Davies v. Olson

746 P.2d 264, 70 Utah Adv. Rep. 42, 1987 Utah App. LEXIS 591, 1987 WL 3494
CourtCourt of Appeals of Utah
DecidedNovember 24, 1987
Docket860145-CA, 860146-CA
StatusPublished
Cited by51 cases

This text of 746 P.2d 264 (Davies v. Olson) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davies v. Olson, 746 P.2d 264, 70 Utah Adv. Rep. 42, 1987 Utah App. LEXIS 591, 1987 WL 3494 (Utah Ct. App. 1987).

Opinion

BILLINGS, Judge:

Both parties appeal from the trial court’s May 17, 1985 judgment against defendant Olson, purporting to award plaintiffs their reasonable costs (plus interest) incurred in constructing four duplexes for defendants. We affirm the trial court’s finding that there was no contract, and the court’s conclusion that quantum meruit was, therefore, the proper theory of recovery. We, however, reverse the finding of no liability on the part of defendant Lund. We remand for findings as to whether he (1) requested plaintiffs to perform work and if so, to what extent, and/or (2) received any benefits as a result of plaintiffs’ construction of the duplexes, and an entry of a judgment consistent with those findings and our opinion. We further reverse the trial court’s calculation of damages against defendant Olson and remand for a determination of the reasonable value of plaintiffs’ services in constructing the duplexes, and an entry of a judgment in that amount against defendant Olson.

FACTS

The following facts were developed in a bifurcated trial held on five nonconsecutive days over a two-year eight-month period. 1 Plaintiff Davies and defendant Olson orally agreed that Davies would construct four duplexes for Olson. The parties originally agreed that plaintiff Davies would construct the duplexes for “cost plus $6,000 builder’s profit per duplex.” Based on this oral agreement, plaintiff Davies prepared a cost breakdown and submitted it to Wasatch Bank for acquisition of long-term financing, and to defendant Olson. Subsequently, defendant Olson requested numerous changes and additions to the original specifications for the duplexes.

Soon thereafter, defendants, in an attempt to establish a ceiling price on the *266 cost of construction at $72,070 per duplex, prepared a contract and submitted it to plaintiffs. In his letter to plaintiffs, defendant Olson stated that the purpose of the proposed contract was “mainly to satisfy [defendant] Lund” as he was concerned about fixing a ceiling price. This contract, however, was never executed.

A settlement statement, dated July 7, 1981 and signed by defendant Lund, fixed the contract sales price at $128,500. This settlement statement was used at the closing with Wasatch Bank. Wasatch Bank provided permanent financing, which was insufficient to cover plaintiffs’ construction expenses. Consequently, plaintiffs initiated an action against, among others, defendants Olson and Lund, alleging claims of fraud, breach of contract, and foreclosure of mechanics’ liens. (The foreclosure claim was resolved).

After the initial trial on August 2, 1982 and September 13, 1982, the trial court entered judgment on August 4, 1983 against defendants Lund and Olson for $23,741.54 2 plus 12% interest accruing from July 7, 1981. The court found there was no agreement among the parties as to the total price to be paid for the construction of the duplexes. The court, however, based on the initial cost breakdown prepared by plaintiff Davies, found defendants jointly liable for $23,741.54. The court then found that plaintiffs were additionally entitled to recover from defendant Olson the reasonable costs incurred because of defendant Olson’s requested changes in the duplex specifications. 3 The court then directed counsel to negotiate and submit a figure as to the reasonable costs plaintiffs incurred because of defendant Olson’s requested changes. The parties failed to reach an agreement. Consequently, a supplemental hearing was held on April 4, 1985, April 10, 1985, and April 16, 1985, focusing on the following issues previously reserved by the trial court:

1. What were the plans and specifications upon which plaintiffs and defendants relied in the cost breakdown?
2. What modifications were subsequently made to those plans and specifications upon defendant Olson’s requests?
3. What were the reasonable costs of the requested modifications which were actually made by plaintiffs?

The trial court, in its final judgment of May 17, 1985, found there was no meeting of the minds between the parties “as to plans and specifications which formed the basis of the cost breakdown,” and, therefore, that it erred in basing its August 4, 1983 judgment on that document. The court concluded that in order to prevent unjust enrichment of defendant Olson, plaintiffs were entitled to recover their reasonable costs of construction from him. The court, however, was silent as to defendant Lund’s liability. The court awarded plaintiffs $51,773.96 plus interest “at the legal rate of interest,” accruing from July 7, 1981, the date the settlement statement was executed. The trial court calculated the May 17, 1985 judgment as follows:

Reasonable cost of construction $366,703.96
Less adjustment for water meters 1,360.00
NET CONSTRUCTION COST 365,363.96
Less the Amount of the August 4 Judgment 4 313,580.00
May 17, 1985 Judgment to Plaintiffs $51,773.96

Both parties appeal from the May 17, 1985 judgment.

I. SUFFICIENCY OF THE EVIDENCE

On appeal, we are asked to determine whether there is sufficient evidence to support the trial court’s finding of no enforceable written or oral contract. The *267 trial court’s findings of fact will not be set aside unless “clearly erroneous.” Utah R.Civ.P. 52(a); State v. Wright, 744 P.2d 315 (Utah Ct.App.1987); State v. Walker, 743 P.2d 191,193 (Utah 1987). A review of the record amply supports the trial court’s findings (1) that there was no meeting of the minds as to the contract price, an essential term of a construction contract; (2) that there was no meeting of the minds as to which plans and specifications formed the basis of the cost breakdown prepared by plaintiff Davies; and (3) that the parties did not intend the settlement statement to constitute an executory accord.

Testimony at trial conflicted significantly as to the contract price. Plaintiff Davies testified that he and defendant Olson orally agreed that plaintiff Davies would construct the four duplexes for cost plus $6,000 builder’s profit per duplex. Defendant Olson, on the other hand, while conceding that cost plus $6,000 was discussed, denied that he agreed to an open-ended deal. Subsequent to the oral conversation between plaintiff Davies and defendant Olson, plaintiff Davies prepared a cost breakdown and submitted it to Wasatch Bank and to defendant Olson. Thereafter, defendant Olson prepared a written contract with a provision that cost was not to exceed $72,070 per duplex, evidently attempting to appease defendant Lund’s concern about cost. Defendant Olson presented this proposed contract to plaintiff Davies, claiming Davies said that he would sign it. This contract, however, was never executed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vander Veur v. Groove Entertainment Technologies
2018 UT App 148 (Court of Appeals of Utah, 2018)
Express Recovery Services Inc. v. Reuling
2015 UT App 299 (Court of Appeals of Utah, 2015)
Saenz Mencia v. Allred
808 F.3d 463 (Tenth Circuit, 2015)
Jones v. MacKey Price Thompson & Ostler
2015 UT 60 (Utah Supreme Court, 2015)
Simons v. Park City RV Resort, LLC
2015 UT App 168 (Court of Appeals of Utah, 2015)
Outsource Receivables Management, Inc. v. Bishop
2015 UT App 41 (Court of Appeals of Utah, 2015)
Northgate Village Development, LC v. Orem City
2014 UT App 86 (Court of Appeals of Utah, 2014)
Dolan v. McQuaide
79 A.3d 394 (Court of Special Appeals of Maryland, 2013)
Soundvision Technologies, LLC v. Templeton Group Ltd.
929 F. Supp. 2d 1174 (D. Utah, 2013)
Wilberg v. Hyatt
2012 UT App 233 (Court of Appeals of Utah, 2012)
Portercare Adventist Health System v. Lego
312 P.3d 201 (Colorado Court of Appeals, 2010)
Johnson v. Larson
2010 SD 20 (South Dakota Supreme Court, 2010)
Ashby v. Ashby
2010 UT 7 (Utah Supreme Court, 2010)
E & M Sales West, Inc. v. Bechtel Jacobs Co.
2009 UT App 299 (Court of Appeals of Utah, 2009)
TruGreen Companies, L.L.C. v. Mower Bros., Inc.
2008 UT 81 (Utah Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
746 P.2d 264, 70 Utah Adv. Rep. 42, 1987 Utah App. LEXIS 591, 1987 WL 3494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davies-v-olson-utahctapp-1987.