Bremmeyer v. Peter Kiewit Sons Co.

585 P.2d 1174, 90 Wash. 2d 787, 1978 Wash. LEXIS 1131
CourtWashington Supreme Court
DecidedNovember 2, 1978
Docket44811
StatusPublished
Cited by18 cases

This text of 585 P.2d 1174 (Bremmeyer v. Peter Kiewit Sons Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bremmeyer v. Peter Kiewit Sons Co., 585 P.2d 1174, 90 Wash. 2d 787, 1978 Wash. LEXIS 1131 (Wash. 1978).

Opinion

Stafford, J.

Appellant Bill Bremmeyer, doing business as Bremmeyer Logging Company, appeals a summary judgment dismissing his complaint. .We reverse and remand for trial.

The State of Washington awarded respondent Peter Kiewit Sons Company (Peter Kiewit) a prime contract to construct several miles of Interstate 90. The highway right-of-way was overgrown and needed to have the trees and debris cleared before construction could begin. For this purpose, Peter Kiewit subcontracted the necessary clearing operation to Bremmeyer.

Under the written subcontract, Bremmeyer agreed to pay Peter Kiewit $35,000 for the right to fall, yard, buck, load and haul to the mill all merchantable timber within the highway right-of-way. Bremmeyer also agreed to (1) furnish a payment and performance bond; (2) provide liability insurance; (3) build, within the clearing limits, all access roads required for clearing if Peter Kiewit's roads were insufficient; and (4) comply with Peter Kiewit's fire plan which was on file with the United States Forest Service.

Bremmeyer furnished a bond and insurance certificate, paid the $35,000, and began clearing the right-of-way. Before he had completed his performance under the contract the State terminated Peter Kiewit's prime contract. Peter Kiewit, in turn, terminated Bremmeyer's subcontract. Peter Kiewit received $1,729,050 from the State for cancellation costs but tendered Bremmeyer only $38.73 for cancellation of the subcontract.

Bremmeyer filed this action to recover the value of the uncut merchantable timber. Peter Kiewit answered and *789 then moved for a summary judgment of dismissal asserting Bremmeyer was barred from bringing the action because he was not registered in accordance with RCW 18.27. The affidavits submitted on summary judgment showed (1) Bremmeyer had not registered as a contractor pursuant to RCW 18.27; (2) the subcontract involved the clearing of trees within a highway right-of-way; (3) the subcontract had no direct or incidental fire prevention purpose; (4) the subcontract's sole purpose was to clear timber to facilitate highway construction; and (5) the Department of Labor and Industries (Department) does not require loggers to register under RCW 18.27. In response to the motion Bremmeyer asserted his failure to register did not bar his action because (1) he was not a "contractor" as defined by RCW 18.27.010; (2) loggers were exempt from registration; and (3) his activities were incidental to land clearing for fire prevention purposes and thus exempt from registration under RCW 18.27.090(10).

The trial court found that no genuine issue of material fact existed and orally granted Peter Kiewit's motion for summary judgment. Thereafter, Bremmeyer moved to reconsider and set aside the oral summary judgment because (1) he had substantially complied with RCW 18.27; (2) the statute was inapplicable to actions between subcontractors and prime contractors; and (3) his activities were exempt from registration under RCW 18.27.090(6) as construction activities upon personal property. As additional evidence Bremmeyer furnished the bond, an insurance certificate, and affidavit showing his reliance upon the Department's policy of exempting loggers from registration, and a letter from the Attorney General's office stating that logging activities per se were exempt from registration.

The trial court refused to consider the additional factual and legal matters and entered its written order granting summary judgment of dismissal. Bremmeyer's motion to reconsider was thereafter denied as improper under CR 60(b)(2) and (6).

*790 Bremmeyer appealed, assigning error to the judgment and to the trial court's refusal to consider the additional factual and legal matters submitted with his motion to reconsider. The Court of Appeals considered all factual and legal matters presented to the trial court, including those which had been rejected, and affirmed the dismissal. Bremmeyer v. Peter Kiewit Sons Co., 16 Wn. App. 318, 555 P.2d 1183 (1976).

Bremmeyer's petition for review raises five issues. (1) Does RCW 18.27 apply to actions between subcontractors and prime contractors? (2) Was the subcontract one for the "purchase of trees?" (3) Must loggers register under RCW 18.27? (4) Did Bremmeyer substantially comply with RCW 18.27? (5) If Bremmeyer's action is barred by RCW 18.27, is Bremmeyer denied his constitutional right of access to the courts? Inasmuch as our resolution of issue (1) is fully dispositive of this appeal, we need not address the remaining issues.

We first considered whether the legislature intended RCW 18.27 to bar actions by unregistered subcontractors against prime contractors in Jeanneret v. Rees, 82 Wn.2d 404, 511 P.2d 60 (1973). On this issue a majority of the court agreed the legislature intended to preclude such actions. However, even among the majority the various rationales utilized to find this intent were hardly unanimous. Some members of the court felt that statute was intended to bar the subcontractor's action because RCW 18.27.090 contained no specific exemption for them. Jeanneret v. Rees, supra at 408. Others concluded the plain and unambiguous language of RCW 18.27.080 controlled, requiring a determination that the legislature intended to foreclose the unregistered subcontractor's action. Jeanneret v. Rees, supra at 410 (dissenting opinion by Justice Wright).

After careful reexamination of the issue, we are convinced that we can no longer be guided in our interpretation of the reach of RCW 18.27

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Awr Const. v. Washington Dept. of Labor
217 P.3d 349 (Court of Appeals of Washington, 2009)
A.W.R. Construction, Inc. v. Department of Labor & Industries
152 Wash. App. 479 (Court of Appeals of Washington, 2009)
Hinton v. Johnson
942 P.2d 1061 (Court of Appeals of Washington, 1997)
Pope & Talbot, Inc. v. Productization, Inc.
872 P.2d 78 (Court of Appeals of Washington, 1994)
Alaska Cascade Financial Services, Inc. v. Doors Northwest, Inc.
762 P.2d 362 (Court of Appeals of Washington, 1988)
Lobak Partitions, Inc. v. Atlas Construction Co.
749 P.2d 716 (Court of Appeals of Washington, 1988)
Frank v. Fischer
739 P.2d 1145 (Washington Supreme Court, 1987)
Frank v. Fischer
730 P.2d 70 (Court of Appeals of Washington, 1986)
Mike's Rental MacHinery, Inc. v. Corbett Draw Farms, Inc.
721 P.2d 1000 (Court of Appeals of Washington, 1986)
Martin v. TX Engineering, Inc.
719 P.2d 1360 (Court of Appeals of Washington, 1986)
Stewart Carpet Service, Inc. v. Contractors Bonding & Insurance
715 P.2d 115 (Washington Supreme Court, 1986)
Allied American Painting Contractors, Inc. v. Shore
700 P.2d 389 (Court of Appeals of Washington, 1985)
International Commercial Collectors, Inc. v. Carver
661 P.2d 976 (Washington Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
585 P.2d 1174, 90 Wash. 2d 787, 1978 Wash. LEXIS 1131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bremmeyer-v-peter-kiewit-sons-co-wash-1978.