued Tyo-nek for the replacement costs, alleging negligence for furnishing unfit concrete. Tyonek counterclaimed for the unpaid concrete.

In March 1978, Smith amended his original complaint to include H & S and its surety, Maryland. Smith sought recovery from them under both tort and. contract theories. In the tort action, he sought to hold H & S liable for the economic loss Smith had suffered due to H & S’ negligent inspection of the concrete supplied by Tyo-nek. Smith also sued under the Little Miller Act to recover amounts unpaid.

All three co-defendants asserted affirmatively that Smith’s failure to comply with contractor registration requirements precluded his claims.

H & S was dissolved on September 30, 1980 for failure to file annual reports and pay corporate taxes and fees due.

On September 30, 1981 Judge Souter granted the summary judgment motion of H & S and Maryland to the extent that Smith sought recovery in contract on Counts II and IV but denied the motion to the extent that Smith sought recovery in tort on those counts. Summary judgment was also granted to defendants on Count III, the Little Miller Act claim. 2 The court so ruled as to all three counts because of Smith’s noncompliance with the contractor’s registration requirements of AS 08.-18.011-171. AS 08.18.151 precludes actions based in contract by unregistered contractors.

Trial commenced October 5, 1981. The jury returned a special verdict on October 16, 1981 finding that no contract existed between Smith and Tyonek to pay for the delivery of concrete. The jury did find all three parties negligent in the following apportionment: Smith — 15% negligent; Tyo-nek — 18% negligent; H & S — 67% negligent. 3

Thereafter, Tyonek renewed its motion for a directed verdict. Tyonek contended that since Smith’s damages consisted solely of economic losses, no tort recovery was available to Smith in the absence of privity of contract. The trial court found this a correct statement of law and granted judgment in favor of Tyonek.

Judge Souter entered a separate judgment in favor of Smith’s negligence claim against H & S on August 16, 1982, in the *1151 principal sum of $45,500 and a separate judgment in favor of Tyonek as to Count I.

Appellant Smith appeals the directed verdict in favor of Tyonek arguing that despite his lack of privity with Tyonek, his replacement costs as a subcontractor are compensable in a negligence claim. Smith also appeals the summary judgment in favor of H & S and Maryland, on the contract and Little Miller Act claims, AS 36.25.020.

II. AFTER A JURY AWARDED SMITH DAMAGES BASED ON A NEGLIGENCE CAUSE OF ACTION, DID THE SUPERIOR COURT ERR IN GRANTING A DIRECTED VERDICT FOR APPEL-LEE, TYONEK, WHEN IT RULED THAT, ABSENT PRIVITY WITH TYONEK, SMITH COULD NOT RECOVER DAMAGES FOR NEGLIGENCE WHERE HE SOUGHT DAMAGES SOLELY FOR ECONOMIC LOSS?

Smith argues that a cause of action in tort should extend to purely economic harm sustained by one not in privity with the supplier of a defective product. He suggests that our prior decisions relative to this subject evidence a willingness to embrace his position. Smith is mistaken.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

South Peninsula Hospital v. Xerox State Healthcare LLC
223 F. Supp. 3d 929 (D. Alaska, 2016)
21st Century Premier Insurance v. Smith
998 F. Supp. 2d 884 (D. Alaska, 2014)
McDonnell v. State Farm Mutual Automobile Insurance Company
299 P.3d 715 (Alaska Supreme Court, 2013)
Deaver v. Auction Block Co.
107 P.3d 884 (Alaska Supreme Court, 2005)
McCormick v. Reliance Insurance Co.
46 P.3d 1009 (Alaska Supreme Court, 2002)
Saunders Properties v. Municipality of Anchorage
846 P.2d 135 (Alaska Supreme Court, 1993)
Forest v. Safeway Stores, Inc.
830 P.2d 778 (Alaska Supreme Court, 1992)
Weller v. Spring Creek Resort, Inc.
477 N.W.2d 839 (South Dakota Supreme Court, 1991)
CARO. WINDS OWNERS'ASSOC., INC. v. Joe Harden Bldrs., Inc.
374 S.E.2d 897 (Court of Appeals of South Carolina, 1988)
Lobak Partitions, Inc. v. Atlas Construction Co.
749 P.2d 716 (Court of Appeals of Washington, 1988)
SKW/Eskimos, Inc. v. Sentry Automatic Sprinkler Co.
723 P.2d 1293 (Alaska Supreme Court, 1986)
Gross v. Bayshore Land Co.
710 P.2d 1007 (Alaska Supreme Court, 1986)
Jones v. Short
696 P.2d 665 (Alaska Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
680 P.2d 1148, 39 U.C.C. Rep. Serv. (West) 108, 1984 Alas. LEXIS 289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-for-use-of-smith-v-tyonek-timber-inc-alaska-1984.