Vic Koepke Excavating & Grading Co. v. Kodner Development Co.

571 S.W.2d 253, 1978 Mo. LEXIS 320
CourtSupreme Court of Missouri
DecidedSeptember 12, 1978
DocketNo. 60106
StatusPublished
Cited by10 cases

This text of 571 S.W.2d 253 (Vic Koepke Excavating & Grading Co. v. Kodner Development Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vic Koepke Excavating & Grading Co. v. Kodner Development Co., 571 S.W.2d 253, 1978 Mo. LEXIS 320 (Mo. 1978).

Opinion

SEILER, Judge.

We ordered this case transferred from the court of appeals, St. Louis district, largely to resolve a conflict in the case law over whether the issue of workmanlike performance is an indispensable component of [255]*255plaintiff’s verdict-directing instruction in an action on a contract.

Defendant is a general contractor. Plaintiff is a dirt-moving subcontractor. The parties had worked together on construction projects since 1960 or 1961. The present controversy centers on construction work done between 1970 and 1972 on Big Bend Woods subdivision.

Plaintiff sued in four counts for recovery of balance plus interest allegedly due for dirt-moving operations and various other construction tasks. An additional count sought recovery of the balance on a promissory note. Defendant denied the allegations of each count of the petition and as to each count asserted that:

“7. For further answer and defense . plaintiff improperly performed grading and filling operations as a direct and proximate result of which defendant was caused to expend $15,277.26. Said amount should be set off against any amounts to which plaintiff is entitled.”1

Trial before a jury resulted in verdicts for plaintiff on all five counts in the amounts sought, a total of $21,729.65, subject to a set off of $2,612.00 on defendant’s claim.2 Defendant appeals on a variety of grounds from the jury verdicts on all counts and challenges the amount of the set off as grossly inadequate and against the weight of the evidence.

Count I of plaintiff’s petition sought $5,361.36 plus interest as the balance due on a promissory note executed by defendant to plaintiff in January of 1971.

By count II and count V of its petition, plaintiff sought recovery of balances due plus interest for grading, cutting and filling operations performed on specified lots of plat 2-B and plat 1, respectively, of the subdivision. According to written contracts of the parties, plaintiff was to be paid a specified amount per lot for a specified number of lots. The contracts provided that “[a]ll work [was] to be completed in a workmanlike manner according to standard practices. . . . ”

Counts III and IV of plaintiff’s petition sought balances due plus interest for grading equipment and labor furnished on plats 3 and 4 by plaintiff at the special instance and request of defendant for which services defendant agreed to pay an amount based on an hourly charge as set forth in a pleaded schedule.

As said, as the basis for a set off against plaintiff’s recovery, defendant asserted in its answer to each count that the work was done improperly and as a result defendant was forced to expend additional sums to correct the errors.

Defendant seeks reversal of plaintiff’s verdicts on counts II and V, alleging error in verdict director instructions submitted by plaintiff. Plaintiff’s witness testified that all grading, cutting and filling on the specified lots had been completed. Plaintiff’s ledger accounts and invoices showing the balances allegedly due were introduced. Plaintiff’s verdict directors on both counts were essentially identical and provided that:

“INSTRUCTION NO. 3
“Your verdict must be for plaintiff on plaintiff’s claim for damages in Count II if you believe:
“First, that the defendant did not pay the plaintiff, and
“Second, because of such failure defendant’s contract obligations were not substantially performed, and
[256]*256“Third, plaintiff was thereby damaged,
“Unless you believe that plaintiff is not entitled to recover, or should be limited to a lesser recovery by reason of Instruction No. 7.”

Defendant’s verdict director on its set off was as follows:

“INSTRUCTION NO. 7
“If your verdict is for plaintiff under Instruction Nos. 2, 3,4, 5, and 6, or any of them, then you must determine whether plaintiff failed to complete all work in a workmanlike manner according to standard practices and whether, as a direct result of such failure, if any, defendant was damaged.
“If you believe:
“First, plaintiff failed to complete all work in a workmanlike manner according to standard practices, and
“Second, as a direct result thereof, defendant was damaged, then you must deduct the amount of such damage from plaintiff’s damage. In the event such damages is equal to or exceeds plaintiff’s damage, your verdict must be for defendant.”

Defendant attacks plaintiff’s instruction on two grounds. First, defendant asserts that plaintiff’s instructions should have specifically required the jury to find whether plaintiff performed at all. We, however, agree with plaintiff that there was sufficient evidence of performance derived from both plaintiff’s oral testimony and defendant’s testimony to remove the issue of performance from consideration by the jury. See Missouri Approved Jury Instructions, XLIX (2d ed. 1969); Bender v. Colt Industries, Inc., 517 S.W.2d 705, 709 (Mo.App.1974).

As the second ground, defendant asserts that instructions 3 and 6 were prejudi-cially erroneous by virtue of their failure to require the jury specifically to find that plaintiff performed its obligation in a workmanlike manner. The court of appeals reversed and remanded on this ground, pointing out that in Baerveldt & Honig Construction Company v. Szombathy, 365 Mo. 845, 289 S.W.2d 116, 120 (1956), we found a similar contention persuasive and held that:

“. . (in the absence of affirmative evidence by defendant conceding that nondefective materials were used and conceding that such materials were applied in a workmanlike manner and in the absence of defendants otherwise eliminating those issues), plaintiff would need to include as essential findings prerequisite to recovery that plaintiff complied with the implied provisions of its contract, viz., that the contract was performed and that the performance thereof was accomplished in a workmanlike manner. . . ”

Plaintiff, in response, contends the court of appeals action is in conflict with the Baerveldt case and also with an earlier opinion of the court of appeals, Brush v. Miller, 208 S.W.2d 816 (Mo.App.1948).3 Plaintiff argues that its instruction No. 3 included a specific reference to instruction 7 which hypothesized the missing element. At first blush this may appear correct, but closer examination shows it is not. Under instructions 3 and 7, the jury could first find for plaintiff as to the contract price without any consideration of the quality of the performance and then consider any evidence of defective performance as the basis only for deductions from the contract price. The result could be a damage award far different from an award made were the jury properly to recognize that plaintiff is only entitled to recovery of any portion of the contract price if plaintiff is able to persuade the jury that its performance was workmanlike.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R.K. Matthews Investment, Inc. v. Beulah Mae Housing, LLC
379 S.W.3d 890 (Missouri Court of Appeals, 2012)
Jake C. Byers, Inc. v. J.B.C. Investments
834 S.W.2d 806 (Missouri Court of Appeals, 1992)
Killian Construction Co. v. Tri-City Construction Co.
693 S.W.2d 819 (Missouri Court of Appeals, 1985)
Seuf, Inc. v. Bartlett
665 S.W.2d 31 (Missouri Court of Appeals, 1984)
Leh v. Dyer
643 S.W.2d 65 (Missouri Court of Appeals, 1982)
Cotton v. 71 Highway Mini-Warehouse
614 S.W.2d 304 (Missouri Court of Appeals, 1981)
Dan Ficken Pools, Inc. v. Flynn
592 S.W.2d 213 (Missouri Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
571 S.W.2d 253, 1978 Mo. LEXIS 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vic-koepke-excavating-grading-co-v-kodner-development-co-mo-1978.