Bates & Associates, Inc. v. Providence Bank & Vision Ventures, LLC

CourtMissouri Court of Appeals
DecidedSeptember 17, 2019
DocketED106955
StatusPublished

This text of Bates & Associates, Inc. v. Providence Bank & Vision Ventures, LLC (Bates & Associates, Inc. v. Providence Bank & Vision Ventures, LLC) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bates & Associates, Inc. v. Providence Bank & Vision Ventures, LLC, (Mo. Ct. App. 2019).

Opinion

In the Missouri Court of Appeals Eastern District DIVISION FOUR

BATES & ASSOCIATES, INC., ) Nos. ED106955/ED107279 ) Appellant, ) Appeal from the Circuit Court ) of St. Louis County v. ) 16SL-CC00187 ) PROVIDENCE BANK & VISION ) VENTURES, LLC ) Honorable David L. Vincent, III ) Respondent. ) Filed: September 17, 2019

OPINION

In these consolidated appeals, Bates & Associates, Inc. (“Bates”) appeals from the

judgment of the trial court in its petition for breach of contract against Vision Ventures, LLC

(“Vision”) and for enforcement of its architect lien against Providence Bank (“Providence”).

Bates asserts the trial court erred in denying its claim for lien enforcement against Providence

because it was entitled to a lien under the statute even though actual construction of the planned

work had not yet commenced, and because its lien was timely filed. We affirm.

Background and Procedure

The parties agree to the following. Bates is a licensed architectural firm, and Bates

entered into a contract with Vision in October 2013 for architectural design and construction

services related to a senior care facility (“the Project”). Prior to the contract between Bates and

Vision, in 2007, the predecessor in interest to Vision entered into a commercial loan agreement with Premier Bank to borrow funds of $2,480,000.00 (“the Loan”). The Loan was secured by a

Deed of Trust, granted by Vision to Premier Bank, encumbering 17655 Wild Horse Creek Road,

Chesterfield, Missouri (“the Property”). In 2008, Vision executed and delivered a promissory

note to Premier Bank for an additional amount of $1,366,862.00 (“the Note”), secured by a

modification to the Deed of Trust. Following the closure of Premier Bank, the Loan, the Deed of

Trust, and the Note were assigned to Providence. In March 2015, Vision filed for Chapter 11

bankruptcy and listed Bates as an unsecured creditor with a claim in the amount of $279,200.00.

Vision defaulted on the Loan and Note by failing to pay all amounts owed, and Providence

elected to foreclose on the Deed of Trust to the Property. On July 15, 2015, Bates filed a

mechanic’s lien upon the Property for the work performed under the contract with Vision. On

July 17, 2015, the non-judicial foreclosure took place, and Providence obtained title to the

Property.

Bates filed a three-count Petition to enforce its mechanic’s lien against Vision and

Providence. In Counts I and III, it requested damages against Vision in the amount of

$305,279.00, plus interest and attorneys’ fees, under theories of breach of contract and quantum

meruit, asserting Vision failed to pay the sums owed Bates for design services rendered pursuant

to their contract; and in Count II, it requested a judgment declaring its mechanic’s lien in the

amount of $305,279.00 against the Property was superior to and had priority over Providence’s

interest, and an order enforcing the lien. Providence filed affirmative defenses, including that

Bates failed to comply with the statutory requirements of Chapter 429, in that its mechanic’s lien

was not timely filed, and that no development work or improvement had occurred at the

Property. Providence also filed, as relevant to this appeal, a counterclaim to quiet title to the

Property and for a declaratory judgment that Bates had no right to or interest in the Property.

2 At a bench trial, Steven Warlick (“Warlick”), an architect from Bates, and Bo Hagerman

(“Hagerman”), the director of design at Bates, testified to the following. Bates initially

contracted with Vision in October 2013 to provide schematic designs, design development,

construction documents, and construction administration for a senior care facility. After the

initial design was approved by the City of Chesterfield, Vision requested so many design

changes to reduce costs that Chesterfield withdrew its approval. In January 2015, Warlick had a

meeting with Rodney Henry (“Henry”) of Vision, during which they discussed providing

additional work to comply with Chesterfield zoning requirements. Warlick sent Vision a

proposal for these services and, although Henry did not sign the proposal, Warlick testified

Henry agreed verbally. In accordance with their agreement, Bates performed additional

architectural work for Vision in January through March of 2015, including reworking the design

plans to regain approval from Chesterfield. Warlick agreed, however, that Bates’s invoices to

Vision did not reflect work performed past July 2014; that the July 2015 lien did not include

documentation showing work was performed in 2015; and that Bates’s internal timesheets

between January and March 2015 documented only client communications and internal

discussions about the proposal, rather than design work. In contrast to Bates’s evidence,

Providence submitted deposition testimony from Henry stating he did not request additional

architectural services from Bates, and he did not provide approval for Bates to begin additional

services because he had not vetted the proposed scope changes.

The trial court granted Bates’s breach-of-contract claim against Vision in the amount of

$276,250.00 and denied the alternative quantum-meruit claim against Vision. The trial court

denied Bates’s claim to enforce its mechanic lien against Providence, and granted Providence’s

counterclaim for quiet title to the Property. The trial court concluded Bates’s architectural

3 services were not directly connected with any construction or other improvements upon the

Property. Further, the trial court concluded Bates did not timely file its lien. This appeal

follows.

Discussion

Bates raises two points on appeal. First, Bates argues the trial court erred in denying its

claim to enforce the mechanic’s lien because the services it performed under the contract were

lienable. Second, Bates argues the trial court erred in denying its claim to enforce its mechanic’s

lien because the lien was timely filed, in that it provided services under the contract within six

months before filing the lien on July 15, 2015. We disagree. Because the second point is

dispositive, our analysis is limited to this point.

This Court reviews a bench-tried case for whether there is substantial evidence to support

the judgment, it is against the weight of the evidence, or it erroneously applies the law. Ivie v.

Smith, 439 S.W.3d 189, 198-99 (Mo. banc 2014). We defer to the trial court’s findings of fact,

so long as they are supported by substantial evidence. Royal Forest Condominium Owners’

Ass’n v. Kilgore, 416 S.W.3d 370, 373 (Mo. App. E.D. 2013). However, because the

interpretation and application of a contract is a question of law, we review such issues de novo,

giving the words of the agreement their plain and ordinary meaning, so as to best ascertain the

intent of the parties. Shocklee v. Albers Chiropractic Health Centre, P.C., 558 S.W.3d 83, 86

(Mo. App. E.D. 2018); McHugh v. Slomka, 531 S.W.3d 588, 593 (Mo. App. E.D. 2017).

Section 429.015 provides that those persons or corporations who provide architectural

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Petroleum Service, Inc. v. Piatchek
218 S.W.3d 477 (Missouri Court of Appeals, 2007)
Altom Construction Co. v. BB Syndication Services, Inc.
359 S.W.3d 146 (Missouri Court of Appeals, 2012)
Winters Excavating, Inc. v. Wildwood Development, L.L.C.
341 S.W.3d 785 (Missouri Court of Appeals, 2011)
R.K. Matthews Investment, Inc. v. Beulah Mae Housing, LLC
379 S.W.3d 890 (Missouri Court of Appeals, 2012)
Royal Forest Condominium Owners's Ass'n v. Kilgore
416 S.W.3d 370 (Missouri Court of Appeals, 2013)
Patterson v. Rough Road Rescue, Inc.
529 S.W.3d 887 (Missouri Court of Appeals, 2017)
McHugh v. Slomka
531 S.W.3d 588 (Missouri Court of Appeals, 2017)
Shocklee v. Albers Chiropractic Health Ctr., P.C.
558 S.W.3d 83 (Missouri Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Bates & Associates, Inc. v. Providence Bank & Vision Ventures, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bates-associates-inc-v-providence-bank-vision-ventures-llc-moctapp-2019.