Altom Construction Co. v. BB Syndication Services, Inc.

359 S.W.3d 146, 2012 Mo. App. LEXIS 184, 2012 WL 503600
CourtMissouri Court of Appeals
DecidedFebruary 15, 2012
DocketSD 30966
StatusPublished
Cited by9 cases

This text of 359 S.W.3d 146 (Altom Construction Co. v. BB Syndication Services, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Altom Construction Co. v. BB Syndication Services, Inc., 359 S.W.3d 146, 2012 Mo. App. LEXIS 184, 2012 WL 503600 (Mo. Ct. App. 2012).

Opinion

NANCY STEFFEN RAHMEYER, Judge.

This appeal arises from a judgment entered by the Circuit Court of Taney County in favor of Altom Construction Company, LLC (“Altom”), and Great River Engineering of Springfield, Inc. (“Great River”), (collectively, “Respondents”), against Hollister Interchange Development Company, LLC (“HIDC”), Gage Excavating, LLC (“Gage”), and BB Syndication Services, Inc. (“BBSSI”). The trial court found BBSSI “made a future advance deed of trust and construction loan” and recorded its deed of trust after it “knew that employment of subcontractors by the general contractor was contemplated and that the mechanics and material providers who were to provide labor and materials might file mechanic’s liens against the property if their bills were not paid.” As such, the court determined Respondents’ liens to be superior to BBSSI’s loan. We affirm the judgment.

As this was a court-tried case, “the judgment of the trial court will be affirmed unless it is not supported by substantial evidence, it is against the weight of the *149 evidence, or it erroneously declares or applies the law.” Glenstone Block Co. v. Pebworth, 330 S.W.3d 98, 101 (Mo.App. S.D.2010). When exercising the power to set aside a decree or judgment on the ground that it is against the weight of the evidence, the appellate court should proceed with caution and with a firm belief that the decree or judgment is incorrect. Id.; Jerry Bennett Masonry, Inc. v. Crossland Const. Co. Inc., 171 S.W.3d 81, 88 (Mo.App. S.D.2005). To make a determination of the sufficiency of the evidence, this Court accepts as true all evidence and inferences that are favorable to the trial court’s judgment and disregards those inferences that are contrary. Bush Const. Machinery, Inc. v. Kansas City Factory Outlets, L.L.C., 81 S.W.3d 121, 122 (Mo.App. W.D.2002). The validity of the trial court’s judgment is presumed and the appellant carries the burden to demonstrate its incorrectness. Glenstone Block Co., 330 S.W.3d at 101.

Viewed in the light most favorable to the verdict, the following evidence was adduced at trial:

In 2007, Gage and HIDC 1 planned to build a water park, an events or convention center, and condominiums or time share units on real property located on the southern side of Hollister, Missouri. The total cost estimate of the development was to be approximately one hundred fifty-five million dollars. Gage and HIDC were given funding for the project from BBSSI. To secure funding from BBSSI, HIDC provided BBSSI with a presentation package including income projections, site plans, potential cost estimates, land value projections, and other commonly used information within the industry, and a partnership agreement with Wilderness Resort Group, the operating entity on the project. BBSSI provided the project with a loan in the amount of “the lesser of: (i) $21,690,-00.00 or (ii) the lesser of 75% of the appraised market value of the land as of completion of the proposed infrastructure construction or 100%) of the total costs of the Project including the cost of acquisition of the Real Property.” The parties dispute the purpose, character, and categorization of the loan.

HIDC and BBSSI entered into an agreement titled, “Interim Loan Agreement,” (“Interim Loan”), which was secured by a mortgage titled, “First Deed of Trust, Assignment of Leases and Rents and Fixture Filing,” (“Deed of Trust”); an advances agreement titled, “Interim Loan Disbursement Agreement,” (“Disbursement Agreement”); and BBSSI required Gage and HIDC to enter into an excavation agreement, drafted partially by BBSSI’s attorney, before they agreed to fund the project.

Altom and Great River understood the Deed of Trust to be a construction mortgage, a portion of which was to be used for the initial infrastructure improvements. The second page of the Deed of Trust reads, “This is a construction mortgage under Section 400.9.334, R.S.MO., as amended or renumbered.” The parties also executed the Interim Loan which provided an assignment by HIDC of its development rights and construction plans over to BBSSI. The Interim Loan did not segregate loan amounts between the land acquisition and initial infrastructure improvements and categorized itself as a “construction loan.” Similarly, the Disbursement Agreement did not differentiate *150 loan amounts between land acquisition and initial infrastructure improvements.

HIDC, through Gage, hired Altom as a subcontractor to begin excavation work on the property. Altom and Gage agreed on the blasting and excavation price of $2.40 per cubic yard, plus the cost of the pre-blast survey. Altom received its payments directly from Gage. Altom hired Explosive Contractors, Inc. (“ECI”) to provide the loading and discharging of explosives on the project. ECI provided Altom with blasting reports and such reports provided the cubic yard basis that, when multiplied by the $2.40 excavation cost per cubic yard, served as the disputed sum in Al-tom’s mechanic’s lien. Gage verified the blast reports to be true and accurate.

BBSSI hired its own inspectors, LM Consultants, to work with HIDC and monitor construction activities in order to verify the project’s progress. HIDC also entered into an agreement with Great River for civil infrastructure design and production of construction plans and specifications. Under this agreement, Great River produced thirty-two pages of design development plans and construction specifications that were at the 60% level of detail. Included in these plans were civil site plans, grading plans, utilities, sanitary sewer, storm water, water lines, gas lines, erosion control, and landscaping. Mel Eakins, of Great River, testified that the construction plans were no further than 66.5% complete. All invoices in connection with the water park project were included in the lien statement.

The project came to a standstill when the Interim Loan funds were expended and further financing did not go forward in spite of Gage’s continued attempts to obtain funding from BBSSI. Altom filed its petition to enforce its mechanic’s lien in May of 2009, naming BBSSI and trustee Michele McCue as parties regarding the Deed of Trust that BBSSI held on the real property. In July of 2009, Great River filed its petition to enforce a mechanic’s lien, also naming BBSSI as the mortgagee of the real property.

In its first point, BBSSI argues that it holds a purchase money lien on the real property that has priority over the mechanic’s liens held by Respondents even as to work done before the attachment of the purchase money lien. BBSSI argues that while the value of the loan was for $21.6 million, $17.5 million of that was used to purchase real property and should be treated as a purchase money lien. BBSSI’s entire argument rests on the assumption that a portion of the loan was for the purchase of property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
359 S.W.3d 146, 2012 Mo. App. LEXIS 184, 2012 WL 503600, Counsel Stack Legal Research, https://law.counselstack.com/opinion/altom-construction-co-v-bb-syndication-services-inc-moctapp-2012.