Grau Contracting, Inc. v. Captiva Lake Investments, LLC

429 S.W.3d 472, 2014 WL 911339, 2014 Mo. App. LEXIS 243
Missouri Court of Appeals·Decided March 10, 2014·No. Nos. SD 32382, SD 32406·Published·Cited by 1 cases

Opinion

DANIEL E. SCOTT, J.

We affirm a judgment enforcing mechanics’ liens and granting them priority over a construction lender’s successor in interest.

Background

This litigation arises from the failed Majestic Pointe condominium development, a project located on a several-acre point jutting into the Lake of the Ozarks. By August 2005, the developer had nearly finished one condo building and planned to build the next one, but the project’s lender did not wish to finance additional construction.

Discussions with National City Bank (“Bank”) led to its agreement to finance finish work on the existing building and construction of another high-rise condo. More specifically, this March 2006 construction loan agreement contemplated construction of “a sixty-one (61) unit condominium tower known as ‘Building 4’”; interior finish of “three unfinished units of a twenty-four (24) unit condominium tower known as ‘Building 5’ and a construction deed of trust in favor of Bank to secure a $20 million construction loan. This deed of trust was recorded on March 15, 2006.

The development failed. Mechanics’ liens and enforcement actions were filed by Respondents, providers of work and material at Building 4 after Bank recorded its deed of trust. Later, Appellant (“Cap-tiva”) bought Bank’s construction loan, foreclosed the deed of trust, acquired the property, and was substituted for Bank in the mechanics’ lien litigation.

In a series of partial summary judgments, the trial court granted mechanics’ liens to Respondents and found “under the first spade rule and the waiver doctrine, the mechanic’s liens of [Respondents] are prior and superior to the interest of Capti-[474]*474va, which is derived from [Bank’s] deed of trust_” Later, § 431.1801 claims for interest and attorney fees were bench tried, yielding a final judgment from which Cap-tiva appeals and Respondent Missouri Builders cross-appeals. We consider Cap-tiva’s complaints first.

Captiva’s Appeal

Point I — First Spade Priority

Captiva challenges the summary judgment determination that Respondents had first spade priority over Bank’s deed of trust. Summary judgment is proper when there is no genuine issue as to any material fact and the movant is entitled to judgment as a matter of law. ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp., 854 S.W.2d 371, 376 (Mo.banc 1993). “Because our review is de novo, the trial court’s order may be affirmed in this Court on an entirely different basis than that posited at trial.” Id. at 387-88.

Lien Priorities — The DeGeorge Case

Our supreme court addressed priorities of mechanics’ liens and deeds of trust most recently in Bob DeGeorge Associates, Inc. v. Hawthorn Bank, 377 S.W.3d 592 (Mo. banc 2012). Deeds of trust are subject to Missouri’s recording statutes (id. at 597), but mechanics’ liens are not “because they arise by operation of statute[s]” which “are construed favorably to uphold the rights of laborers and material-men.” Id. at 598. “Unlike recording an instrument under the recording statutes, filing a mechanic’s lien is irrelevant for the purpose of determining first-in-time priority between competing encumbrances on real property.” Id.

Two statutory provisions govern the priority of a mechanic’s lien against other encumbrances on real property. For encumbrances on the land, the “first spade rule” under section 429.060 gives the mechanic’s lien relation-back priority to the date when work commenced.... So long as a mechanic’s lien arises on the land and is filed properly, it will have priority over any third-party encumbrance attaching after the date work began. In contrast to a mechanic’s lien attached to the land, section 429.050 gives a mechanic’s lien attached to the structure or improvements priority over all other encumbrances....

Id. (internal quotation and citations omitted). Thus, “priority of a mechanic’s lien will vary based on the type of property. A mechanic’s lien on land is given relation-back priority under section 429.060, whereas a mechanic’s lien on a building, erection, or improvement is given complete priority under section 429.050.” Id. at 598-99.2

As to the land (as opposed to the complete priority on improvements), “a deed of trust recorded after the commencement of work on a project is inferior to any mechanic’s liens arising on the land from that work.” Id. at 599. This is known as the “first spade rule” for mechanics’ liens. Id. “ ‘All mechanics’ liens commence at the date of the first stroke of the axe or spade, and continue in the erection of [a structure], without regard to the time of their being filed, or of the doing of the work or furnishing the materials.’ ” Id. (quoting Schroeter Bros. Hardware Co. v. Croatian “Sokol” Gymnastic Ass’n, 332 Mo. 440, 58 S.W.2d 995, 1003 (1932)).

[475]*475 Captiva’s Arguments/Analysis

Captiva offers alternative challenges to the trial court’s finding that these mechanics’ liens had first spade priority over Bank’s deed of trust.

First, Captiva characterizes § 443.055, which governs future advance deeds of trust, as a statutory exception to first spade priority. No support is cited for this proposition, which Captiva seems to concede is contrary to recent decisions of this court. See Altom Constr. Co. v. BB Syndication Servs., Inc., 359 S.W.3d 146, 150-51 (Mo.App.2012); Glenstone Block Co. v. Pebworth, 330 S.W.3d 98, 102 (Mo. App.2010). Indeed, Captiva acknowledges elsewhere in its brief the line of cases holding construction liens to be inferior to mechanics’ liens, both before and since adoption of § 443.055.

Still, Captiva urges that no prior case has directly considered whether § 443.055 trumps the first spade rule. While this may be so, we cannot fail to note a law student’s keen foresight three decades ago regarding § 443.055 in this context:

The priority rules of the new statute [§ 443.055] conflict with sections 429.055 and 429.060, which grant mechanics’ lienors priority as to the improvements for which they contributed labor or capital. Good arguments exist for applying either law to resolve priority disputes between construction, mortgagees and mechanics’ lienors. The legislature, however, neither expressly stipulated which would apply nor expressly overruled H.B. Deal [Constr. Co. v. Labor Discount Center, Inc., 418 S.W.2d 940 (Mo.1967), which granted mechanics liens priority over construction mortgage advances] and its progeny. The mechanics’ lien statute will likely still control.

Free access — add to your briefcase to read the full text and ask questions with AI

Grau Contracting, Inc. v. Captiva Lake Investments, LLC, 429 S.W.3d 472, 2014 WL 911339, 2014 Mo. App. LEXIS 243 (Mo. Ct. App. 2014).

429 S.W.3d 472 (Grau Contracting, Inc. v. Captiva Lake Investments, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Delise diaz v. Autozoners, LLC, D/B/A Autozone
484 S.W.3d 64 (Missouri Court of Appeals, 2015)