Sumner Development Corporation v. Shivers

517 P.2d 757, 1974 Alas. LEXIS 301
CourtAlaska Supreme Court
DecidedJanuary 2, 1974
Docket2036
StatusPublished
Cited by31 cases

This text of 517 P.2d 757 (Sumner Development Corporation v. Shivers) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sumner Development Corporation v. Shivers, 517 P.2d 757, 1974 Alas. LEXIS 301 (Ala. 1974).

Opinion

OPINION

BOOCHEVER, Justice.

We granted this petition for review in order to consider important questions respecting the application of Alaska’s contractor’s licensing statutes to civil litigation among subcontractors, contractors and owners. 1

In August of 1972, the respondent Shivers, doing business as S & S Construction, entered into a contract with petitioner Sumner Development Corporation for the performance by S & S of site work on Majestic View Subdivision. The subdivision was partially owned by Sumner which, as general contractor, was developing it. Neither at the time of entering into the contract nor during the performance of it was Shivers licensed by the State of Alaska or bonded according to its statutes. The chief executive of Sumner Development Corporation, Del Sumner, was aware of the lack of bonding of Shivers. Del Sumner, a third person and Shivers had formed the Northwind Corporation to provide a bond and license under which Shivers could work. Shivers was no longer affiliated with Northwind at the time of the transactions relevant to this case. Del Sumner represented to Shivers that the latter could work under the bond and registration of Northwind or Sumner Development Corporation on the site work contract. Shivers commenced work on the site, digging basements, hauling trees, installing sewer lines and septic tanks, and backfilling.

A dispute arose regarding the performance of and payment for the work. On December 7, 1972, Shivers d/b/a S & S filed liens totaling $26,944.50 against various lots in the Majestic View Subdivision. On December 20, 1972, Shivers commenced this action to foreclose those liens. Alaska Mutual Savings Bank now owns the relevant property, having secured it by deed in lieu of foreclosure.

Sumner Development Corporation and Alaska Mutual Savings Bank filed a joint amended answer in which they denied the operative allegations of the complaint. They asserted as affirmative defenses failure to state a claim upon which relief could be granted, accord and satisfaction, estoppel to enforce the lien, failure of consideration, and voidness of the largest of the lien claims; and finally, they counterclaimed against Shivers for breach in failing to do the work in a competent and workmanlike manner and for malicious prosecution/abuse of process.

After engaging in discovery petitioners moved for summary judgment on the lien foreclosure claims against respondent upon several grounds, the only one of which material here is the admission of respondent that he was not a bonded and registered contractor.

The motion for summary judgment was denied by Judge Victor Carlson on July 6, 1973. On July 16, 1973, Justice Fitzgerald ordered a stay of trial to facilitate this petition for review, filed by Sumner Development Corporation and the bank after the denial of the motion.

RATIONALE FOR EXTRAORDINARY REVIEW

We first shall discuss our reasons for our grant of extraordinary review. Under Appellate Rule 23(e) 2 review of an *760 interlocutory order may be granted where postponement will result in injustice “because of unnecessary delay, expense [and] hardship . . . . ” Ordinarily the mere denial of summary judgment will not work an injustice upon a party sufficient to authorize review. Here, however, Shivers sought foreclosure of filed mechanic’s liens. If the petitioners were entitled to summary judgment, they also were entitled to have their land freed from the cloud upon title. 3 The interest in releasing a large block of property held and developed solely for the purpose of sale substantially outweighs the ordinary interest in mere avoidance of the expense of an adversary trial. We further note that, regardless of other claims raised by the parties, release of property subject to liens frequently results in material advancement of the whole of the litigation. 4

Ample ground exists under Appellate Rule 24(a) 5 for grant of review to these petitioners. First, wherever Appellate Rule 23(e) authorizes review, the same factors will ordinarily move our discretion under Appellate Rule 24(a)(2). Further, the petition presents issues “of such substance and importance as to justify deviation from the normal appellate procedure by way of appeal and to require the immediate attention of this court . . . .” 6

Shivers has argued that we ought not to grant review because the assertion of his rights as counterclaims (assuming they are barred from affirmative presentation) against Sumner Development Corporation and the bank in their action for breach of contract will result in a trial of the identical issues as if the action proceeded with Shivers’ lien claims affirmatively asserted and the petitioners’ countering. Thus the course of litigation would not be advanced. We shall discuss the question of presentation of barred claims as- setoffs extensively later; here let it suffice that respondent’s argument does not rebut the injustice of perpetuating invalid lien claims, nor does it completely respond to the argument that the course of this litigation would be materially advanced by entry of summary judgment. We therefore granted review.

Turning to the merits, we must decide whether AS 08.18.151 bars this action by an unlicensed subcontractor to foreclose a mechanic’s lien against a contractor-owner and a subsequent owner, whether the issue was properly raised, and, if so, whether any reason not to apply the statute to these parties exists.

*761 APPLICATION OF THE STATUTE

AS 08.18.151 bars actions for compensation for work done by unlicensed contractors:

No person acting in the capacity of a contractor may bring an action in a court of this state for the collection of compensation for the performance of work or for breach of a contract for which registration is required under this chapter without alleging and proving that he was a registered contractor at the time he contracted for the performance of the work.

That the contract between the parties denominated Shivers a subcontractor is immaterial. The licensing statute defines “contractor” by the nature of the work performed. If the work falls within a single craft classification, done under the supervision of a general contractor, the person doing the work is nevertheless a “contractor” for the, purposes of the statute, although he may be referred to as a “spe-ciality contractor”. 7

Shivers’ work falls within that specified by the legislature; thus, the licensing act applies to this action. Other jurisdictions hold that similar statutes comprise actions by subcontractors. 8

Actions to foreclose mechanic’s liens are of the genre prohibited. The Arizona Court of Appeals, acting upon a statute indistinguishable in operative language from Alaska’s, 9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daggett v. Feeney
397 P.3d 297 (Alaska Supreme Court, 2017)
Strike Four, LLC v. Nissan North America, Inc.
64 A.3d 936 (Supreme Court of New Hampshire, 2013)
Larson v. Benediktsson
152 P.3d 1159 (Alaska Supreme Court, 2007)
Brandner v. Agre
80 P.3d 691 (Alaska Supreme Court, 2003)
McCormick v. Reliance Insurance Co.
46 P.3d 1009 (Alaska Supreme Court, 2002)
Perry v. Goff Motors, Inc.
736 P.2d 949 (Court of Appeals of Kansas, 1987)
Gross v. Bayshore Land Co.
710 P.2d 1007 (Alaska Supreme Court, 1986)
State v. Weidner
684 P.2d 103 (Alaska Supreme Court, 1984)
State for Use of Smith v. Tyonek Timber, Inc.
680 P.2d 1148 (Alaska Supreme Court, 1984)
Caruso v. Local Union No. 690 of International Brotherhood of Teamsters
653 P.2d 638 (Court of Appeals of Washington, 1982)
Industrial Power & Lighting Corp. v. Western Modular Corp.
623 P.2d 291 (Alaska Supreme Court, 1981)
Capo v. Century Life Insurance
610 P.2d 1202 (New Mexico Supreme Court, 1980)
Olsen & Sons Logging, Ltd. v. Owens
607 P.2d 949 (Alaska Supreme Court, 1980)
Wetzler v. Wetzler
570 P.2d 741 (Alaska Supreme Court, 1977)
Balboa Insurance Co. v. Senco Alaska Inc.
567 P.2d 295 (Alaska Supreme Court, 1977)
Saxton v. Splettstoezer
557 P.2d 1126 (Alaska Supreme Court, 1977)
Interior Credit Bureau, Inc. v. Bussing
559 P.2d 104 (Alaska Supreme Court, 1977)
Bachner v. Rich
554 P.2d 430 (Alaska Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
517 P.2d 757, 1974 Alas. LEXIS 301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sumner-development-corporation-v-shivers-alaska-1974.