McCormick v. Reliance Insurance Co.

46 P.3d 1009, 2002 Alas. LEXIS 64, 2002 WL 959922
CourtAlaska Supreme Court
DecidedMay 10, 2002
DocketS-9813
StatusPublished
Cited by19 cases

This text of 46 P.3d 1009 (McCormick v. Reliance Insurance Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCormick v. Reliance Insurance Co., 46 P.3d 1009, 2002 Alas. LEXIS 64, 2002 WL 959922 (Ala. 2002).

Opinion

OPINION

EASTAUGH, Justice.

I. INTRODUCTION

Alaska Statute 08.18.151 bars a contractor from suing for compensation unless the contractor either met or was in substantial compliance with the contractor registration requirements when the contract was formed. Because there are genuine, material fact disputes about whether John MeCormick substantially complied with these requirements when he contracted to perform services on a public works project, we reverse the summary judgment that dismissed his Little Miller Act claim against the general contractor's surety. We do not reach MeCormick's alternative argument that he was Alaska Elec-trie's employee.

II. FACTS AND PROCEEDINGS

In May 1999 John MeCormick orally contracted with Alaska Electric Company, an electrical subcontractor on an Anchorage International Airport runway project, to provide end-dump trucking services at the rate of $60 per hour. McCormick worked on the runway project from May 10 through Sep *1011 tember 8, 1999. Although MeCormick initially provided only end-dump trucking services on the project, Alaska Electric eventually asked McCormick to provide additional services, including excavation, installing electrical vaults, and driving an Alaska Electric truck to purchase fuel and materials for the construction site. MeCormick also furnished a service van, a small semi-tractor, and various tools to the site.

McCormick submitted invoices for completed work to Alaska Electric, which forwarded the invoices to Wilder Construction Company, the general contractor on the project. Wilder then issued checks made out to both Alaska Electric and McCormick for invoices approved by Alaska Electric. McCormick was paid for all work performed through July 17, 1999.

As of October 1, 1999 McCormick 'had received no payment for work he performed after July 17, 1999. On October 1 he gave Wilder written notice, as required by AS 36.25.020(b), 1 of a claim for $48,186.23 for services he claimed he rendered from July 18 through September 8, 1999. The same day Wilder sent McCormick a check for $12,375.96. 2 Wilder claimed that the services McCormick rendered from July 18 through September 8 were outside the scope of the agreement to provide end-dump trucking services at the rate of $60 per hour, and that MeceCormick was entitled only to a labor rate of $27.32 per hour for those services.

On November 12, 1999 McCormick filed a superior court complaint against Alaska Electric and Reliance Insurance Company. The complaint alleged that Alaska Electric breached the contract and the covenant of good faith and fair dealing. It asserted a Little Miller Act 3 claim against Reliance, which had furnished a surety bond for Wilder. In April 2000 Reliance moved for summary judgment, claiming that it was entitled to judgment as a matter of law, because (1) McCormick's registration with the state as a contractor had expired before he contracted with Alaska Electric, and (2) McCormick filed his claim prematurely. McCormick opposed Reliance's motion and cross-moved for summary judgment.

The superior court dismissed MeCormick's Little Miller Act claim against Reliance on summary judgment because John MeCor-mick was not registered "under AS 08.18.011 et seq:" at relevant times. The court denied McCormick's cross-motion for summary judgment.

McCormick moved for reconsideration, claiming that the superior court had failed to consider his alternative argument that he was an employee of Alaska Electric, and that he was therefore not required to register as a contractor in order to sue for unpaid compensation: The superior court denied the reconsideration motion and entered a final judgment in favor of Reliance. McCormick appeals.

IH. DISCUSSION

A. Standard of Review

We review a grant of summary judgment de novo and affirm if the evidence in the record fails to disclose a genuine issue of material fact, and the moving party is entitled to judgment as a matter of law. 4 A We view the facts in the light most favorable to the non-moving party. 5 We apply our independent judgment to any questions of law, adopting the rule of law that is most persua *1012 sive in light of precedent, reason, and policy. 6

B. It Was Error to Dismiss McCormick's . Little Miller Act Claim Against Reliance on Summary Jydgment.

1. There are genuine issues of material fact about whether McCormick substantially complied with AS 08.18's registration requirements.

McCormick's only claim against Reliance was under the Little Miller Act. That statute "requires that the primary contractor . on a public works project post a bond to the state or political subdivision thereof 'for the protection of all persons who supply labor and material in the prosecution of the work provided for in the contract....'" 7 The Little Miller Act further provides:

A person who furnishes labor or material in the prosecution of the work provided for in the contract for which a payment bond is furnished ... and who is not paid in full before the expiration of:-90 days after the last day on which the labor is performed or material is furnished for which the claim is made, may sue on the payment bond for the amount unpaid at the time of suit.[ 8 ]

A contractor may not sue under the Little Miller Act without alleging and proving that the contractor was a registered contractor at the time of contract formation. 9 "Registration as a construction contractor under AS 08.18 requires: a registration fee, a surety bond, and public liability and property damage insurance." 10 "Registration was intended by the legislature to ensure 'competence and financial responsibility in those who undertake work as contractors.'" 11

Because "the legislature chose the closing of the doors of the courts as a fundamental tool to enforce its policy of ensuring competence and financial responsibility in those who undertake work as contractors," we have consistently enforced AS 08.18.151's requirement that a contractor must be registered at the time of contract formation in order to maintain an action for compensation. 12 But because "statutes which cause forfeiture are not favored," 13 we have adopted the doctrine of substantial compliance. 14 We have held that AS 08.18.151's statutory bar may be abrogated by a contractor's substantial compliance with the registration requirements. 15

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leahy v. Conant
447 P.3d 737 (Alaska Supreme Court, 2019)
Alaska Trustee, LLC v. Ambridge
372 P.3d 207 (Alaska Supreme Court, 2016)
Brooks v. Horner
344 P.3d 294 (Alaska Supreme Court, 2015)
Olson v. City of Hooper Bay
251 P.3d 1024 (Alaska Supreme Court, 2011)
Holmes v. Wolf
243 P.3d 584 (Alaska Supreme Court, 2010)
West v. STATE, BD. OF GAME
248 P.3d 689 (Alaska Supreme Court, 2010)
Commercial Recycling Center, Ltd. v. Hobbs Industries, Inc.
228 P.3d 93 (Alaska Supreme Court, 2010)
Bridges v. Banner Health
201 P.3d 484 (Alaska Supreme Court, 2008)
Larson v. Benediktsson
152 P.3d 1159 (Alaska Supreme Court, 2007)
Casey v. Semco Energy, Inc.
92 P.3d 379 (Alaska Supreme Court, 2004)
Brandner v. Agre
80 P.3d 691 (Alaska Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
46 P.3d 1009, 2002 Alas. LEXIS 64, 2002 WL 959922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccormick-v-reliance-insurance-co-alaska-2002.