Honig Construction Company v. Szombathy

345 S.W.2d 111, 1961 Mo. LEXIS 688
CourtSupreme Court of Missouri
DecidedMarch 13, 1961
Docket47844
StatusPublished
Cited by4 cases

This text of 345 S.W.2d 111 (Honig Construction Company v. Szombathy) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Honig Construction Company v. Szombathy, 345 S.W.2d 111, 1961 Mo. LEXIS 688 (Mo. 1961).

Opinion

HOLMAN, Commissioner.

In this action to enforce a mechanic’s lien plaintiff sought a judgment in the sum .of $11,066.50, the alleged balance due for labor and materials furnished by plaintiff in the construction of a building for Louis R. and Alice P. Szombathy, defendants herein. The defendants filed a counterclaim in which they sought damages in the sum of $27,559. A trial resulted in a verdict for plaintiff on its claim in the amount of $10,929.55, together with interest from April 23, 1952, in the sum of $4,590.39, and a verdict in favor of plaintiff upon defendants’ counterclaim. After considering defendants’ motion for new trial and motion for judgment in accordance with their motion for directed verdict the court ordered that “if plaintiff will within five days remit from the amount of the jury’s verdict the sum of $3,500 together with interest thereon at 6% per annum from April 23, 1952, defendants’ motion for a new trial will be overruled; otherwise a new trial will be ordered as to the issue of damages only, on the ground that the verdict is excessive.” Plaintiff did not enter the .remittitur and all parties have appealed.

This is the second appeal in this case. Upon the prior appeal a judgment for plaintiff was reversed and the cause remanded for a new trial because of error in plaintiff’s verdict-directing instruction. Baerveldt & Honig Construction Co. v. Szombathy, 365 Mo. 845, 289 S.W.2d 116.

Defendants owned a lot located on Airport Road in Berkeley, St. Louis County, Missouri. They desired to construct a one-story building thereon which was to be leased to the United States for use as the post office in Berkeley. The negotiations between plaintiff and defendants were carried on by Robert J. Honig on behalf of plaintiff and Louis R. Szombathy on the part of defendants. In the spring of 1951 Louis contacted Mr. Honig and obtained an estimate as to the cost of constructing the building. Honig also assisted Louis.in preparing the “Proposal to Lease Quarters” *113 which defendants submitted to the post office department.

On or about August 3, 1951, an oral contract was entered into between plaintiff and defendants for the construction of the building. There is conflicting testimony in regard to some of the terms of the agreement. Mr. Honig testified that it had been agreed that plaintiff would construct the building in good workmanlike manner and that defendants would pay plaintiff the cost of the labor, plus 10% thereof to cover insurance and taxes, the cost of all materials used, plus 10% of the total cost (labor and materials) for plaintiff’s overhead and profit. Mr. Szombathy agreed with the testimony of Mr. Honig as to the terms of the contract with the exception that he stated that plaintiff had guaranteed that the maximum cost would not exceed $25,-280. It should also be stated that Mr. Szombathy was engaged in the heating business and it was agreed that he could install the heating equipment in the building. Mr. Honig had estimated the cost of the heating plant at $1,680. Mr. Szom-bathy testified that plaintiff had agreed that he should be allowed a credit of $1,680 for the installation of the heating plant, thus reducing the maximum or ceiling cost for all items furnished by plaintiff to $23,-600.

As soon as plaintiff had been authorized to proceed with the construction it employed Louis Baerveldt, a licensed architect, to prepare the detailed plans for the building. (The architect was apparently employed to prepare plans but not to supervise construction.) The plans show a date of August 30, 1951, but apparently were revised and finally delivered to plaintiff on September 24, 1951. These plans did not show the details for installation of the heating equipment but did show the location of the two gas heaters.

The actual construction of the building began on September 11, 1951. The building has been occupied and used as a post office since January 5, 1952 under a ten-year lease providing for payment of a rental of $3,500 annually. The walls of the building were constructed of concrete blocks although the north and west walls (street sides) were veneered with Bedford stone. The walls rest upon a concrete foundation 12" thick and 63" high in which (according to plaintiff’s evidence) was placed two one-half inch reinforcement rods. The foundation rests upon a concrete footing 28" wide and 11" high in which was also placed two half-inch reinforcement rods. Plaintiff’s evidence indicated that the total cost of the building (not including the cost of the heating plant) was $27,881.33. Defendants paid plaintiff a total of $16,814.83. During the trial plaintiff gave a voluntary credit of $135.95 for the architect’s fees because of a question as to the lienability of that item. Therefore, according to plaintiff,' the balance due upon plaintiff’s claim (excluding interest) was $10,930.55. Computed according to defendants’ version of the agreement, the balance due upon plaintiff’s claim would not have exceeded $6,785.17.

The main controversy at the trial related to the cause and effect of certain cracks that were discovered in the fall of 1952 in the foundation and walls of the building. It was conceded that a number of cracks developed in the east and south walls. In regard thereto defendants pleaded “that the building so constructed was and is defective by reason of foundation wall cracks arising either from defective or insufficient materials or defective workmanship, or both, or from defective plans providing insufficient materials which plans were drawn by plaintiff’s agent and represented by plaintiff as sufficient properly to construct and complete the building in a good and workmanlike manner; * * * that defendants are informed and believe and therefore allege the fact to be that the walls and floors as erected are shrinking or settling due to insufficient steel or Other causes not known to defendants but within the control of plaintiff as the work of construction commenced and progressed.” *114 Defendants presented evidence tending to prove (1) that the cracks resulted from the failure of the plaintiff to use sufficient reinforcement rods in the foundation, (2) that the rods specified in the plans were only about one-fourth of the quantity that should have been used, (3) that no rods were placed in the foundation under the east wall (this was shown by the testimony of an expert who took industrial X-ray exposures of the’ foundation and was rebutted by the testimony of an expert offered by plaintiff who used a similar device which he said disclosed the rods in the east foundation), (4) that there is no way to permanently repair the walls so that there would be no cracks therein, (5) that the only way to eliminate the cracks would be to tear out the walls and rebuild them properly, and (6) that the cost of rebuilding the east and south walls while the building is in use would be $27,559. Defendants’ counterclaim is based upon the cost of rebuilding those walls.

Mr. Honig testified that when the revised plans were received on September 24, 1951, he immediately sent copies to Mr. Szombathy, together with a letter which read as follows: “Enclosed herewith four (4) sets revised drawings for the above.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R.K. Matthews Investment, Inc. v. Beulah Mae Housing, LLC
379 S.W.3d 890 (Missouri Court of Appeals, 2012)
Strain-Japan R-16 School District v. Landmark Systems, Inc.
965 S.W.2d 278 (Missouri Court of Appeals, 1998)
Bethell v. Porter
595 S.W.2d 369 (Missouri Court of Appeals, 1980)
Vic Koepke Excavating & Grading Co. v. Kodner Development Co.
571 S.W.2d 253 (Supreme Court of Missouri, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
345 S.W.2d 111, 1961 Mo. LEXIS 688, Counsel Stack Legal Research, https://law.counselstack.com/opinion/honig-construction-company-v-szombathy-mo-1961.