Lost Valley Timber, Inc. v. Power City Construction, Inc.

809 F.2d 590, 1987 U.S. App. LEXIS 1625
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 4, 1987
DocketNo. 85-4381
StatusPublished
Cited by2 cases

This text of 809 F.2d 590 (Lost Valley Timber, Inc. v. Power City Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lost Valley Timber, Inc. v. Power City Construction, Inc., 809 F.2d 590, 1987 U.S. App. LEXIS 1625 (9th Cir. 1987).

Opinion

EUGENE A. WRIGHT, Circuit Judge.

Defendants, Power City Construction, Inc., Power Constructors, Inc., Power Two, and Fidelity & Deposit Co. of Maryland, appeal the denial of their motions and the final judgment. They contend that (1) the plaintiff, Lost Valley, is barred from recovering on its claim because of its failure to comply with the Alaska Contractor Registration Act, and (2) the district court erred by instructing the jury that it could find an implied contract. We agree with the first contention to the extent that Lost Valley contracted for work before registering. We disagree with the latter argument.

BACKGROUND

Alaska Power Authority, a corporate agency of the State of Alaska, awarded a prime contract for power line construction in the Tyee Lake Hydroelectric Project to Power Two. Power Two is a joint venture composed of its principals, Power City Construction, Inc. and Power Constructors, Inc. All defendants, including the surety Fidelity & Deposit, are referred to as Power Two.

Power Two subcontracted with Lost Valley to perform clearing work on the project. Power Two later directed Lost Valley to perform work outside the scope of the subcontract. The majority of the work was performed on property owned by the federal government. Lost Valley failed to obtain its Alaska license to engage in construction work until shortly before it completed its part of the job.

[592]*592STANDARD OF REVIEW

We review de novo the interpretation of state law. Olympic Sports Products, Inc. v. Universal Athletic Sales Co., 760 F.2d 910, 912 (9th Cir.1985), cert. de nied, — U.S. -, 106 S.Ct. 804, 88 L.Ed.2d 780 (1986); Decker Coal Co. v. Commonwealth Edison Co., 805 F.2d 834, 838 (9th Cir.1986). When applying state law, we are bound by the decisions of the state’s highest court. See Olympic Sports, 760 F.2d at 913.

ANALYSIS

A. ALASKA REGISTRATION ACT

Alaska law states that, unless a contractor falls within an exemption, it is unlawful “to submit a bid or work as a contractor until that person has been issued a certificate of registration by the Department of Commerce and Economic Development.” Alaska Stat. § 08.18.011 (1982). If a contractor fails to register, Alaska Statute § 08.18.151 (1982) provides:

A person acting in the capacity of a contractor may not bring an action in a court of this state for the collection of compensation for the performance of work or for breach of a contract for which registration is required under this chapter without alleging and proving that the contractor was a registered contractor at the time of contracting for the performance of the work. (Emphasis added).

Lost Valley asserts four arguments to persuade this court that the Registration Act does not bar its suit: (1) the Act is not applicable to subcontractors; (2) if it is, Lost Valley substantially complied with it; (3) the federal site exemption applies; and (4) the logging exemption applies. We are not persuaded.

First, the Alaska Supreme Court has twice held that subcontractor suits against general contractors are barred by a failure to comply with the Registration Act. Smith v. Tyonek Timber, Inc., 680 P.2d 1148, 1155 (Alaska 1984); Sumner Dev. Corp. v. Shivers, 517 P.2d 757, 761 (Alaska 1974). The district court’s reliance on Bremmeyer v. Peter Kiewit Sons, 90 Wash.2d 787, 585 P.2d 1174 (1978) is misplaced. Though Bremmeyer held that a similar act allowed actions by subcontractors, Smith, decided after Bremmeyer, reaffirmed that Alaska subcontractor suits are barred by the statute. Lost Valley’s action is governed by the Alaska Registration Act.

Second, Lost Valley contends that it substantially complied with the statute. The Alaska Supreme Court held, in Alaska Protection Serv. v. Frontier Colorcable, 680 P.2d 1119, 1122 (Alaska 1984), that substantial compliance exists when the contractor affords the other party the effective protection of the statute. This doctrine applies when a contractor is registered, bonded and covered by insurance. Id. Lost Valley was neither registered nor bonded until the day before it completed work. Belated registration does not remove the statutory bar. See Smith v. Tyonek Timber, Inc., 680 P.2d 1148, 1155 (Alaska 1984). Lost Valley did not substantially comply with the Registration Act.

Third, Lost Valley argues it is exempted from the registration requirement by Alaska statute § 08.18.161(7) (1982). This exempts from registration “construction, alteration, or repair carried on within the boundaries of a site under legal jurisdiction of the federal government.” (Emphasis added). Lost Valley’s work does not come within the literal language of the statute. Its work was not carried on totally “within” federal boundaries. See Olsen & Sons Logging, Ltd v. Owens, 607 P.2d 949, 951 (Alaska 1980).

Lost Valley’s fourth contention, that it falls within the logging exemption, is also rejected. It did not perform construction work incidental to logging.1 Its reliance on [593]*593Olsen & Sons Logging, Ltd. v. Owens, 607 P.2d 949 (Alaska 1980) is misplaced. The primary contract in Owens was for logging. Olsen then subcontracted with Owens to drill and shoot rock for logging roads. Here, the prime contract was for power line construction. Even though Lost Valley may have performed logging activities, those were incidental to power line construction, not to logging.2

We reverse the decision of the district court. The Alaska Registration Act applies to Lost Valley which is not within the Act’s exemptions. It is barred from recovery for all work until it registered. Since it may recover for work contracted for after registration, we next consider the implied contract contention.

B. IMPLIED CONTRACT

Lost Valley contends that extra work performed by it was outside the scope of its contract with Power Two. It maintains that the extra work performed was not covered by the provisions in the subcontract or prime contract. It argues that the issue was properly submitted to the jury because an ambiguity existed concerning what work was subject to provisions in the prime contract. We agree.

If the subcontract unambiguously governs payment for work outside the scope of the contract, the court erred by submitting the implied contract to the jury. See McMillan v. Anchorage Community Hosp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tiffany v. Commissioner
47 T.C. 491 (U.S. Tax Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
809 F.2d 590, 1987 U.S. App. LEXIS 1625, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lost-valley-timber-inc-v-power-city-construction-inc-ca9-1987.