Dye v. Precision Foundation Specialties & Flow Rite Drainage Solutions, Inc.

2022 Ark. App. 220, 646 S.W.3d 168
CourtCourt of Appeals of Arkansas
DecidedMay 11, 2022
StatusPublished
Cited by3 cases

This text of 2022 Ark. App. 220 (Dye v. Precision Foundation Specialties & Flow Rite Drainage Solutions, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dye v. Precision Foundation Specialties & Flow Rite Drainage Solutions, Inc., 2022 Ark. App. 220, 646 S.W.3d 168 (Ark. Ct. App. 2022).

Opinion

Cite as 2022 Ark. App. 220 ARKANSAS COURT OF APPEALS DIVISION I No. CV-19-499

JOHN RAY DYE AND BOBBY JO DYE Opinion Delivered May 11, 2022 APPELLANTS/CROSS-APPELLEES APPEAL FROM THE BENTON COUNTY CIRCUIT COURT V. [NO. 04CV-17-1591]

PRECISION FOUNDATION HONORABLE JOHN R. SCOTT, SPECIALTIES & FLOW RITE JUDGE DRAINAGE SOLUTIONS, INC. APPELLEE/CROSS-APPELLANT AFFIRMED ON DIRECT APPEAL; REVERSED AND REMANDED ON CROSS-APPEAL

KENNETH S. HIXSON, Judge

This appeal arises from an order and judgment awarding the appellee/cross-appellant,

Precision Foundation Specialties & Flow Rite Drainage Solution, Inc. (“PFS”), damages for

breach of contract against the appellants/cross-appellees, John Ray Dye and Bobby Jo Dye

(collectively the “Dyes”) for a cause of action arising from a residential-construction repair.

The Dyes argue that (1) PFS failed to strictly comply with the statutory notice requirement

in Ark. Code Ann. § 18-44-115 (Supp. 2021), which precluded a judgment in its favor; (2)

the contract is usurious, which voids the contract; and (3) the jury’s viewing of the residence

in question deprived them of a fair trial because the deficiencies in PFS’s work product were

concealed. PFS cross-appeals, arguing that it should have been awarded attorney’s fees as a

matter of law and contract. We affirm on appeal, but we reverse and remand on cross-appeal. I. Background Facts

The Dyes own a residence in Pea Ridge, Arkansas. The two-story residence was

constructed approximately thirty years ago. The floors in some areas of the residence were

uneven or sagging. The Dyes contacted PFS to inspect the floors and the crawl space to

determine the cause of the problem.

PFS, a contractor, inspected the residence, including the floors and the crawl space.

PFS found that the residence was built using a pier and beam construction method. Upon

inspection, PFS found that some of the trusses supporting the residence were sagging or

twisting between piers or pedestals and that some of the shims on top of the pedestals had

compressed, causing the floors to be uneven.

The Dyes entered into a contract with PFS for construction services on the Dyes’

single-family residence (the “Contract”) on November 21, 2016. Pertinent to this appeal,

the scope of services and schedule of pricing included:

Removal of existing compressed shims on all existing pedestals in between existing pedestals in crawl space to include 4” 5000 psi base pads, CMU block and TIVAR shims, installation of new 14 feet of auxiliary beam under kitchen area to include pedestals. Total sum of the project of $7,500.00 with a security deposit in the amount of $3,750.00 to be paid at the contract signing. Balance to be paid in full upon completion in the amount of $3,750.00.

And the Contract provided the following regarding costs of collection:

Section 3.6: Client [the Dyes] will reimburse PFS, Inc. for all time spent and expenses (including fees of any attorney, collection agency, and/or court costs) incurred in connection with collecting any delinquent account.

2 The Dyes paid $3,750 to PFS when they entered into the Contract. The work

commenced a few weeks later, and PFS submitted an invoice on December 20, 2016, stating

that the work was complete and that payment was due upon receipt in accordance with the

payment provision in the Contract. Mr. Dye responded to the request for payment via email

and requested further documentation, including photographs of the repair work. On

December 21, 2016, PFS sent Mr. Dye photographs of the repairs as requested.

Subsequently, the parties engaged in further email communications regarding final payment;

however, despite Mr. Dye’s acknowledgment that he owed PFS money, the Dyes never paid

the balance of the invoice.

On January 10, 2017, PFS sent the Dyes a notice of intent to file a mechanics’ and

materialmen’s lien. On January 20, 2017, PFS filed the lien against the Dyes’ residence

alleging an outstanding balance, including late fees pursuant to the Contract, in the amount

of $6,114.27. PFS filed its complaint against the Dyes on August 25, 2017, for breach of

contract and to enforce the lien on the property. The Dyes filed an answer wherein they

denied that they were in breach of contract. The Dyes also filed a counterclaim alleging PFS

was in breach of contract for PFS’s failure to provide construction services that met the

implied warranty of workmanlike construction as well as a violation of the Arkansas

Deceptive Trade Practices Act (ADTPA) claiming that PFS’s contract was usurious.

Additionally, the Dyes protested the lien filed on their residence and sought a declaration

3 from the circuit court that PFS had failed to comply with the statutory notice provisions of

Ark. Code Ann. § 18-44-115.1

On February 23, 2018, the Dyes filed a motion for partial summary judgment alleging

that as a matter of law, PFS’s contract was unenforceable for its failure to comply with the

notice requirements of Ark. Code Ann. § 18-44-115, and because the late fees included in

the Contract are usurious. PFS responded, arguing that it qualified for the “direct sale”

exemption to the notice requirements of the statute and that the Contract was not usurious

in that the late fees were a permissible penalty for the Dyes’ failure to pay. The Dyes filed a

reply contending that (1) PFS did not qualify for the “direct sale” exemption because the

exemption had been subsequently clarified by our legislature to preclude contractors like

PFS and that the clarification should be applied retroactively to this contract, and (2) the

charges were a mere cloak for usury because they were recurring in nature rather than a one-

time penalty.

The circuit court held a hearing on the Dyes’ motion for partial summary judgment,

and on May 23, 2018, entered an order denying the motion. Specifically, the court held that

PFS was entitled to the “direct sale” exemption; therefore, the statutory notice was not

required. The court further found, contrary to the contention of retroactivity by the Dyes,

that the effective date of Act 808 of 2017, which amended Ark. Code Ann. § 18-44-115 to

1 The lien was subsequently discharged by the agreement of the parties for noncompliance with Ark. Code Ann. § 18-44-118 (Repl. 2018) for reasons that are not pertinent to the issues in this appeal.

4 explicitly require residential contractors to provide the important notice, was August 1, 2017,

and should not be applied retroactively. Regarding late fees, the circuit court cited supreme

court precedent in Hayes v. First National Bank of Memphis, 256 Ark. 328, 507 S.W.2d 701

(1974), which held that penalties to induce prompt payment are free from usury; therefore,

the Contract was not void. The court, however, did find that the late fees imposed by the

Contract were unconscionable and dismissed the portion of PFS’s complaint attempting to

collect the late fees.

The case proceeded to a two-day jury trial on October 29–30, 2018. In a pretrial

motion, the Dyes requested that the jury be transported to their residence for a visual

inspection, which the circuit court granted. Therefore, after the close of testimony from two

experts as well as Mr. Dye and a representative of PFS, the circuit judge led the jury, silently

and in a single-file line, through the residence at the Dyes’ request. Ultimately, the jury

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dye v. Precision Found. Specialties & Flow Rite Drainage Sols., Inc.
2025 Ark. App. 183 (Court of Appeals of Arkansas, 2025)
Morrnad Enters., LLC v. sachs/haynes 503, LLC
2022 Ark. App. 451 (Court of Appeals of Arkansas, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ark. App. 220, 646 S.W.3d 168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dye-v-precision-foundation-specialties-flow-rite-drainage-solutions-arkctapp-2022.