Diversified Mortgage Investors v. Lloyd D. Blaylock General Contractor, Inc.

576 S.W.2d 794, 22 Tex. Sup. Ct. J. 146, 1978 Tex. LEXIS 369
CourtTexas Supreme Court
DecidedDecember 20, 1978
DocketB-6725
StatusPublished
Cited by90 cases

This text of 576 S.W.2d 794 (Diversified Mortgage Investors v. Lloyd D. Blaylock General Contractor, Inc.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diversified Mortgage Investors v. Lloyd D. Blaylock General Contractor, Inc., 576 S.W.2d 794, 22 Tex. Sup. Ct. J. 146, 1978 Tex. LEXIS 369 (Tex. 1978).

Opinion

SAM D. JOHNSON, Justice.

ON MOTION FOR REHEARING

We grant the motion for rehearing filed by DMI only insofar as it deals with that part of our previous opinion relating to the issue of equitable subrogation. We therefore set aside our former judgment, withdraw our former opinion, and substitute the following in its place.

This case requires determination of the relative priorities of mechanic’s and materi-alman’s liens, deed of trust liens, and a vendor’s lien to which the mortgagee may be equitably subrogated. Lloyd D. Blaylock General Contractor, Inc. and Lloyd D. Blay-lock, individually, (hereinafter collectively referred to as “Blaylock”) hold duly perfected mechanic’s liens on certain properties pursuant to a construction contract with Dollar Inns of America, Inc. (“Dollar Inns”) and K. R. Riley. Diversified Mortgage Investors (“DMI”) holds deed of trust liens on these properties through financing arrangements whereby it provided permanent financing to Dollar Inns for the purchase of land, the purchasing of a prior vendor’s lien, and the construction of two motels on these properties. All parties sought a declaration of the priorities of their claims. In addition, Blaylock sought to recover the balance due on the construction contract and to foreclose the mechanic’s liens on the properties. In the alternative, Blaylock sought the right to follow the proceeds of the deed of trust foreclosure sales to acquire payment of the construction contract. The trial court rendered judgment against Dollar Inns and Riley, holding them liable on the construction contract; however, the trial court ruled that Blaylock take nothing from DMI because the deed of trust liens were superior to the mechanic’s liens. The court of civil appeals reversed and rendered, holding that DMI’s deed of trust mortgages were superior to the mechanic’s liens only to the extent such mortgages secured the purchase money, not the construction loans. Furthermore, the intermediate court held *797 that Blaylock could recover $204,776.29 from DMI out of the proceeds of the deed of trust foreclosure sales. 548 S.W.2d 924. We reverse the judgment of the court of civil appeals as to the Fort Worth property and affirm the judgment of the trial court. We modify the judgment of the court of civil appeals as to the Irving property and, as modified, such judgment is affirmed.

The liens involved in the instant case arise from the financing and construction of two Dollar Inns motels — one in Fort Worth and one in Irving. Although the facts are similar as to each location, the lien priorities must be determined independently for each piece of property; therefore, the facts relative to construction and financing on the two pieces of property will be discussed separately.

FORT WORTH PROPERTY

Construction:

In the fall of 1972 Blaylock and Dollar Inns began negotiations for construction of two motels. Thereafter, on December 29, 1972, Dollar Inns and Blaylock entered into a preliminary agreement whereby Blaylock agreed to construct motels on both the Fort Worth and Irving sites pursuant to a general construction contract to be executed at a later date. At this time, Dollar Inns further directed Blaylock to proceed with construction on the land as much as possible until the building permit could be obtained. Pursuant to such an agreement, subcontractors of Blaylock began subsurface investigation of the site on January 24, 1973. Such work involved the drilling of core bor-ings and analysis of the content of the soil. Thereafter, between January 25, 1973 and March 1, 1973, another subcontractor of Blaylock performed job site engineering and topographical survey work upon the site, which entailed the placing of various stakes and iron rods to locate drives, grades, and building sites upon the land. By March 1, 1973 approximately one hundred fifty stakes and eight iron rods were placed on the land and stood visibly one to three feet above the ground. During this period, on February 21,1973, Blaylock and Dollar Inns finalized their agreement in a written construction contract. On March 5, 1973 lumber for batter boards was delivered, and delivery of fill dirt was begun. Erection of the batter boards was begun on the same day as delivery and such work was completed by March 9, 1973. Batter boards are L-shaped structures which stand two feet off the ground and extend five feet in each direction. Such boards define the corners of the building and are preparatory to building the foundation. At the same time the batter boards were being erected, and continuing for approximately forty-five days, Blaylock began spread operations with the fill dirt being delivered. Such operations entailed the moving of dirt upon the land to prepare the ground for the foundation and the grading of the lot and involved six trucks and front-end loaders working on the property. Excavation for a retaining wall was also begun. As of March 9, 1973 all batter boards were erected, and a sign was placed at the job site indicating that construction of a Dollar Inns motel was in progress. Thereafter, on March 16, 1973, a building permit was obtained for the Fort Worth project. After the permit was received, foundation work was begun by a subcontractor of Blaylock. Such foundation work required the subcontractor to excavate for perimeter beans around the foundation and to lay the concrete foundation upon the dirt pad formed during the spread operations. After the completion of construction, on January 19, 1974, Blaylock filed its mechanic’s lien pursuant to Article 5453, Texas Revised Civil Statutes Annotated, to secure the unpaid portion of the construction contract relative to the Fort Worth project, amounting to $68,009.29.

Financing:

In November 1972 Dollar Inns began negotiations with DMI concerning permanent financing for the construction of two motels. Similar negotiations were conducted with Palomar Mortgage Investors in January 1973. On December 11, 1972 Dollar Inns, acting through K. R. Riley, contracted *798 to purchase property in Fort Worth from J. M. Loffland, Jr., trustee. 1 Under such contract of sale, Dollar Inns placed $5,000 earnest money in escrow. Later, Dollar Inns placed an additional $5,000 in escrow in order to extend the closing date beyond the January 15, 1975 closing date specified in the contract of sale. The $10,000 earnest money was later applied toward the total cost of closing. On February 16, 1973 Dollar Inns and Palomar executed a loan agreement by which Palomar agreed to provide interim financing for the purchase of the Fort Worth property and construction of a motel thereon. Palomar, in exchange for its funds, received Dollar Inns’ promissory note in the amount of $1,200,000 and secured the same through a deed of trust covering the Fort Worth property and improvements erected thereon. Such loan agreement incorporated by reference a commitment of DMI dated November 10, 1972 and a commitment of Palomar dated January 15, 1973. In such commitments and a tri-party agreement executed by Dollar Inns, DMI, and Palomar, it was agreed that Palomar would provide interim financing for the purchase of land and construction of the motel and that DMI would provide permanent financing after construction was completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trimcos, LLC v. Compass Bank
Court of Appeals of Texas, 2021
Whitcomb v. Lane (In re Whitcomb)
599 B.R. 908 (S.D. Texas, 2019)
Denco CS Corporation v. Body Bar, LLC
445 S.W.3d 863 (Court of Appeals of Texas, 2014)
Lyda Swinerton Builders, Inc. v. Cathay Bank
409 S.W.3d 221 (Court of Appeals of Texas, 2013)
I-10 Colony, Inc. v. Chao Kuan Lee, Li Yang Lee, Li Hsiang Chang
393 S.W.3d 467 (Court of Appeals of Texas, 2012)
Rupa Kothari v. Refugio Oyervidez
373 S.W.3d 801 (Court of Appeals of Texas, 2012)
Bank of America v. Babu
340 S.W.3d 917 (Court of Appeals of Texas, 2011)
Pineridge Associates, L.P. v. Ridgepine, LLC
337 S.W.3d 461 (Court of Appeals of Texas, 2011)
Panorama Construction, Inc. v. Farm Credit Services
733 F. Supp. 2d 748 (N.D. Texas, 2010)
In Re Demay International, LLC
431 B.R. 164 (S.D. Texas, 2010)
Sheppard v. Interbay Funding, LLC
305 S.W.3d 102 (Court of Appeals of Texas, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
576 S.W.2d 794, 22 Tex. Sup. Ct. J. 146, 1978 Tex. LEXIS 369, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diversified-mortgage-investors-v-lloyd-d-blaylock-general-contractor-tex-1978.