KEHRER BROTHERS CONSTRUCTION, INC., Plaintiff-Respondent v. BANK OF VERSAILLES, and EDWIN J. GIRE, KENNETH O. McCUTCHEON, JR., and BUSEY BANK

499 S.W.3d 718, 2016 Mo. App. LEXIS 737
CourtMissouri Court of Appeals
DecidedJuly 27, 2016
DocketSD34000
StatusPublished

This text of 499 S.W.3d 718 (KEHRER BROTHERS CONSTRUCTION, INC., Plaintiff-Respondent v. BANK OF VERSAILLES, and EDWIN J. GIRE, KENNETH O. McCUTCHEON, JR., and BUSEY BANK) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KEHRER BROTHERS CONSTRUCTION, INC., Plaintiff-Respondent v. BANK OF VERSAILLES, and EDWIN J. GIRE, KENNETH O. McCUTCHEON, JR., and BUSEY BANK, 499 S.W.3d 718, 2016 Mo. App. LEXIS 737 (Mo. Ct. App. 2016).

Opinion

DON E. BURRELL, P.J.

OPINION AUTHOR

The Bank of Versailles (“Bank”) appeals the judgment that found Bank’s ownership of certain real property in Osage Beach (“the property”) to be subject to a mechanic’s lien and awarded the lienholder, Kehrer Brothers Construction, Inc. (“Contractor”), $740,153.89. Contractor filed the lien to cover work it performed on the property between November 2007 and August 2010 for the previous owner, Edwin J. Gire (“Owner”). 1 Bank held a deed of trust on the property, but it later became the owner via foreclosure.

In three points relied on, Bank contends “[t]he trial court erred in enforcing the mechanic’s lien ... because”: (1) Contractor did not “perform any work” under a “Subcontract Agreement” (“the contract”) with Owner “as required by [section] 429.010.1”; (2) Contractor “did not file its Statement of Mechanic’s Lien [‘the lien statement’] within the time required by [section]. 429.080, in that the last item allowed by the trial court ... [was] for the month of December 2009 but [Contractor] did not file its [statement] until February 14, 2011”; and (3) “the equipment rental charges” included in the mechanic’s lien “are not lienable pursuant to [section] 429.010.2[,]” in that Contractor’s improve *722 ments “were not on commercial proper- ty.” 2

*723 ■■ Finding no merit in these points, we affirm the judgment of the* trial court.

Standard of Review and Governing Law

We presume the judgment to be correct, and it is the appellant’s burden to demonstrate reversible error. Scheck Indus. Corp. v. Tarlton Corp., 435 S.W.3d 705, 717 (Mo.App.E.D.2014). “Upon review of a court-tried mechanic’s lien action, the trial court’s judgment will be affirmed unless there is no substantial evidence to support it, it is against the weight of the evidence, or it erroneously declares or applies the law.” Winters Excavating, Inc. v. Wildwood Dev., L.L.C., 341 S.W.3d 785, 789 (Mo.App.S.D.2011). “[W]e view the evidence and all reasonable inferences drawn therefrom in the light most favorable to the judgment and disregard all evidence and inferences to the contrary.” Id. (quotation omitted). The trial court decides the credibility of witness, and “we generally defer to the trial court’s findings of faet[.]” Mo. Land Dev. Specialties, LLC v. Concord Excavating Co., 269 S.W.3d 489, 496 (Mo.App.E.D.2008). “All fact issues upon which no specific findings are made shall be considered as having been found in accordance with the result reached.” Rule 73.01(c); see also Piazza v. Combs, 226 S.W.3d 211, 220 (Mo.App.W.D.2007).

“[T]he mechanic’s lien law should be construed as favorably to mechanics and materialmen as its .terms will per-mití.]” Mid -W. Eng’g & Constr. Co. v. Campagna, 421 S.W.2d 229, 233 (Mo.1967). However, because a “mechanic’s lien is purely a creature of the statutes[,] .the policy- of liberal construction of the lien statutes does not relieve a claimant of the necessity of reasonable and substantial compliance with statutory requirements.” Patrick V. Koepke Constr., Inc. v. Woodsage Constr. Co., 844 S.W.2d 508, 512 (Mo.App.E.D.1992).

Evidentiary and Procedural Background

A director of Contractor, Joseph Kehrer, testified that sometime in 2007, Owner “asked if we wanted to get involved with building this project at the lake [(‘the project’) ] because he knew our capabilities and he asked if we’d be willing to help him with the project and I accepted.” Owner and Contractor executed the contract in October 2007, and Contractor began excavation work the following month. During Mr. Kehrer’s testimony,. Bank’s attorney 3 informed the trial court that there was no dispute that the contract was a construction contract.

Near the top of the contract, Contractor was denominated “Contractor^]” but Owner was identified as “Subcontractor.]” The contract identified Owner by name in the space provided for the “Project Name[.]” Owner’s signature was below the caption *724 “OWNER[,]” and Owner’s name was typed in capital letters. A signature for Contractor followed its identification as “Contractor” and by Contractor’s typed name. The contract ■ specified that it was a “TIME AND MATERIAL CONTRACTU” The contract included an addendum signed by Owner as “Owner” and Contractor as “Contractor/Sub-contractor” that, in addition to a notice regarding lien waivers, provided:

CONSENT OF THE OWNER ■ IS HEREBY GIVEN FOR FILING OF MECHANIC’S LIENS BY ANY PERSON WHO SUPPLIES MATERIALS OR SERVICES FOR THE WORK DESCRIBED IN THIS CONTRACT ON THE PROPERTY ON WHICH IT IS LOCATED IF HE IS NOT PAID.

Mr. Kehrer explained that Contractor’s form contract was entitled “Subcontract Agreement” because when Contractor started out in business, it did more subcontracting work than “regular general contracting work.”

Mr. Kehrer testified that a time frame for the project was not initially discussed. He additionally testified that the property would not “be considered residential, but yeah, [Owner] was building a place on his land.” He explained that the projéct involved the construction of a garage with a basement and access from the lake for Owner’s boat. The excavation portion of the project was completéd in January 2008. From that point until March 2009, “other trades” worked on the site so that Contractor “could set the precast [panels].”

On cross-examination, Mr. Kehrer testified that Contractor was the general contractor for the work on the project and Contractor was “supposed to do .... [p]retty much whatever [Owner] wanted [Contractor] to .do” on the property. In April 2009, Bank “became the holder of a promissory note in the original principal amount of $1,650,000, and a deed of trust secured by the property, both executed by [Owner].” Kehrer I, 453 S.W.3d at 821.

Between May and December 2009, following Contractor’s installation of the precast panels, some of Contractor’s equipment remained on the property at Owner’s request. Copies of Contractor’s “Time Sheet[s]” and “Equipment Rental Agreement[s]” signed by Owner as “Renter” were identified by Mr. Kehrer and admitted into evidence. Mr. Kehrer confirmed that the lien statement included multiple charges for what was labeled as “equipment rental[,]” but he then explained (without objection),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mid-West Engineering & Construction Co. v. Campagna
421 S.W.2d 229 (Supreme Court of Missouri, 1967)
City of Peculiar v. Hunt Martin Materials, LLC
274 S.W.3d 588 (Missouri Court of Appeals, 2009)
Missouri Land Development Specialties, LLC v. Concord Excavating Co.
269 S.W.3d 489 (Missouri Court of Appeals, 2008)
Midwest Floor Co. v. Miceli Development Co.
304 S.W.3d 243 (Missouri Court of Appeals, 2009)
Piazza v. Combs
226 S.W.3d 211 (Missouri Court of Appeals, 2007)
Houston v. Crider
317 S.W.3d 178 (Missouri Court of Appeals, 2010)
S & R Builders & Suppliers, Inc. v. Marler
610 S.W.2d 690 (Missouri Court of Appeals, 1980)
Patrick v. Koepke Construction, Inc. v. Woodsage Construction Co.
844 S.W.2d 508 (Missouri Court of Appeals, 1992)
Winters Excavating, Inc. v. Wildwood Development, L.L.C.
341 S.W.3d 785 (Missouri Court of Appeals, 2011)
Kacie Nickel v. Stephens College
480 S.W.3d 390 (Missouri Court of Appeals, 2015)
Bellemere v. Cable-Dahmer Chevrolet Inc.
423 S.W.3d 267 (Missouri Court of Appeals, 2013)
Flanagan Bros. v. O'Connell
88 Mo. App. 1 (Missouri Court of Appeals, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
499 S.W.3d 718, 2016 Mo. App. LEXIS 737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kehrer-brothers-construction-inc-plaintiff-respondent-v-bank-of-moctapp-2016.