Environmental Waste Management, Inc. v. Industrial Excavating & Equipment, Inc.

981 S.W.2d 607, 1998 Mo. App. LEXIS 1740, 1998 WL 684179
CourtMissouri Court of Appeals
DecidedOctober 6, 1998
DocketWD 54823
StatusPublished
Cited by15 cases

This text of 981 S.W.2d 607 (Environmental Waste Management, Inc. v. Industrial Excavating & Equipment, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Waste Management, Inc. v. Industrial Excavating & Equipment, Inc., 981 S.W.2d 607, 1998 Mo. App. LEXIS 1740, 1998 WL 684179 (Mo. Ct. App. 1998).

Opinion

ELLIS, Presiding Judge.

Environmental Waste Management, Inc. filed suit against Industrial Excavating and Equipment, Inc. for breach of contract in Jackson County circuit court. A jury rendered a verdict in favor of Environmental Waste Management, Inc., awarding damages in the amount of $263,663.59. Industrial Excavating and Equipment, Inc. brings this appeal.

In 1992, the federal government, acting through the General Services Administration (“GSA”) contracted with Rand & Co. (“Rand”) to make general improvements to the Internal Revenue Service building on Bannister Road in Kansas City. During the course of the improvements, workers discovered what they thought were two underground storage tanks (“UST’s”) that had to be removed before completion of the project. The UST’s were located under an asphalt parking lot and had been used to store oil. Workers eventually confirmed there were two 15,000 gallon tanks and one 600 gallon tank, all full of oil. Oil had leaked out of the tanks and contaminated a large amount of soil surrounding the tanks. The tanks, the oil, and the contaminated soil had to be removed from the site.

As already noted, the government’s general contractor was Rand. The government also contracted with Energy Masters Corporation *609 (“Energy Masters”) to provide contract services for the project. Rand hired Industrial Excavating & Equipment, Inc. (“Industrial,” defendant/appellant) as a subcontractor to provide certain labor and materials for the removal of the tanks. Industrial then contracted 'with Environmental Waste Management, Inc. (“EWM,” plaintiff/respondent) to provide labor and materials to aid in site excavation, tank removal, soil removal, soil disposal, and the drafting of a closure report. 1 The main issues at trial revolved around what agreement, if any, Industrial and EWM reached with respect to the prices Industrial agreed to pay EWM for its services and the method used to determine the amount of contaminated soil removed from the site. 2

Originally, Industrial contracted with EWM to aid in the removal of a different UST at the IRS building project. EWM performed its services under that contract and Industrial paid EWM based on a lump sum bid. The provisions of that contract were fully performed by both parties and are not an issue in this ease. After the discovery of the UST’s under the parking lot, Industrial and EWM began negotiating a second contract. EWM submitted a lump sum bid of $39,492.00 to Industrial on July 1, 1992. 3 Industrial requested EWM provide a price breakdown, detailing how it arrived at the lump sum reflected in the bid. Industrial told EWM the numbers did not have to be accurate, they just had to add up to the amount of the lump sum bid. Industrial had to submit the breakdown to Energy Masters, the government’s contract representative, to substantiate its own costs. Michael Duffey, vice president of EWM, produced a document with primarily fictitious numbers, warning Industrial the numbers did not reflect EWM’s actual costs. EWM worked backwards from their quote of $39,492.00, plugging in numbers that would add up to the total of the lump sum bid. As a result, the numbers did not reflect actual prices for each individual item.

Energy Masters, the governments contract representative, met with the parties in early August, 1992. Energy Masters had a problem with all the costs submitted to it by the various contractors, including the breakdown provided by EWM. Energy Masters told the parties they might have to begin work on the removal of the UST’s and proceed on a PDL basis. 4 Ultimately, Industrial and EWM did not reach an agreement based on the lump sum bid EWM submitted July 1, 1992, nor the subsequent breakdown of the lump sum bid submitted on July 22. EWM never agreed to work for Industrial on a PDL basis. Industrial and Rand eventually agreed to proceed with their work on a PDL basis.

Around August 20, 1992, Industrial and EWM again entered into contract negotiations regarding the removal of the UST’s. Industrial asked EWM, instead of submitting a lump sum bid, to provide a price list reflecting what it would charge per unit of work on the project. EWM provided Industrial with a letter dated August 21, 1992 which outlined the prices it would charge for certain services. The prices were set out as follows:

Labor
Supervisor $ 40.00/hour
Laborer $ 30.00/hour
Clerical $ 25.00/hour
Equipment & Supplies
EWM Pickup $ 10.00/hour
Cleaning Chemicals $ 40.00/gallon
Explosion Meter $125.00/day
Pumps & Hoses $125.00/day
Sampling Supplies $ 5.00/sample
Tank Head Cleaner $250.00/day
Poly Sheeting $ 70.00/roll
Transportation $700.00/load
Liquid-Disposal $000.75/gallon
Hazardous Sludge Disposal $350.00/drum
Laboratory Analysis/BETX & TPH Rush $300.00/sample

*610 A day or two after EWM sent the August 21 letter to Industrial, Ken Gray, who worked for Industrial at the time and had the power to enter into contracts on its behalf, telephoned EWM. He spoke to Michael Duf-fey. Gray pointed out to Duffey that the price list did not include a price for the disposal of contaminated soil. EWM’s prior bid included a cost of $32.20 per cubic yard of soil removed from the site. Duffey told Gray he would still honor that quote.

Another day or two later, Gray called again and spoke to both John and Michael Duffey. 5 Gray complained that he thought the prices EWM was charging for its services were too high. John Duffey told Gray that Industrial did not have the expertise to do the job themselves, they needed EWM’s experience, and the prices on the list were the amounts it would cost Industrial to hire EWM. Gray again complained about the “mark-ups” and asked whether the prices on the list included everything; meaning cost, overhead, and profit. John Duffey told him it did and that when Industrial received EWM’s daily bills, these prices would be on the bills. Gray again asked EWM to provide a further breakdown of the numbers to “make them more palatable to the client” (presumably the federal government). Michael Duffey told Gray he could do whatever he wanted to with the numbers, but that the price list was what EWM would work for.

After another day or two, Gray again called and spoke only with Michael Duffey. During this conversation, Gray simply told Michael Duffey they would accept the numbers and said, “Let’s go to work.” Throughout the project, EWM billed Industrial on a daily basis. Each daily billing reflected the prices outlined in the August 21 letter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Cape Girardeau ex rel. Kluesner Concreters v. Jokerst, Inc.
402 S.W.3d 115 (Missouri Court of Appeals, 2013)
McGuire v. Kenoma, LLC
375 S.W.3d 157 (Missouri Court of Appeals, 2012)
West v. Sharp Bonding Agency, Inc.
327 S.W.3d 7 (Missouri Court of Appeals, 2010)
Carroll v. Kelsey
234 S.W.3d 559 (Missouri Court of Appeals, 2007)
State v. Freeman
212 S.W.3d 173 (Missouri Court of Appeals, 2007)
Pride v. Lewis
179 S.W.3d 375 (Missouri Court of Appeals, 2005)
Heritage Roofing, LLC v. Fischer
164 S.W.3d 128 (Missouri Court of Appeals, 2005)
Citibank (South Dakota), N.A. v. Wilson
160 S.W.3d 810 (Missouri Court of Appeals, 2005)
Thornton v. Gray Automotive Parts Co.
62 S.W.3d 575 (Missouri Court of Appeals, 2001)
Nichols v. Preferred Risk Group
44 S.W.3d 886 (Missouri Court of Appeals, 2001)
Roy v. Missouri Pacific Railroad Co.
43 S.W.3d 351 (Missouri Court of Appeals, 2001)
Portis v. Greenhaw
38 S.W.3d 436 (Missouri Court of Appeals, 2001)
Lay v. P & G Health Care, Inc.
37 S.W.3d 310 (Missouri Court of Appeals, 2000)
Aliff v. Cody
26 S.W.3d 309 (Missouri Court of Appeals, 2000)
Guess v. Escobar
26 S.W.3d 235 (Missouri Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
981 S.W.2d 607, 1998 Mo. App. LEXIS 1740, 1998 WL 684179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-waste-management-inc-v-industrial-excavating-equipment-moctapp-1998.