Winters Excavating, Inc. v. Wildwood Development, L.L.C.

341 S.W.3d 785, 2011 Mo. App. LEXIS 717, 2011 WL 2002280
CourtMissouri Court of Appeals
DecidedMay 24, 2011
DocketSD 30612
StatusPublished
Cited by4 cases

This text of 341 S.W.3d 785 (Winters Excavating, Inc. v. Wildwood Development, L.L.C.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winters Excavating, Inc. v. Wildwood Development, L.L.C., 341 S.W.3d 785, 2011 Mo. App. LEXIS 717, 2011 WL 2002280 (Mo. Ct. App. 2011).

Opinion

GARY W. LYNCH, Judge.

Winters Excavating, Inc. (“Winters”) filed an action seeking to enforce its mechanic’s lien against certain real estate in Camden County and for recovery based on quantum meruit against the former and present property owners for excavation services it provided in the development of the real estate. The trial court, finding that Winters’s mechanic’s lien was invalid and unenforceable, denied its petition to enforce but entered judgment in its favor in quantum meruit against Wildwood Development, L.L.C. (“Wildwood”), a former owner of the real estate. Winters appeals the trial court’s denial of its petition for enforcement of its mechanic’s lien. Finding no reversible error as alleged by Winters, we affirm.

Factual and Procedural Background

Wildwood was organized by Tracy White, Sr., Leland Nollau, and Jerry Buck for the purpose of constructing a real estate development at Lake of the Ozarks. On July 4, 2004, Wildwood acquired the real property for the development, which was to be known as Diamond Pointe. 1 Fi *788 nancing for Wildwood’s construction project was obtained in part from First Bank of the Lake (“First Bank”) in Lake Ozark and was secured in part by deeds of trust on the real estate.

Initially, Winters was subcontracted for excavation work on an oral time-and-materials basis by the general contractor for the project, Constructive Engineering Design, Inc. (“CED”). Winters began work on May 3, 2005, clearing and preparing the site for development. Subsequently, Winters executed three subcontracts with CED: one provided a fixed sum for road and storm drainage excavation; another designated a maximum price for sanitary sewer service on a per-unit and rock-removal cost basis; and the third designated a maximum price for potable water service on a per-unit and rock-removal cost basis. Under these subcontracts, CED was designated as contractor, Winters as subcontractor, and Diamond Pointe Development as owner. The total amount due to Winters under the subcontracts upon completion was $520,084.95.

On October 19, 2005, Wildwood terminated CED as general contractor, and CED notified Winters of its termination, requesting a final invoice for work performed. 2 The three subcontracts executed by Winters as subcontractor were terminated by CED, and Winters was paid in full for all work performed as a subcontractor under CED.

At the request of Wildwood through its agent Nollau, Winters continued work on the project on October 20, 2005, and for some time thereafter, ultimately completing the work described under the subcontracts with CED. 3 Winters’s principal agent, Everett Winters, Jr., knew that Nollau, White, and Buck were the owners of the real estate and that Winters was an original contractor with those individuals, “whatever entity they may have formed” to build the development.

After the termination of CED, Nollau directed Winters’s work and was present at the worksite almost every day to supervise the project. The parties agreed that Winters would be compensated on a time- and-materials basis -without a fixed price or written contract. Initially, Winters submitted hand-written invoices for work performed on a monthly basis, which were delivered to either Nollau or White. At Nollau’s direction, Winters’s invoices identified Diamond Pointe Development, L.L.C., as the customer but Winters received its payments from Wildwood.

Commencing on August 25, 2006, Winters began submitting computer-generated invoices for work performed. These invoices itemized the services rendered, the previous balance carried forward, payments received, and the current amount due. The reverse side of the invoices contained the terms and conditions of payment and the requisite statutory lien notice pursuant to section 429.012. 4 Invoices submitted by Winters prior to this time did not contain this notice, and all such invoices had been paid. Winters rendered *789 excavating services for water, sewer, and roadwork until March 2007, when it terminated its services due to delinquencies in payments from Wildwood.

Wildwood was divested of its interests in the real estate through foreclosure sales on May 31, 2007. First Bank was the purchaser. On June 21, 2007, First Bank conveyed the real property to Reinvestment Enterprises, L.L.C.

Winters filed its statement of mechanic’s lien on June 21, 2007. Winters claimed that $268,381.06 was due under a contract with Wildwood. Winters designated “Winters Excavating, Inc.” as “Original Contractor” and named Wildwood as “Property Owner.” In its invoice attached thereto, Winters identified its customer as “Diamond Pointe Development LLC.” Winters’s invoice indicates that work was authorized by “Leland Nolluu [sic] of Wildwood Development” and a signature line provided thereunder is apparently signed by Nollau.

On December 19, 2007, Winters filed a two-count petition requesting enforcement of its mechanic’s lien against the real estate and asserting a claim in quantum meruit against Wildwood, First Bank, and Reinvestment Enterprises, L.L.C. Winters filed its first amended petition on August 12, 2009. In its count for enforcement of its mechanic’s lien therein, Winters asserted that following Wildwood’s termination of CED as general contractor, “Diamond Pointe Development LLC assumed [Winters’s] subcontracts and agreed to pay for all of the excavation services which were to be provided thereunder[.]” Winters further alleged that it “fully complied with the requirements of Chapter 429 RSMo[,]” claimed damages in the amount of $268,381.06, plus interest and costs, and prayed that “all rights to the real property of the named Defendants be found and adjudged to be subordinate and inferior to said special lien in favor of [Winters].”

Following trial, the circuit court entered its judgment denying enforcement of Winters’s mechanic’s lien against First Bank and Reinvestment Enterprises, L.L.C. The trial court found that Winters was an original contractor during the period between October 20, 2005, and March 2006, and as such, its failure to provide the requisite notice to owner as provided under section 429.012.1 rendered its mechanic’s lien invalid and unenforceable. On Winters’s claim in quantum meruit, the trial court granted judgment in favor of Winters and against Wildwood for the balance due for Winters’s excavating services. Winters appeals that portion of the judgment denying enforcement of its mechanic’s lien against First Bank and Reinvestment Enterprises, L.L.C., respondents herein.

Standard of Review

Upon review of a court-tried mechanic’s lien action, the trial court’s judgment will be affirmed unless there is no substantial evidence to support it, it is against the weight of the evidence, or it erroneously declares or applies the law. Bullmaster v. Krueger, 151 S.W.3d 380, 384 (Mo.App.2004). In conducting our review,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
341 S.W.3d 785, 2011 Mo. App. LEXIS 717, 2011 WL 2002280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winters-excavating-inc-v-wildwood-development-llc-moctapp-2011.