Brettschneider v. Wellman

41 N.W.2d 255, 230 Minn. 225, 1950 Minn. LEXIS 608
CourtSupreme Court of Minnesota
DecidedFebruary 10, 1950
Docket35,069
StatusPublished
Cited by12 cases

This text of 41 N.W.2d 255 (Brettschneider v. Wellman) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brettschneider v. Wellman, 41 N.W.2d 255, 230 Minn. 225, 1950 Minn. LEXIS 608 (Mich. 1950).

Opinion

Knutson, Justice.

Defendant Thomas G. Wellman, desiring to build a house, had preliminary talks with an architect, Edward W. Barber, the contemplated contractor, Emery Wohlers, and one D. L. Mills, secretary and treasurer of appellant, Lake City Federal Savings and Loan Association, during the early part of 1946. Before he had a deed to the lot on which he proposed to build his house, he told Wohlers, on or about July 20,1946, that everything was all set and that he should go ahead with the work. Wohlers thereupon did some brushing on the lot, and on or about August 16, 1946, he procured a power shovel and had the basement excavated. On August 21, 1946, Wellman and Wohlers signed a contract under which Wohlers agreed to build the house according to the architect’s plans and specifications for $10,715. On August 21 or 22, 1946, Wellman applied to appellant for a loan, which was approved, and a note in the amount of $12,115, secured by a mortgage covering the premises on which the house was to be built, in the' usual form, was signed by Wellman on August 27, 1946. It was filed for record in the office of the register of deeds of Wabasha county, Minnesota, on August 28, 1946. The debt was guaranteed by the *227 veterans administration up to the sum of $4,000 by what is commonly known as a Gr. I. loan. From the proceeds of the loan, appellant paid for the lot and some other items of expense which had been incurred. The first material for the house was secured on October 14,1946, after which work began. The architect supervised the work and was at the house at least three times each week. On December 14, 1946, appellant and Wellman executed a loan settlement statement under which Wellman approved certain payments which had been made out of the proceeds of the loan and appellant set forth the balance of the loan to be paid Wellman. 2

*228 The contract between Wellman and Wohlers contains this provision :

“Article III. The Owner agrees to pay the Contractor in current funds for the performance of the contract ten thousand seven hundred fifteen dollars ($10,715.00) subject to any additions or deductions to the general conditions of the contract agreed upon in writing, and to make payments on account hereof upon presentation of proper lien waivers, as the work progresses.”

After the execution of the loan settlement statement, appellant paid for material furnished and paid the contractor, upon submis *229 sion by the claimants of statements purporting to represent completed work or material furnished, in the following amounts:

February 3,1947 — Emery Wohlers.....................$ 380.00

A. M. Kramer....................... 187.50

F. A. Brettschneider ................ 33.50

Schmauss Plumbing................. 77.45

William Kehren .................... 18.50

Arthur Mickow..................... 25.00

February 27,1947 — Cochrane Kirkwood................. 73.95

April 22,1947 —Emery Wohlers..................... 2,200.00-

May 26,1947 —Emery Wohlers..................... 2,000.00

No lien waivers were taken, nor were the bills submitted to Well-man or his architect for approval. Wellman testified that he assumed that the payments were being made, that this was the usual way of handling building, and that it was agreeable to him that the matter be so handled. Wellman made monthly payments on the note from April 24, 1947, to November 14, 1947, aggregating $678. He also paid $160 toward loan expenses, as shown on the loan settlement statement.

During the progress of the work a number of changes and alterations were made in the plan. Wellman thought that the additions which would increase the cost would about equal those changes which decreased the cost. In addition to these changes, an old house was purchased and wrecked, and much of the material was used in building Wellman’s house. The record fails to disclose how much, if any, the use of such old material added to the cost. In any event, during late May or early June 1947, appellant became apprehensive of being able to complete the house with the remaining money from the loan and refused to pay any more bills unless Wellman could raise more money to insure completion of the project. Wohlers continued to work until June 17, 1947, when he discontinued his work. The amount of the loan then remaining undisbursed was $4,818.30. Outstanding bills amounted to about $5,233.24. Much of the material for the completion of the house was then on the loca *230 tion. The cost of completing the house was estimated by the architect to be about $1,800 to $2,000 above the money then on hand.

After appellant refused to make any more payments and Wohlers had quit work on the project, liens were filed by plaintiff, F. A. Brettschneider, and defendants Botsford Lumber Company, a corporation, Henry Schmauss, Gipson Lumber Company, a corporation, and Oliver K. Hein. Appellant thereafter applied the undis-bursed balance of the loan on the note. Actions to foreclose the liens and the mortgage were consolidated for trial. The trial court found that the liens were entitled to priority over the mortgage and that appellant was entitled to recover $1,718 with interest, which amount was arrived at by deducting from the payments approved in the loan settlement statement the payments made by Wellman on the note. The court held that other payments made by appellant were unauthorized and that Wellman had not received $9,814.20 of the consideration of the note and mortgage. Wohlers was denied any recovery, for the reason that he had not performed his contract. He has not appealed. In its memorandum to the order denying appellant’s motion for amended findings or a new trial, the court explains the reason for its decision thus:

“The evidence clearly shows that the association did not make the disbursements at the instance or request of the mortgagors. It did not rely upon the representations of the mortgagors nor of their architects. It made no investigations of its own. It merely paid out, from time to time, eighty per cent of the bills without questioning the amount and without regard to the contract price or the status of the work. It was this foolish practice that brought about the catastrophe.”

Appellant attempted to show an oral understanding or agreement between it and Wellman under which appellant was to pay for labor and material as the work progressed. The trial court refused to admit evidence of such agreement.

The appeal presents for our determination these questions:.

*231 (1) Are the lienholders entitled to preference over the mortgage of appellant?

(2) Was it error to reject evidence of an oral understanding as to how the proceeds of the loan should be disbursed?

(3) Is the court’s finding as to the amount appellant is entitled to recover sustained by the evidence?

M. S. A. 514.05 provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Big Lake Lumber, Inc. v. Security Property Investments, Inc.
836 N.W.2d 359 (Supreme Court of Minnesota, 2013)
Big Lake Lumber, Inc. v. Security Property Investments, Inc.
820 N.W.2d 253 (Court of Appeals of Minnesota, 2012)
KETCHUM, KONKEL v. Heritage Mt.
784 P.2d 1217 (Court of Appeals of Utah, 1989)
In Re Zachman Homes, Inc.
47 B.R. 496 (D. Minnesota, 1984)
Midwest Federal Savings & Loan Ass'n of Minot v. Miller
349 N.W.2d 19 (North Dakota Supreme Court, 1984)
Kloster-Madsen, Inc. v. Tafi's, Inc.
226 N.W.2d 603 (Supreme Court of Minnesota, 1975)
Reuben E. Johnson Co. v. Phelps
156 N.W.2d 247 (Supreme Court of Minnesota, 1968)
New Prague Lumber & Readi-Mix Co. v. Bastyr
117 N.W.2d 7 (Supreme Court of Minnesota, 1962)
Brodsky v. Maloney
105 N.W.2d 911 (South Dakota Supreme Court, 1960)
National Lumber Co. v. Farmer & Son, Inc.
87 N.W.2d 32 (Supreme Court of Minnesota, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
41 N.W.2d 255, 230 Minn. 225, 1950 Minn. LEXIS 608, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brettschneider-v-wellman-minn-1950.