Markway Construction Co. v. Kirchenbauer

769 S.W.2d 836, 1989 Mo. App. LEXIS 635, 1989 WL 47658
CourtMissouri Court of Appeals
DecidedMay 9, 1989
DocketNo. 55023
StatusPublished
Cited by1 cases

This text of 769 S.W.2d 836 (Markway Construction Co. v. Kirchenbauer) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Markway Construction Co. v. Kirchenbauer, 769 S.W.2d 836, 1989 Mo. App. LEXIS 635, 1989 WL 47658 (Mo. Ct. App. 1989).

Opinion

HAMILTON, Judge.

Lary and Concetta Kirchenbauer (hereinafter cited as Kirchenbauers) appeal from a [837]*837judgment rendered by the trial court in favor of Markway Construction Company, Inc. (hereinafter cited as Markway). Mark-way cross-appeals. Markway brought this action to recover the balance due on a contract between the parties for the remodeling of the Kirchenbauers’ residence. Following a non-jury trial, the trial court awarded Markway, in addition to prejudgment interest and costs, the principal sum of $10,245.08, an amount reflecting $12,-302.79 owed on the contract, plus $5,335.29 owed for work performed pursuant to unsigned change orders, reduced by $7,400 as a set-off for Markway’s delays and un-workmanlike services.

On appeal, the Kirchenbauers contend that the trial court erred in: (1) deeming Markway’s pleadings amended to conform to the evidence and granting Markway’s post-trial motion to amend its pleadings with respect to amounts owed to Markway as a result of unpaid unsigned change orders, and (2) awarding Markway $5,335.29 for work performed pursuant to unsigned change orders. In its cross-appeal, Mark-way contends that the trial court erred in awarding the Kirchenbauers the sum of $7,200 for costs incurred as a result of Markway’s delays. We affirm in part and vacate in part.

On May 9, 1984, the Kirchenbauers and Markway entered into a written contract for extensive remodeling of the Kirchen-bauers’ residence. The Kirchenbauers agreed to compensate Markway on a cost-plus basis defined as construction costs incurred plus ten percent of that figure as overhead and five percent of costs plus overhead as profit. The contract also provided that “[t]he Owner may make Changes in the Work as provided in the Contract Documents. The Contractor shall be reimbursed for Changes in the Work on the basis of Cost of Work as defined in [the contract]”.

In their first point on appeal, the Kirchenbauers claim that the trial judge erred in allowing Markway to amend its petition to conform to the evidence. The amendment consisted of a claim for $5,335.29 in damages as a result of unpaid unsigned change orders. The Kirchen-bauers argue the amendment was improper because the evidence adduced at trial regarding the unsigned change orders was relevant to the issue of whether Markway had substantially performed its obligations under the terms of the contract. Thus, Kirchenbauers contend, because the evidence relating to unsigned change orders raised no new issues, amendment of the petition was improper.

Markway responds that the original petition included no claim regarding the unsigned change orders. A review of the original petition supports Markway’s contention. In addition, evidence was adduced at trial, without objection, regarding the work completed pursuant to unsigned change orders. Moreover, the trial court admitted the unsigned change orders, without objection.

A trial court’s grant of leave to amend a petition is wholly discretionary; it may not be overturned on appeal absent a clear abuse of discretion. Conchola v. Kraft, 575 S.W.2d 792, 794 (Mo.App.1978). The same standard applies to the amendment of a prayer for damages. Id.; Prewitt v. Continental Ins. Co., 538 S.W.2d 902, 906 (Mo.App.1976).

Kirchenbauers rely on three cases for the proposition that evidence admitted without objection may result in an amendment to the pleading by implied consent of the parties only when such evidence bears on a new issue, not on an issue already in the case by reason of the initial pleading: Brazell v. St. Louis Southwestern Ry. Co., 632 S.W.2d 277, 281 (Mo.App.1982); Smith v. Heisserer, 609 S.W.2d 485, 486 (Mo.App.1980); Gee v. Gee, 605 S.W.2d 815, 817 (Mo.App.1980). None of these cases assists the Kirchenbauers, however, because they admit the original petition failed to include a claim for reimbursement for work and services performed pursuant to the unsigned change orders. Thus, any evidence pertaining to the issue of payment [838]*838for the unsigned change orders necessarily raises a new issue. The first point is, therefore, denied.

Kirchenbauers’ next claim that no substantial evidence supports the trial court’s finding that Markway was entitled to $5,335.29 for the work performed pursuant to the unsigned change orders. With respect to change orders in general, the trial court found:

The contract also provided for “Changes in the Work” and modifications of contract work by agreement of the parties on the same cost-plus basis. The parties did not agree to and adopt the “General Conditions of the Contract for Construction,” A.I.A. Document A 201, thus, there was no formal agreement as to the use of written or signed “Change Orders”.

The trial court further found:

The parties encountered many changes in the scope of the initially agreed upon work. Plaintiff performed additional work at the request of or with the acquiescence by Defendants, all as contained in twenty-five (25) separate change orders attached to Plaintiff’s Petition and marked as Exhibit B to that Petition. Defendants did not sign of [sic] formally agree to certain change orders totalling $5,335.29 for work performed under said change orders. Defendants, however, accepted and adopted the work performed under said change orders as a routine practice and without objection.

Based upon the foregoing factual findings, the trial court concluded

... that Plaintiffs are entitled to recover for the $5,335.29 as for work performed by Plaintiff as set out in the change orders, work which all credible testimony indicated was accepted by Defendants’ words and actions, as well as the actions of the Defendants’ representative, Mr. Hastings.

Kirchenbauers argue that the unsigned change orders constitute a modification to the contract and that the assent of both parties, allegedly lacking here, is necessary to create a valid modification. As an initial matter, the work performed pursuant to change orders constitutes no modification because the contract unambiguously contemplates “changes” in the scope of the work and provides a basis to pay for the work performed pursuant to the change orders. Moreover, the contract fails to require written, signed change orders as a prerequisite to payment for performing work designated as a change in the scope of the contract.

Evidence adduced at trial disclosed that, as a practice, the contractor sought to obtain the Kirchenbauers’ signature on a written change order prior to seeking payment for the work performed. Evidence also revealed that Markway often performed additional work prior to obtaining Kirchenbauers’ signature on a change order. In addition, evidence showed that, with the exception of some expensive programmable thermostats, the Kirchenbauers accepted the work performed pursuant to the unsigned change orders and at no time expressed any complaints with respect to either the cost or the workmanship.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greene County Concerned Citizens v. Board of Zoning Adjustment
873 S.W.2d 246 (Missouri Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
769 S.W.2d 836, 1989 Mo. App. LEXIS 635, 1989 WL 47658, Counsel Stack Legal Research, https://law.counselstack.com/opinion/markway-construction-co-v-kirchenbauer-moctapp-1989.