Uhrhahn Construction & Design, Inc. v. Hopkins

2008 UT App 41, 179 P.3d 808, 598 Utah Adv. Rep. 24, 2008 Utah App. LEXIS 45, 2008 WL 466569
CourtCourt of Appeals of Utah
DecidedFebruary 22, 2008
Docket20060616-CA
StatusPublished
Cited by20 cases

This text of 2008 UT App 41 (Uhrhahn Construction & Design, Inc. v. Hopkins) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uhrhahn Construction & Design, Inc. v. Hopkins, 2008 UT App 41, 179 P.3d 808, 598 Utah Adv. Rep. 24, 2008 Utah App. LEXIS 45, 2008 WL 466569 (Utah Ct. App. 2008).

Opinion

OPINION

ORME, Judge:

¶ 1 Lamar Hopkins (Hopkins) and Joan B. Hopkins, individually and as trustees (the homeowners), appeal from a judgment, entered following a bench trial, by which the trial court ruled in favor of Uhrhahn Construction & Design, Inc. on its mechanic’s lien and breach of contract claims. 1 This case presents the issue, among others, of whether parties to a construction contract can orally agree on extra work to be performed when the written contract contains a provision requiring change orders or “extras” to be put in writing. We affirm the trial court’s breach of contract determination, reverse its mechanic’s lien and attorney fees rulings, and remand for a determination of the homeowners’ attorney fees, limited to those fees incurred in litigating the timeliness of the mechanic’s lien enforcement action.

BACKGROUND 2

¶2 This dispute involves Uhrhahn’s written proposals for the partial construction of the homeowners’ house, in which Uhrhahn estimated the cost and specifications for multiple projects it would complete. Each proposal stated that “[a]ny alteration or deviation from above specifications involving extra costs will be executed only upon written orders.” Hopkins signed the proposals under sections titled “Acceptance of Proposal.” 3

¶ 3 The trial court found that “Hopkins ... made several requests for additional work to the home which [were] not included in the initial proposals,” and that “Uhrhahn ... completed a substantial amount of the additional work requested.” Hopkins paid for work performed in connection with at least three of the additional requests, only one of which may have been in writing. 4

¶4 The trial court further found that “[djuring the initial bidding process, Mr. Hopkins requested installation of Durisol blocks on the home rather than standard cinder blocks.” “[He] represented to [Roger] Uhrhahn ... that the Durisol blocks were easier to install than traditional cinder *812 block and would take half the time.” He also “gave [Roger] Uhrhahn written information about the blocks, which turned out to be incomplete.” The trial court found that the Durisol blocks Hopkins provided for Uh-rhahn to install “were deformed, requiring [Uhrhahn] to expend a substantial amount of additional time to install the blocks, above and beyond the initial proposal amount.” This increased installation time caused Uh-rhahn to incur expenses above its original estimation for the Durisol block project.

¶ 5 The dispute that ensued over the Duri-sol blocks led to the deterioration of the parties’ relationship. Hopkins refused to pay Uhrhahn for the extra cost incurred while installing the deformed blocks, and Uhrhahn refused to continue working if it was not paid. For reasons that are not entirely clear, Uhrhahn did continue to work on the house, probably because Roger Uhrhahn was under the impression that Hopkins would pay after Uhrhahn provided “a complete breakdown and analysis of all costs to date, including additions, with documentation.” After Uhrhahn provided the detailed information, Hopkins still refused to pay.

¶ 6 On March 28, 2003, Uhrhahn filed a complaint in district court “to collect a debt and to foreclose on a Mechanic’s lien” pursuant to Utah Code section 38-1-11, see Utah Code Ann. § 38-1-11 (Supp.2001). 5 The homeowners then filed an answer, counterclaim, and third-party complaint, alleging breach of contract and wrongful lien, and seeking punitive damages and attorney fees. After a bench trial, the court entered a memorandum decision on September 15, 2005, ruling in favor of Uhrhahn on its claims and against the homeowners on theirs. The trial court directed Uhrhahn to prepare findings of fact and conclusions of law following a damages hearing. After the damages hearing held on February 22, 2006, the homeowners objected to Uhrhahn’s proposed factual findings because the findings failed to indicate whether or not the mechanic’s lien was timely filed. The trial court entered its final factual findings and conclusions of law on June 7, 2006, without addressing the homeowners’ concern, and they now appeal the court’s final order.

ISSUES AND STANDARDS OF REVIEW

¶ 7 The first issue is whether the parties entered into a contract implied in fact that allowed them to agree orally to changes and extra work that deviated from the proposal agreement. Whether a contract implied in fact exists is generally considered a question of fact, and we review a trial court’s factual findings under the deferential clearly erroneous standard. See Ryan v. Dan’s Food Stores, Inc., 972 P.2d 395, 401 (Utah 1998); Sorenson v. Kennecott-Utah Copper Corp., 873 P.2d 1141, 1144 (Utah Ct.App.1994). However, we “ ‘retain[ ] the power to decide whether, as a matter of law, a reasonable [fact finder] could find that an implied contract exists.’” Ryan, 972 P.2d at 401 (quoting Sanderson v. First Sec. Leasing Co., 844 P.2d 303, 306 (Utah 1992)). As our review of this matter is limited to the trial court’s factual findings, which we accept as valid, we will be determining whether an implied-in-fact contract exists as a matter of law in light of those findings.

¶ 8 The second issue is whether the trial court’s damages award was proper given the lack of explicit factual findings regarding the award. “[An] award of damages is a factual determination that we review for clear error.” Saleh v. Farmers Ins. Exch., 2006 UT 20, ¶ 29, 133 P.3d 428.

¶ 9 The third issue is whether the trial court, albeit only implicitly, correctly determined that Uhrhahn timely filed its mechanic’s hen enforcement action under Utah Code section 38-1-11. See Utah Code Ann. § 38-l-ll(l)(b) (Supp.2001) (current version at Utah Code Ann. § 38-1-11(2) (Supp. 2007)). “[Statutory interpretation [presents] a question of law that we review for correctness.” Sill v. Hart, 2007 UT 45, ¶ 5, 162 P.3d 1099.

*813 ¶ 10 Finally, in light of our disposition of the third issue, the fourth issue is whether the homeowners were the successful party in the mechanic’s hen action, thus entitling them to attorney fees under Utah Code section 38-1-18. See Utah Code Ann. § 38-1-18(1) (Supp.2001) (current version at Utah Code Ann. § 38-1-18

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Utah, 2026
Copper Hills Custom Homes v. Griffin
2024 UT App 110 (Court of Appeals of Utah, 2024)
Wilson v. Wilson
2024 UT App 87 (Court of Appeals of Utah, 2024)
Beauty Lab and Laser v. Jelosek
2023 UT App 139 (Court of Appeals of Utah, 2023)
Bear v. Lifemap Assurance
2021 UT App 129 (Court of Appeals of Utah, 2021)
Jensen v. West Jordan City
Tenth Circuit, 2020
Cai v. Huntsman Corporation
Tenth Circuit, 2020
Cook Martin Poulson v. Smith
2020 UT App 57 (Court of Appeals of Utah, 2020)
Seamons v. Wiser
2020 UT App 33 (Court of Appeals of Utah, 2020)
Copper Hills Custom Homes, LLC v. Countrywide Bank, FSB
428 P.3d 1133 (Utah Supreme Court, 2018)
Copper Hills v. Countrywide Bank
2018 UT 42 (Utah Supreme Court, 2018)
Houweling's Nurseries Oxnard, Inc. v. Robertson
276 F. Supp. 3d 1239 (D. Utah, 2017)
Burr v. Koosharem Irrigation Company
2017 UT App 123 (Court of Appeals of Utah, 2017)
Judd v. Bowen
2017 UT App 56 (Court of Appeals of Utah, 2017)
Brasher v. Christensen
2016 UT App 100 (Court of Appeals of Utah, 2016)
Outsource Receivables Management, Inc. v. Bishop
2015 UT App 41 (Court of Appeals of Utah, 2015)
Gardiner v. Vanderwerff
2014 UT 56 (Utah Supreme Court, 2014)
Lane Myers Construction, LLC v. Countrywide Home Loans, Inc.
2012 UT App 269 (Court of Appeals of Utah, 2012)
Anderson v. Larry H. Miller Communications Corp.
2012 UT App 196 (Court of Appeals of Utah, 2012)
Smith v. SECURITY INVESTMENT LTD.
2009 UT App 355 (Court of Appeals of Utah, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2008 UT App 41, 179 P.3d 808, 598 Utah Adv. Rep. 24, 2008 Utah App. LEXIS 45, 2008 WL 466569, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uhrhahn-construction-design-inc-v-hopkins-utahctapp-2008.