Lepore v. Parker-Woodward Corp.

818 F. Supp. 1029, 1993 U.S. Dist. LEXIS 333, 1993 WL 6839
CourtDistrict Court, E.D. Michigan
DecidedJanuary 8, 1993
DocketNos. 89-73475, 89-73476
StatusPublished
Cited by2 cases

This text of 818 F. Supp. 1029 (Lepore v. Parker-Woodward Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lepore v. Parker-Woodward Corp., 818 F. Supp. 1029, 1993 U.S. Dist. LEXIS 333, 1993 WL 6839 (E.D. Mich. 1993).

Opinion

ORDER ACCEPTING MAGISTRATE JUDGE KOMIVES’ OPINION AND ORDER GRANTING RAYCO/PETERSEN GROUP’S MOTION FOR PRIORITY

GADOLA, District Judge.

The court, pursuant to 28 U.S.C. § 636(b)(1)(B), Fed.R.Civ.P. 72(b), and LR 72.1(d)(2) (E.D.Mich. Jan. 1, 1992), has reviewed the transcript of the December 4, 1992 hearing on this matter, the magistrate judge’s December 10, 1992 memorandum opinion and order, and Resolution Trust Corporation’s objections filed December 18,1992. After conducting a de novo review, the court accepts the magistrate judge’s memorandum opinion and order as the court’s findings and conclusions.

Therefore, it is hereby ORDERED that the magistrate judge’s December 10, 1992 memorandum opinion and order is ADOPTED.

It is further ORDERED that Rayco/Petersen Group Construction’s motion for priority of all construction lien claimants is GRANTED.

SO ORDERED.

MEMORANDUM OPINION AND ORDER

KOMIVES, United States Magistrate Judge.

A.

This matter is before the Court for determination of the Rayco/Petersen Group Construction’s amended motion for priority of all construction lien claimants, filed November 25, 1992. The motion was referred by an order dated November 30,1992, which stated that I was to hear the parties on December 4, 1992, and determine the matter pursuant to 28 U.S.C. § 636(b)(1)(A). Should the Court conclude that the reference should have been under § 636(b)(1)(B) for a report and recommendation on a “dispositive” matter, see Columbia Record Productions v. Hot Wax Records, 966 F.2d 515 (9th Cir.1992), this opinion and order should be construed as a report and recommendation.

Rayco/Petersen Group Construction (“Ray-co”) was the general contractor for the construction of a commercial building located in Bloomfield Hills, Michigan. The project was financed by Guaranty Federal Savings Bank.1 A construction loan in the amount of $800,000 was approved, and on August 5, 1988, the construction mortgage on the property was executed. Construction on the project began sometime in September 1988, after the execution and delivery of the mortgage. However, the mortgage was not recorded until October 31, 1988.

Rayco, as the general contractor for the project, now brings this motion for priority of all construction lien claimants. Rayco contends that the first physical improvement on the land occurred, at the latest, on October 4,1988. The mortgage was not recorded until October 31, 1988. Therefore, Rayco asserts, under the terms of the Michigan [1032]*1032Construction Lien Act, Mich.Comp.Laws § 570.1101, et seq., the mortgagee’s interest is inferior to the liens held by the general contractor and all subcontractors.

B.

On December 4, 1992, RTC, as mortgagee, filed a response in opposition to Rayco’s motion. RTC contends that Rayco offers no authority for the proposition that the priority of all lien claimants may be established by motion. Rather, RTC submits, this determination is replete with issues of fact and, as such, must necessarily be decided at trial. Moreover, RTC argues that, although Rayco submits that its motion is not dispositive, such a determination will necessarily and ultimately determine final claim priorities as between or among the mortgagee, the general contractor and the subcontractors.

RTC further contends that Rayco’s motion attempts to treat each of the construction lien claimants on an equal footing despite the existence of equitable circumstances, in particular the fact that Rayco had actual notice of the mortgage prior to commencement of construction or demolition. To the extent that Rayco seeks to establish priority of its or its subcontractors’ liens, RTC argues, it should be estopped from claiming priority superior to that of RTC due to (1) its participation in a scheme to secure additional funds, and (2) the fact that Raymond Husic, Rayco’s principal, had notice of and participated in procuring the construction loan from Guaranty Federal Savings Bank. Thus, RTC urges, the Court should deny Rayco’s motion and enter an order establishing RTC’s superior position.

C.

Rayco asserts that because the mortgage held by RTC was recorded after the first physical improvement occurred on the property, the lien held by Rayco and all of its subcontractors has priority. In support of this assertion, Rayco relies upon portions of the Michigan Construction Lien Act and caselaw interpreting the Act.

The Michigan Construction Lien Act, Mich.Comp.Laws § 570.1101, et seq., deals with the priority of construction liens. It provides, in pertinent part:

(3) A construction lien arising under this act shall take priority over all other interests, liens, or encumbrances which may attach to the building, structure, or improvement, or upon the real property on which the building, structure, or improvement is erected when the other interests, liens, or encumbrances are recorded subsequent to the first actual physical improvement.

Mich.Comp.Laws § 570.1119(3).

Rayco cites Durant Construction, Inc. v. Gourley, 125 Mich.App. 695, 336 N.W.2d 856 (1983), in which the court noted that, under Mich.Comp.Laws § 570.1119, a construction lien, which takes effect when the first actual physical improvement occurs, has priority over a mortgage instrument recorded subsequent to the commencement of the construction work.

The Michigan Supreme Court decision in Williams & Works v. Springfield, 408 Mich. 732, 293 N.W.2d 304 (1980), also relied upon by Rayco, defined “commencement” of a building:

The term ‘commencement of a building’ had a well-established meaning in most states when Michigan incorporated that term into its own mechanics’ lien law. As illustrative of this meaning, and in order not to belabor the point, we quote from one such case, while citing the reader to others which preceded or were contemporaneous with Michigan’s statute:
‘The commencement of a building is the doing of some act upon the ground upon which the building is to be erected, and in pursuance of a design to erect, the result of which act should make known to a person viewing the premises, from observation alone, that the erection of a building upon that lot or tract of land has been commenced.’ (citations omitted).
Likewise, early Michigan case law espoused this same idea of keying the concept of ‘commencement’ in its priority section to some actual, visible work on the land such that it was apparent to all that a building was being erected or improvements were being made.

Id. at 740-741, 293 N.W.2d 304.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Federal Deposit Insurance
61 F.3d 1552 (Eleventh Circuit, 1995)
Smith v. Federal Deposit Insurance Corporation
61 F.3d 1552 (Third Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
818 F. Supp. 1029, 1993 U.S. Dist. LEXIS 333, 1993 WL 6839, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lepore-v-parker-woodward-corp-mied-1993.