EDSA/CLOWARD, LLC v. Klibanoff

2008 UT App 284, 192 P.3d 296, 609 Utah Adv. Rep. 9, 2008 Utah App. LEXIS 274, 2008 WL 2854133
CourtCourt of Appeals of Utah
DecidedJuly 25, 2008
Docket20060958-CA
StatusPublished
Cited by7 cases

This text of 2008 UT App 284 (EDSA/CLOWARD, LLC v. Klibanoff) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EDSA/CLOWARD, LLC v. Klibanoff, 2008 UT App 284, 192 P.3d 296, 609 Utah Adv. Rep. 9, 2008 Utah App. LEXIS 274, 2008 WL 2854133 (Utah Ct. App. 2008).

Opinion

OPINION

ORME, Judge:

1 1 Plaintiff EDSA/Cloward, LLC (EDSA) appeals from the trial court's judgment and order ruling that its mechanic's lien was of a lower priority than Defendant Daniel Kliba-noffs security interest in connection with a luxury condominium project in Midway, Utah (the Project) because EDSA did not commence sufficient on-gite work or deliver any materials on the ground before Klibanoff's interest was recorded on June 15, 2001. EDSA also argues that the trial court erred in deeming Klibanoff the successful party and in awarding him all of his attorney fees and costs even though EDSA successfully appealed a prior order granting Klibanoff summary judgment. 1 We affirm.

*298 BACKGROUND

T2 Defendant Red Sea Development, LC (Red Sea) began the Project in 2000. The Project involved the development of luxury condominiums on thirteen acres of vacant land in Midway, Utah (the Property) 2 To fund the Project, Red Sea obtained a sizeable loan from Zions Bank. The loan was secured by a trust deed recorded on June 15, 2001, and later assigned to Klibanoff. 3

T 3 Some months earlier, in the fall of 2000, EDSA, a consulting engineering firm specializing in water projects, entered into an oral contract with Red Sea to provide various services in connection with the Project. Under the terms of the parties' agreement, Red Sea was to pay EDSA on an hourly basis for work performed on the Project, with payments due monthly. Red Sea made only two payments, totaling $3701.41, and by July 31, 2001, Red Sea owed EDSA approximately $186,000. The parties then modified the terms of their agreement to allow Red Sea to pay EDSA for its services once Red Sea obtained construction financing. EDSA continued providing services to Red Sea until it became clear that Red Sea would not be able to obtain financing. On November 8, 2002, EDSA recorded a mechanic's lien to recover more than $555,000 in unpaid services.

4 EDSA filed a complaint to foreclose on its mechanic's lien on February 11, 2008 4 Klibanoff answered the complaint, claiming his security interest held priority over EDSA's lien. After the close of discovery, the parties filed cross-motions for summary judgment on the issue of whether EDSA had, as of June 15, 2001, "commence{[d] to do work or furnish materials on the ground" as required for its lien to relate back to that date under Utah Code section 38-1-5. 5 See Utah Code Ann. $ 38-1-5 (2005). The trial court held that EDSA's on-site work did not satisfy the requirement of section 38-1-5 and held that Klibanoff's interest in the Property was superior to EDSA's. EDSA appealed, and we reversed and remanded for a trial on the merits. 6 See EDSA/Cloward, LLC v. Klibanoff, 2005 UT App 367, ¶¶ 31-32, 122 P.3d 646.

15 After a bench trial on the merits, the trial court found that EDSA performed the following work prior to June 15, 2001; (1) it delineated the wetlands on the Jones, Gygi, and Guymon parcels by drilling seventeen sampling holes with a handheld auger, then examining the samples, backfilling the holes, marking the holes with pin flags, placing ninety-two additional pin flags along the de *299 lineation lines, and marking fifty-one of the pin flags with rebar stakes; (2) it performed a topographical survey of the Jones and Gygi parcels, placing approximately fourteen stakes with flags at the corners of the parcels; (8) it conducted a geotechnical study of the soil and subsurface conditions of the Property by drilling eight sampling holes with a rig brought onto the Property for one day by a subcontractor, then backfilled the holes without marking them; (4) it installed PVC pipe into eight to twelve eight-inch "well" holes to temporarily monitor ground water on the Gygi parcel, then backfilled the holes and marked the holes with orange-topped lathe stakes; (5) it performed a certified boundary survey of the Property, placing one additional stake with a flag on the corner of the Guymon parcel; (6) it removed two man-made "check dams" from a pre-existing irrigation ditch and, using a backhoe, replaced a decrepit underground pipe used to direct water from the ditch, all in an effort to prevent the development of artificial wetlands; and (7) it installed a flat metal weir, designed to temporarily monitor water flow onto a neighbor's property, on the Guymon parcel. The trial court specifically found that "[the surveys, wetlands delineations, ground water monitoring and geotechnical testing had to be performed before EDSA[] could complete the design of the Project." It also found that these activities "were prerequisites to obtaining preliminary and final approvals for the Project from Midway City and the required permit from the U.S. Army Corps of Emgineers," all of which "were required in advance of commencing construction." Finally, it found that EDSA's irrigation improvements were nothing more than "ordinary maintenance of an existing irrigation system." 7

T6 The trial court also found that livestock, including three or four horses and six or seven sheep, were on the Property during the relevant time periods and that as of June 15, 2001, there was no orange netting or silt fencing on the Property, the corners of the buildings and roads were not staked, and there had been no exeavation done, no footings or foundations poured, and no construction materials delivered to or stored on the Property. Based on these findings, which EDSA does not dispute, 8 the trial court once again held that "there was no visible commencement of work on the Property prior to June 15, 2001," 9 ruled that Klibanoff's interest in the Property was superior to EDSA's lien, and awarded Klibanoff his attorney fees and costs pursuant to Utah Code section 38-1-18, see Utah Code Ann. § 38-1-18(1) (2005). EDSA timely appealed.

ISSUES AND STANDARDS OF REVIEW

T7 On appeal, EDSA argues that the trial court's factual findings are insufficient to support its holding that no work was visibly commenced and no materials were furnished on the ground at the Property before June 15, 2001. This presents a mixed question of fact and law. We review the trial court's factual determinations-those findings of historical fact concerning what work was commenced and what materials were delivered-for clear error, and its legal conclusions-specifically, whether that work and those materials were sufficient to satisfy the statute-for correctness. See State v. Pena, 869 P.2d 932, 935-36 (Utah 1994); General Glass Corp. v. Mast Constr. Co., 766 P.2d 429, 485-86 (Utah Ct.App.1988) (reviewing trial court's finding that no work commenced and no materials were delivered on the ground under a clearly erroneous standard).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schenk Family Ltd. Partnership v. Northshore Ltd. Partnership
2016 UT App 124 (Court of Appeals of Utah, 2016)
Steffensen-WC, LLC v. Volunteers of America of Utah, Inc.
2016 UT App 49 (Court of Appeals of Utah, 2016)
Pentalon Construction, Inc. v. Rymark Properties, LLC
2015 UT App 29 (Court of Appeals of Utah, 2015)
PC Crane Service, LLC v. McQueen Masonry, Inc.
2012 UT App 61 (Court of Appeals of Utah, 2012)
Jones v. Riche
2009 UT App 196 (Court of Appeals of Utah, 2009)
HOLLADAY TOWNE CENTER, LLC v. Brown Family Holdings, LC
2008 UT App 420 (Court of Appeals of Utah, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2008 UT App 284, 192 P.3d 296, 609 Utah Adv. Rep. 9, 2008 Utah App. LEXIS 274, 2008 WL 2854133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edsacloward-llc-v-klibanoff-utahctapp-2008.