Ellsworth Paulsen Construction Co. v. 51-SPR, L.L.C.

2006 UT App 353, 144 P.3d 261, 559 Utah Adv. Rep. 14, 2006 Utah App. LEXIS 386, 2006 WL 2506475
CourtCourt of Appeals of Utah
DecidedAugust 31, 2006
Docket20040507-CA
StatusPublished
Cited by5 cases

This text of 2006 UT App 353 (Ellsworth Paulsen Construction Co. v. 51-SPR, L.L.C.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellsworth Paulsen Construction Co. v. 51-SPR, L.L.C., 2006 UT App 353, 144 P.3d 261, 559 Utah Adv. Rep. 14, 2006 Utah App. LEXIS 386, 2006 WL 2506475 (Utah Ct. App. 2006).

Opinion

OPINION

ORME, Judge:

¶ 1 This ease arises from a real estate project gone bad. We have before us the appeal and cross-appeal from several aspects of the trial court’s rulings. We reverse in part and affirm in part, and remand for additional proceedings.

BACKGROUND

¶2 Plaintiff Ellsworth Paulsen Construction Company (Ellsworth) entered into two construction contracts with Guy Hatch and his company, Broadstone Investments, L.C. (Broadstone), under which Ellsworth agreed to act as general contractor for the construction of two commercial buildings (Building I and Building II) as part of a project in American Fork, Utah (the Northshore Prop *264 erty). 51-SPR, L.L.C. (SPR), through its owner, Robert Chimento, entered into an agreement with Hatch and Broadstone (the Agreement), which provided, among other things, that SPR would contribute $2.9 million toward the purchase and development of the Northshore Property and take title to the property as a tenant in common with Broad-stone. Based on the Agreement and SPR’s actions, the trial court ruled on a partial summary judgment motion that SPR and Broadstone were joint venturers in the development of the Northshore Property and, thus, that SPR shared liability on the construction contracts Broadstone had entered into with Ellsworth.

¶ 3 Apparently, however, Ellsworth knew nothing about SPR’s involvement in the project, having no direct dealings with SPR until Hatch disappeared toward the end of construction and Ellsworth sought payment on outstanding invoices that Hatch had left unpaid. 1 Until that time, Ellsworth had dealt exclusively with Hatch as the owner of Broadstone, Broadstone being designated under the Agreement as the project manager in charge of supervising construction on the Northshore Property.

¶4 To fund the construction, Broadstone had entered into two separate construction loan arrangements with Central Bank, which Hatch and a co-member of Broadstone, Dan Parkinson, personally guarantied. Under the Agreement, Broadstone was “in charge of obtaining remaining needed construction financing and institutional permanent financing.” The Agreement also required that Broadstone was to “provide financing for needed construction monies for the office building[s] and remaining cash needs of the project” beyond SPR’s $2.9 million investment. The Agreement also expressly provided that “Guy Hatch will guaranty such financing.”

¶ 5 Prior to disappearing, and toward the end of construction on the Northshore Property, Hatch had become suspiciously slow in paying Ellsworth’s invoices, apparently due to the fact that the construction loan funds were almost exhausted. At least according to SPR, Hatch had been drawing on the construction loan funds and using them in other projects unrelated to the Northshore Property. Despite not being paid, Ellsworth continued its work. Toward the end of the project, with the construction loan funds apparently exhausted and Hatch having disappeared, Ellsworth had nowhere to send its final three draw requests.

¶ 6 Throughout the earlier course of construction, Ellsworth would submit draw requests to Central Bank either directly or through Hatch. Once the draws were approved, Central Bank would then issue cheeks to Ellsworth for its work and for the work of its subcontractors. Each check bore a lien waiver provision on the reverse side of the instrument. 2 The trial court ruled on summary judgment that the lien waivers were valid and enforceable, and therefore cut off any lien rights through the date of each draw request, which is the date the draw was requested and not the date the check was received or cashed. In considering a subsequent motion for summary judgment, however, the trial court ruled that the indemnity provision within the lien waivers was inapplicable, invalid, and unenforceable, and that Ellsworth was not responsible to indemnify SPR against any subcontractor claims.

*265 ¶ 7 After Hatch disappeared and the loan funds were exhausted, Ellsworth learned of SPR’s involvement in the project and approached SPR directly for payment for the completed work. SPR, viewing itself as a mere investor or limited partner, disclaimed any obligation to pay Ellsworth or its subcontractors. 3 Ellsworth then filed a mechanic’s lien against Building I and Building II, and commenced this action to foreclose the lien. 4 After initially ruling on a motion for summary judgment that there was a question of fact concerning whether Ellsworth’s lien had been timely filed, the trial court reconsidered its ruling and concluded that the mechanic’s lien was timely filed and otherwise valid. Also on summary judgment, the trial court dismissed Ellsworth’s claim that SPR failed to obtain a payment bond.

¶ 8 Ellsworth brought additional claims against Hatch and Broadstone for, among other things, failure to pay amounts due under two construction contracts entered into pursuant to the Agreement. Ellsworth brought those same claims against SPR on the theory that SPR was in a joint venture relationship with Hatch and Broadstone in the development of the Northshore Property. SPR defended against these claims by initiating, in a separate proceeding which was later consolidated into this lawsuit, an action to quiet title in Building I and Building II. SPR also brought claims against Ellsworth under Utah’s abusive hen statute, see Utah Code Ann. § 38-1-25 (2005), for including in its lien claim $78,000 that SPR asserted was attributable to an unrelated project on which Hatch and Ellsworth were collaborating without SPR’s involvement.

¶ 9 A three-day bench trial was held on the issues not previously decided on summary judgment. At the conclusion of the trial, the court ruled in Ellsworth’s favor on its lien and breach of contract claims in the amount of just over $721,000. Although it disallowed the claim for $78,000, the trial court denied SPR’s related abusive lien argument, holding that Ellsworth had acted in good faith in including the $78,000 in its lien claim and had not intended to exact more from SPR than was due. The trial court also granted Ells-worth attorney fees as the prevailing party under the lien statute, but refused to award Ellsworth pre-judgment contractual interest on its final three draws because Ellsworth never submitted those final draws and, thus, the court could not fix a date at which the contract was breached and from which interest began to accrue. Both sides now appeal various aspects of the trial court’s resolution of this complicated dispute.

ANALYSIS

I. Joint Venture Ruling

¶ 10 SPR argues that the trial court erred in concluding, on partial summary judgment, that it was in a joint venture relationship with Broadstone and Hatch. Specifically, SPR attacks the trial court’s conclusion that SPR had a duty to share in the losses of the Northshore Property. Because there is a genuine issue of material fact regarding the key issue of whether SPR agreed to share losses with Broadstone and Hatch, we reverse the trial court’s partial summary judgment ruling.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DAYNIGHT, LLC v. Mobilight, Inc.
2011 UT App 28 (Court of Appeals of Utah, 2011)
Ellsworth Paulsen Construction Co. v. 51-SPR-L.L.C.
2008 UT 28 (Utah Supreme Court, 2008)
Uhrhahn Construction & Design, Inc. v. Hopkins
2008 UT App 41 (Court of Appeals of Utah, 2008)
Wasatch Oil & Gas, L.L.C. v. Reott
2007 UT App 223 (Court of Appeals of Utah, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2006 UT App 353, 144 P.3d 261, 559 Utah Adv. Rep. 14, 2006 Utah App. LEXIS 386, 2006 WL 2506475, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellsworth-paulsen-construction-co-v-51-spr-llc-utahctapp-2006.