R.K. Matthews Investment, Inc. v. Beulah Mae Housing, LLC

379 S.W.3d 890, 2012 WL 4344190, 2012 Mo. App. LEXIS 1194
CourtMissouri Court of Appeals
DecidedSeptember 25, 2012
DocketNo. WD 74567
StatusPublished
Cited by8 cases

This text of 379 S.W.3d 890 (R.K. Matthews Investment, Inc. v. Beulah Mae Housing, LLC) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.K. Matthews Investment, Inc. v. Beulah Mae Housing, LLC, 379 S.W.3d 890, 2012 WL 4344190, 2012 Mo. App. LEXIS 1194 (Mo. Ct. App. 2012).

Opinion

CYNTHIA L. MARTIN, Judge.

R.K. Matthews Investment, Inc. (“RKMI”) appeals from a judgment entered following a bench trial. The judgment found in favor of Beulah Mae Housing, LLC (“BMH”) on RKMI’s claims for breach of contract and enforcement of mechanic’s lien and for relief under the Missouri Prompt Pay Act.1 We affirm.

Factual and Procedural Background

Viewing the evidence in the light most favorable to the judgment, on July 9, 2009, RKMI and BMH reached an agreement to have RKMI perform foundation and other construction work on an uninhabited residence located at 2404 Red Bridge Road.

A written agreement with various attached exhibits was introduced at trial.2 The written agreement was not [893]*893signed by BMH. Various attachments to the agreement, including a consent of owner to mechanic’s liens, a schedule for making payment, and a notification that mechanic’s liens might be filed in the event of nonpayment, were signed by Lynn Stark (“Stark”), the principal of BMH. Though the agreement itself was not signed by BMH, there was no dispute that BMH intended, through its principal Stark, to enter into an agreement with RKMI to perform the work described in the written agreement.

RKMI’s scope of work was described in Exhibit A to the agreement as:

1. Repair Crack in foundation, dig around foundation install sealer, rubber blanket, and drain line.
2. Tear out 39ftX8ftX8in wall.
3. Garage floor
4. Stair case with walls & drain
5. Cut out opening for Egress window and metal door

Additional costs for engineering report Exhibit A provided that the cost to perform this work would be $20,000.00, with one-third due on signing, one-third due after tear out, and one-third due on completion.

Exhibit B to the agreement identified the terms for payment more specifically, and required $7,600.00 to be paid on signing of the agreement, $7,000.00 to be paid after excavation, and $6,980.00 to be paid upon completion. These figures total $21,580.00, not the $20,000.00 contract amount set forth in the agreement. At trial, RKMI’s principal, R.K. Matthews (“Matthews”) explained that the difference between the sums was made up of $1,500.00 for the engineering “report” anticipated in the scope of work described in Exhibit A, and an $80.00 “permit fee.” Matthews claimed that the “report” was actually a set of architectural drawings prepared for the project by Joseph Zubeck (“Zubeck”). Other than Matthews’s testimony, there was no evidence that BMH ever agreed to pay $1,500.00 for Zubeck’s architectural drawings. Instead, the evidence indicated that BMH gave RKMI a check for $500.00 on June 25, 2009, at about the time drawings were given to BMH, and some two weeks before the July 9, 2009 agreement was entered into.

Exhibit A to the agreement identified Ralph Williams (“Williams”), Stark’s husband, as the “customer.” However, there is no dispute that the “customer” was actually BMH, and that Williams had been given the authority by Stark to act on BMH’s behalf in connection with the work anticipated by the agreement.

According to Matthews’s testimony at trial, BMH3 paid RKMI $7,600.00, the first installment required by the agreement, on or about July 10, 2009.

RKMI commenced work immediately thereafter. RKMI did not, however, have a permit to commence work. RKMI could not secure the necessary permit because it did not have a license to work on residential property. Matthews did not inform Stark or Williams that neither he, nor RKMI, was licensed to work on residential property. Matthews claimed that BMH was responsible for pulling its own permit. However, Matthews also inconsistently testified that the total amount RKMI was [894]*894to be paid included $80.00 for the cost to secure a permit.

After starting work, Matthews told Stark and Williams that they needed to make application to pull their own permit. Stark and Williams unsuccessfully attempted to do so. Matthews then used another contractor’s credentials to pull a permit for the project. This contractor obtained a permit in his name on August 13, 2009, more than a month after work on the project had commenced, but never performed any work on the project. The permit was pulled the day before the city’s first scheduled inspection of the work. On August 14, 2009, foundation work performed to that date passed inspection.

Over the course of the project, two change orders were prepared. The first, dated August 14, 2009, was in the sum of $4,500.00 and added the following work:

1. Add dirt and swell change flow of water away from house
2. Drive pad 8X20 & remove and install
3. Plaster foundation wall
4. Add one step remove lose [sic] debris install new concrete
5. Haul away previous debris

The second change order, dated September 2, 2009, was in the sum of $3,550.00 and added the following work:

1. Install wall and stoop
2. 25X4 sidewalk
3. Basement 2X20 floor replacement and saw cut
4. Install pump and pit for sewer
5. Sand and finish floor 626 sq ft
6. Install 28X7 garage doors

Neither change order was signed by a representative of BMH. However, it is not disputed that Williams authorized RKMI to perform the additional work.

According to Matthews’s testimony, RKMI was given its second installment check in the amount of $7,000.00 or about August 15, 2009. Matthews also testified that BMH paid two thirds of the $3,550.00 change order, $2,366.00.4 Matthews testified that RKMI did not perform all of the work described in the September 2, 2009 change order.

Numerous issues arose about the quality of RKMI’s work. Williams attempted without success to contact Matthews to address his concerns. Williams would frequently leave written notes for Matthews. On one occasion, he drove to the address he had been given for RKMI only to find that it was a private mailbox business. The disputes escalated to the point that BMH ordered RKMI off the job sometime in October 2009. On October 27, 2009, the city conducted a second inspection. The inspection noted multiple deficiencies including failure to provide a handrail on the stairs, failure to provide a guardrail at the stairs, failure to pull a plumbing permit for the plumbing work performed, failure to provide an egress door, failure to provide a window, and failure to place headers over a door. Although RKMI performed plumbing work on the project, Matthews [895]*895was not licensed to perform plumbing work.

On February 26, 2010, RKMI filed a statement of mechanic’s lien. The lien statement claimed that $13,255.00 was due and owing to RKMI from BMH.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
379 S.W.3d 890, 2012 WL 4344190, 2012 Mo. App. LEXIS 1194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rk-matthews-investment-inc-v-beulah-mae-housing-llc-moctapp-2012.