GRAU CONTRACTING, INC. v. CAPTIVA LAKE INVESTMENTS, LLC, Appellant/Cross-Respondent, MISSOURI BUILDERS SERVICE, INC., Respondent/Cross-Appellant, QUESTEC CONTRUCTORS, INC., BUTLER SUPPLY, INC., HOUSE OF CARPET, INC., and MEYER ELECTRIC CO., INC.

CourtMissouri Court of Appeals
DecidedMarch 10, 2014
DocketSD32382 and SD32406 (Consolidated)
StatusPublished

This text of GRAU CONTRACTING, INC. v. CAPTIVA LAKE INVESTMENTS, LLC, Appellant/Cross-Respondent, MISSOURI BUILDERS SERVICE, INC., Respondent/Cross-Appellant, QUESTEC CONTRUCTORS, INC., BUTLER SUPPLY, INC., HOUSE OF CARPET, INC., and MEYER ELECTRIC CO., INC. (GRAU CONTRACTING, INC. v. CAPTIVA LAKE INVESTMENTS, LLC, Appellant/Cross-Respondent, MISSOURI BUILDERS SERVICE, INC., Respondent/Cross-Appellant, QUESTEC CONTRUCTORS, INC., BUTLER SUPPLY, INC., HOUSE OF CARPET, INC., and MEYER ELECTRIC CO., INC.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GRAU CONTRACTING, INC. v. CAPTIVA LAKE INVESTMENTS, LLC, Appellant/Cross-Respondent, MISSOURI BUILDERS SERVICE, INC., Respondent/Cross-Appellant, QUESTEC CONTRUCTORS, INC., BUTLER SUPPLY, INC., HOUSE OF CARPET, INC., and MEYER ELECTRIC CO., INC., (Mo. Ct. App. 2014).

Opinion

GRAU CONTRACTING, INC., ) ) Plaintiff, ) ) vs. ) ) CAPTIVA LAKE INVESTMENTS, LLC, ) ) Appellant/Cross-Respondent, ) ) Nos. SD32382 and SD32406 MISSOURI BUILDERS SERVICE, INC., ) Consolidated ) Respondent/Cross-Appellant, ) ) FILED: March 10, 2014 QUESTEC CONTRUCTORS, INC., ) BUTLER SUPPLY, INC., ) HOUSE OF CARPET, INC., ) and MEYER ELECTRIC CO., INC., ) ) Respondents. )

APPEAL FROM THE CIRCUIT COURT OF CAMDEN COUNTY

Honorable Bernhardt C. Drumm, Jr., Judge

AFFIRMED

We affirm a judgment enforcing mechanics’ liens and granting them priority

over a construction lender’s successor in interest. Background

This litigation arises from the failed Majestic Pointe condominium

development, a project located on a several-acre point jutting into the Lake of the

Ozarks. By August 2005, the developer had nearly finished one condo building and

planned to build the next one, but the project’s lender did not wish to finance

additional construction.

Discussions with National City Bank (“Bank”) led to its agreement to finance

finish work on the existing building and construction of another high-rise condo.

More specifically, this March 2006 construction loan agreement contemplated

construction of “a sixty-one (61) unit condominium tower known as ‘Building 4’”;

interior finish of “three unfinished units of a twenty-four (24) unit condominium

tower known as ‘Building 5”; and a construction deed of trust in favor of Bank to

secure a $20 million construction loan. This deed of trust was recorded on March

15, 2006.

The development failed. Mechanics’ liens and enforcement actions were filed

by Respondents, providers of work and material at Building 4 after Bank recorded its

deed of trust. Later, Appellant (“Captiva”) bought Bank’s construction loan,

foreclosed the deed of trust, acquired the property, and was substituted for Bank in

the mechanics’ lien litigation.

In a series of partial summary judgments, the trial court granted mechanics’

liens to Respondents and found “under the first spade rule and the waiver doctrine,

the mechanic’s liens of [Respondents] are prior and superior to the interest of

2 Captiva, which is derived from [Bank’s] deed of trust ….” Later, § 431.1801 claims for

interest and attorney fees were bench tried, yielding a final judgment from which

Captiva appeals and Respondent Missouri Builders cross-appeals. We consider

Captiva’s complaints first.

Captiva’s Appeal

Point I – First Spade Priority

Captiva challenges the summary judgment determination that Respondents

had first spade priority over Bank’s deed of trust. Summary judgment is proper

when there is no genuine issue as to any material fact and the movant is entitled to

judgment as a matter of law. ITT Commercial Finance Corp. v. Mid-America

Marine Supply Corp., 854 S.W.2d 371, 376 (Mo. banc 1993). “Because our

review is de novo, the trial court’s order may be affirmed in this Court on an entirely

different basis than that posited at trial.” Id. at 387-88.

Lien Priorities – The DeGeorge Case

Our supreme court addressed priorities of mechanics’ liens and deeds of trust

most recently in Bob DeGeorge Associates, Inc. v. Hawthorn Bank, 377

S.W.3d 592 (Mo. banc 2012). Deeds of trust are subject to Missouri’s recording

statutes (id. at 597), but mechanics’ liens are not “because they arise by operation of

statute[s]” which “are construed favorably to uphold the rights of laborers and

materialmen.” Id. at 598. “Unlike recording an instrument under the recording

statutes, filing a mechanic’s lien is irrelevant for the purpose of determining first-in-

time priority between competing encumbrances on real property.” Id.

1 Also called the Private Prompt Payment Act. Statutory citations are to RSMo 2000. 3 Two statutory provisions govern the priority of a mechanic’s lien against other encumbrances on real property. For encumbrances on the land, the “first spade rule” under section 429.060 gives the mechanic’s lien relation-back priority to the date when work commenced …. So long as a mechanic’s lien arises on the land and is filed properly, it will have priority over any third-party encumbrance attaching after the date work began. In contrast to a mechanic’s lien attached to the land, section 429.050 gives a mechanic’s lien attached to the structure or improvements priority over all other encumbrances ….

Id. (internal quotation and citations omitted). Thus, “priority of a mechanic’s lien

will vary based on the type of property. A mechanic’s lien on land is given relation-

back priority under section 429.060, whereas a mechanic’s lien on a building,

erection, or improvement is given complete priority under section 429.050.” Id. at

598-99.2

As to the land (as opposed to the complete priority on improvements), “a deed

of trust recorded after the commencement of work on a project is inferior to any

mechanic’s liens arising on the land from that work.” Id. at 599. This is known as

the “first spade rule” for mechanics’ liens. Id. “‘All mechanics’ liens commence at

the date of the first stroke of the axe or spade, and continue in the erection of [a

structure], without regard to the time of their being filed, or of the doing of the work

or furnishing the materials.’” Id. (quoting Schroeter Bros. Hardware Co. v.

Croatian “Sokol” Gymnastic Ass’n, 58 S.W.2d 995, 1003 (Mo. 1932)).

2 By its terms, § 429.050 limits the “complete” priority noted in DeGeorge to “buildings, erections or improvements for which [lienable items] were furnished or the work was done ….”

4 Captiva’s Arguments / Analysis

Captiva offers alternative challenges to the trial court’s finding that these

mechanics’ liens had first spade priority over Bank’s deed of trust.

First, Captiva characterizes § 443.055, which governs future advance deeds of

trust, as a statutory exception to first spade priority. No support is cited for this

proposition, which Captiva seems to concede is contrary to recent decisions of this

court. See Altom Constr. Co. v. BB Syndication Servs., Inc., 359 S.W.3d 146,

150-51 (Mo.App. 2012); Glenstone Block Co. v. Pebworth, 330 S.W.3d 98, 102

(Mo.App. 2010). Indeed, Captiva acknowledges elsewhere in its brief the line of

cases holding construction liens to be inferior to mechanics’ liens, both before and

since adoption of § 443.055.

Still, Captiva urges that no prior case has directly considered whether § 443.055

trumps the first spade rule. While this may be so, we cannot fail to note a law

student’s keen foresight three decades ago regarding § 443.055 in this context:

The priority rules of the new statute [§ 443.055] conflict with sections 429.055 and 429.060, which grant mechanics’ lienors priority as to the improvements for which they contributed labor or capital. Good arguments exist for applying either law to resolve priority disputes between construction mortgagees and mechanics’ lienors. The legislature, however, neither expressly stipulated which would apply nor expressly overruled H.B. Deal [Constr. Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fru-Con/Fluor Daniel Joint Venture v. Corrigan Bros., Inc.
154 S.W.3d 330 (Missouri Court of Appeals, 2004)
ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp.
854 S.W.2d 371 (Supreme Court of Missouri, 1993)
Glenstone Block Co. v. Pebworth
330 S.W.3d 98 (Missouri Court of Appeals, 2010)
Drilling Service Co. v. Baebler
484 S.W.2d 1 (Supreme Court of Missouri, 1972)
H. B. Deal Construction Co. v. Labor Discount Center, Inc.
418 S.W.2d 940 (Supreme Court of Missouri, 1967)
Altom Construction Co. v. BB Syndication Services, Inc.
359 S.W.3d 146 (Missouri Court of Appeals, 2012)
Schroeter Bros. Hardware Co. v. Croatian "Sokol" Gymnastic Ass'n
58 S.W.2d 995 (Supreme Court of Missouri, 1933)
Tate v. AutoZoners, L.L.C.
363 S.W.3d 179 (Missouri Court of Appeals, 2012)
Bob DeGeorge Associates, Inc. v. Hawthorn Bank
377 S.W.3d 592 (Supreme Court of Missouri, 2012)
Greasel Conversions, Inc. v. Massa
399 S.W.3d 456 (Missouri Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
GRAU CONTRACTING, INC. v. CAPTIVA LAKE INVESTMENTS, LLC, Appellant/Cross-Respondent, MISSOURI BUILDERS SERVICE, INC., Respondent/Cross-Appellant, QUESTEC CONTRUCTORS, INC., BUTLER SUPPLY, INC., HOUSE OF CARPET, INC., and MEYER ELECTRIC CO., INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/grau-contracting-inc-v-captiva-lake-investments-llc-moctapp-2014.