Aaron C. Sluyter and Cheryl Sluyter v. Wood Guys, LLC

2021 Ark. App. 442, 638 S.W.3d 849
CourtCourt of Appeals of Arkansas
DecidedNovember 10, 2021
StatusPublished
Cited by1 cases

This text of 2021 Ark. App. 442 (Aaron C. Sluyter and Cheryl Sluyter v. Wood Guys, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aaron C. Sluyter and Cheryl Sluyter v. Wood Guys, LLC, 2021 Ark. App. 442, 638 S.W.3d 849 (Ark. Ct. App. 2021).

Opinion

Cite as 2021 Ark. App. 442 Elizabeth Perry ARKANSAS COURT OF APPEALS I attest to the accuracy and DIVISION IV integrity of this document No. CV-20-595 2023.07.14 11:52:16 -05'00' 2023.003.20244 AARON C. SLUYTER AND CHERYL Opinion Delivered November 10, 2021 SLUYTER APPEAL FROM THE BENTON APPELLANTS COUNTY CIRCUIT COURT [NO. 04CV-19-1639] V. HONORABLE JOHN R. SCOTT, WOOD GUYS, LLC JUDGE

APPELLEE REVERSED AND REMANDED

WAYMOND M. BROWN, Judge

Appellants Cheryl and Aaron Sluyter (the “Sluyters”) appeal the order and judgment

entered against them on March 5, 2020. On appeal, the Sluyters challenge the validity of

the judgment entered by the Benton County Circuit Court, arguing that due to failure to

give preconstruction lien notice pursuant to Arkansas Code Annotated section 18-44-115, 1

appellee Wood Guys, LLC, is barred from recovering on its breach-of-contract and

quantum meruit claims. We reverse and remand.

In February 2019, the parties orally contracted for Wood Guys to replace and refinish

hardwood flooring in a house owned by the Sluyters located in Rogers, Arkansas. Pursuant

to the contract, Wood Guys provided labor, materials, and supplies related to hardwood

flooring, including the removal and repair of existing flooring and installation of new

1 (Supp. 2017). hardwood flooring. Wood Guys completed the work on March 19, 2019, for a total cost of

$5289.95.

A dispute arose between the parties regarding both the quality of the work performed

and the amount owed for the work. The Sluyters refused Wood Guys’ demands for

payment. Consequently, Wood Guys filed a mechanics’ and materialmen’s lien on the

property and then filed a complaint against the Sluyters on July 15 to foreclose its lien,

seeking damages for breach of contract or, in the alternative, to recover under the theory of

quantum meruit for improvements it made to the Sluyters’ property.

On July 29, the Sluyters answered and counterclaimed alleging that (1) the orally

agreed-upon price for the flooring work was $3,400; (2) because Wood Guys caused $125

damage to a bathroom toilet, the Sluyters should have an offset or judgment against Wood

Guys in the sum of $125; (3) due to negligent installation, the floors buckled and need to

be replaced, and therefore they received no benefit from the services provided by Wood

Guys; and (4) they are entitled to judgment against Wood Guys for costs to remove and

replace the defective flooring. Additionally, the Sluyters requested costs of the action and

reasonable attorney’s fees. Wood Guys answered the counterclaim denying all allegations.

In its amended answer and counterclaim filed on November 8, the Sluyters claimed

entitlement to judgment in the amount of $6,954.73 to replace the defective flooring

negligently installed by Wood Guys. The Sluyters further claimed that Wood Guys is a

“home improvement contractor” as defined by Arkansas Code Annotated section 17-25-

502(2) and, pursuant to Arkansas Code Annotated section 18-44-115(a), Wood Guys, as a

home improvement contractor, was required to provide preconstruction lien notice; failure

2 to do so barred Wood Guys from pursuing any claims against them. Wood Guys responded,

denying it was required to provide preconstruction lien notice.

The Sluyters moved for summary judgment, asserting that due to Wood Guys’ failure

to provide the statutorily required preconstruction lien notice, Wood Guys is barred from

bringing any action to enforce the provisions of the contract. Therefore, the Sluyters alleged,

there are no material issues of fact to be decided, and they are entitled to summary judgment

as a matter of law. The case proceeded to trial without a ruling on the summary-judgment

motion.

Following the February 18, 2020 trial, the circuit court ruled in favor of Wood Guys.

In its order dated March 5, the circuit court found:

1. Under Ark. Code Ann. § 18-44-115 no lien may be acquired on residential real estate unless the owner or owner’s authorized agent has received the notice set forth in Ark. Code Ann. § 18-44-115(7).

2. Plaintiff did not provide the pre-construction lien notice stated in Ark. Code Ann. § 18-44-115(7) to Defendants prior to performing the work on the residence located at 4420 Blossom Way, Rogers, Arkansas (the “Property”). Accordingly, Plaintiff did not acquire a valid lien on the defendants’ property even though Plaintiff filed a lien.

3. Plaintiff is not a “residential building contractor” as defined in Ark. Code Ann. 17-25-502(3). The term “residential contractor” appearing in A.C.A. § 18-44- 115 and the term “residential building contractor” defined in A.C.A. § 17-25-502(3) are synonymous.

4. Plaintiff is a “home improvement contractor” as defined in Ark. Code Ann. § 17-25-502(2).

5. Plaintiff is not barred from bringing this action to enforce its contractual and quantum meruit claims.

6. There is no dispute Plaintiff performed the work on the Property as stated in its invoice, including removal and replacement of a section of wood flooring and

3 sanding and refinishing flooring at the Property and that the Plaintiff hired a subcontractor to perform part of the work.

7. There is no dispute Defendants have not paid Plaintiff for any of the work Plaintiff performed.

8. The amount charged by Plaintiff for its work is fair and reasonable.

9. Plaintiff is entitled to judgment against Defendants for the full amount of Plaintiff’s invoice in the amount of $5,289.95, plus interest at the rate of four percent (4%) per annum from March 19, 2019, until paid, plus the costs of filing this action in the amount of $190.00, plus the cost of serving summons and complaint on the Defendants in the amount of $130.00, plus a reasonable attorney’s fee in the amount of $2,500.

10. Defendants’ counterclaim is dismissed with prejudice.

11. Defendants’ assertion that Plaintiff’s work was defective is inconsistent with Defendants’ representations in a Property Disclosure Statement to buyers of the Property and inconsistent with testimony and other evidence at trial.

12. Defendants failed to present any evidence of any damages they sustained in the sale of the Property as a result of any alleged defect in Plaintiff’s work.

Following the March 23 denial of the Sluyters’ motion for reconsideration, they

timely appealed.

We review issues of statutory construction de novo and we will not reverse a circuit

court’s interpretation of a statute unless it is shown that the circuit court erred. 2 It has long

been held that mechanics’ and materialmen’s liens are in derogation of common law. 3

Because they are in derogation of common law and were created by the legislature, we

strictly construe these lien statutes. 4 Strict construction requires that nothing be taken as

2 Ahern Rentals, Inc. v. Salter Constr., Inc., 2014 Ark. App. 423, 439 S.W.3d 699. 3 Bryant v. Jim Atkinson Tile, 100 Ark. App. 408, 269 S.W.3d 383 (2007). 4 Id.

4 intended that is not clearly expressed, and the plain meaning of the language employed

should be used. 5 Even when statutes are to be strictly construed, however, they must be

construed in their entirety, harmonizing each subsection where possible. 6 Where the

meaning is clear and unambiguous, we do not resort to the rules of statutory interpretation. 7

The Sluyters argue that pursuant to the clear provisions of Arkansas Code Annotated

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2021 Ark. App. 442, 638 S.W.3d 849, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aaron-c-sluyter-and-cheryl-sluyter-v-wood-guys-llc-arkctapp-2021.