Gooch v. Hiatt

337 N.E.2d 585, 166 Ind. App. 521, 1975 Ind. App. LEXIS 1388
CourtIndiana Court of Appeals
DecidedNovember 19, 1975
Docket3-474A58
StatusPublished
Cited by21 cases

This text of 337 N.E.2d 585 (Gooch v. Hiatt) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gooch v. Hiatt, 337 N.E.2d 585, 166 Ind. App. 521, 1975 Ind. App. LEXIS 1388 (Ind. Ct. App. 1975).

Opinion

Hoffman, J.

Plaintiff-appellee Ernest Hiatt d/b/a Hiatt Electric (Hiatt) commenced this action in the trial court to foreclose a mechanic’s lien claimed by him upon certain real estate owned by defendants-appellants William E. Gooch and Mae Gooch (Gooch). Following a trial to the court, judgment was entered in favor of Hiatt. Gooch’s motion to correct errors was overruled, and this appeal was perfected.

On appeal, Gooch first asserts that Hiatt failed to prove that the subject mechanic’s lien was timely filed.

*524 *523 Indiana law places a burden upon a mechanic’s lienholder who seeks to foreclose such a lien to show that the purported *524 lien meets all statutory requirements necessary to its creation. Hough v. Zehrner (1973), 158 Ind. App. 409, 302 N.E.2d 881; Kidd Bros. Lumber Co., Inc. v. Tonnis et al. (1958), 128 Ind. App. 459, 149 N.E.2d 828. Accordingly, it must be determined whether the evidence in the record of this cause is sufficient to support the trial court’s determination that Hiatt’s lien was timely filed.

.When.questions regarding the sufficiency of evidence are raised on appeal, this court will only consider the evidence most favorable to the appellee together with all reasonable inferences to be drawn therefrom. We will neither weigh the evidence nor determine the credibility of witnesses.- Freeman v. State (1975), 163 Ind. App. 650, 325 N.E.2d 485.

The evidence and reasonable inferences therefrom most favorable to appellee Hiatt in the record of this cause establish that from 1959 until the time of trial he was engaged in an electrical and heating contracting business. During 1967, Gooch authorized Hiatt to install the wiring and certain heating, lighting and air conditioning equipment in a building which was then under construction. No formal plans or specifications for such building were furnished to Hiatt, and no written contract was executed between the parties.

From time to time as the work on the building progressed, Gooch specified the type of equipment which he desired to have installed. Some of the items so specified by Gooch were deviations from, or additions to, the type of work which the parties discussed prior to the commencement of such work.

The actual construction of the subject structure was completed in November of 1967. However, the oil furnaces which had been installed by Hiatt failed to function reliably throughout the following winter and when a request for payment was made by Hiatt, Gooch refused to make payment for any of-the work -until such defect and other alleged defects were cor *525 rected. In response to one of many complaints about the operation of the furnaces, Hiatt installed an additional fuel line and “check valves” on July 30,1968. Thereafter, on September 23, 1968, Hiatt filed a notice of intent to hold a mechanic’s lien on the subject structure.

Appellant Gooch asserts that because the subject, structure was completed and the furnaces were capable of operation in November, 1967, the trial court erred as a matter of law in holding that Hiatt’s mechanic’s lien was timely filed.

IC 1971, 32-8-3-3 (Burns Code Ed.), provides, in pertinent part:

“Any person who wishes to acquire a lien upon any property, whether his claim be due or not, shall file in the recorder’s office of the county, at any time within sixty [60] days after performing such labor or furnishing such materials, or machinery, described in section 1 [32-8-3-1] of this act, a sworn statement in duplicate of his intention to hold a lien upon such property for the amount of his claim, ***.”

This court has held that such 60-day period for the filing of a mechanic’s lien may not be extended, nor the right to such a lien revived, through the performance by the contractor of some act incidental to the work, or which is not done in good faith with the intention of completing the job. Miller Monuments, Inc. v. Asbestos Insul. etc. (1962), 134 Ind. App. 48, 185 N.E.2d 533; Ellis v. Auch, et al. (1954), 124 Ind. App. 454, 118 N.E.2d 809; Chapman-Stein Co. v. Lippincott Glass Co. (1928), 87 Ind. App. 411, 161 N.E. 645. Cf: Conlee et al. v. Clark et al. (1896), 14 Ind. App. 205, 42 N.E. 762.

However, where a property owner will not accept lienable work as completed and refuses to pay for the same until satisfactory corrective work is done, such property owner is estopped from asserting that the contracted . work had been completed as of an earlier • date. Walker v. Statzer (1972), 152 Ind. App. 544, 284 N.E.2d 127 *526 (transfer denied) ; Miller Monuments, Inc. v. Asbestos Insul. etc., supra.

In the case at bar, the additional work which is relied upon for the timeliness of appellee’s lien was performed by him following a complaint about the furnaces by the owner. Inasmuch as the owner had not yet paid for any of the work at the time of such complaint and additional work, and subsequently stated that the work was unacceptable and that payment would be withheld until corrective action was taken, he must be estopped from now asserting that the job was completed prior to such additional work. It must be concluded that the trial court properly found that the subject lien was filed within sixty days of the date that the last materials and labor were expended on the job and, thus, that such lien was timely filed.

Appellant Gooch next asserts that because no contract existed between these parties, any recovery by Hiatt must rest upon the theories of quantum meruit and quantum valebant. Therefore, he contends, evidence of the reasonable value of the materials and labor was necessary to allow the trial court to find in favor of Hiatt, and although evidence of Hiatt’s charges to Gooch was introduced, there was “no evidence from which the [trial] Court could have found the reasonable value of the labor performed and materials furnished by the Contractor in the installation of the heating equipment in the Owner’s building.”

However, even assuming that proof of the reasonable value of such materials and services was necessary to Hiatt’s case, evidence was introduced at trial establishing such value. At trial, Hiatt detailed his charges to Gooch for all the materials furnished and services rendered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quantum Concrete Inc v. Plaza De Kaza LLC
Michigan Court of Appeals, 2023
Cho v. Purdue Research Foundation
803 N.E.2d 1161 (Indiana Court of Appeals, 2004)
Abbey Villas Development Corp. v. Site Contractors, Inc.
716 N.E.2d 91 (Indiana Court of Appeals, 1999)
Riddle v. Newton Crane Service, Inc.
661 N.E.2d 6 (Indiana Court of Appeals, 1996)
Interiors Contracting, Inc. v. Smith, Halander & Smith Associates
881 P.2d 929 (Court of Appeals of Utah, 1994)
McCorry v. G. Cowser Construction, Inc.
636 N.E.2d 1273 (Indiana Court of Appeals, 1994)
Wilson v. Jenga Corp.
490 N.E.2d 375 (Indiana Court of Appeals, 1986)
Biggerstaff v. Vanderburgh Humane Society, Inc.
453 N.E.2d 363 (Indiana Court of Appeals, 1983)
DISPLAY FIXTURES CO., ETC. v. RL Hatcher, Inc.
438 N.E.2d 26 (Indiana Court of Appeals, 1982)
Clouse v. Fielder
431 N.E.2d 148 (Indiana Court of Appeals, 1982)
Smith v. Bruning Enterprises, Inc.
424 N.E.2d 1035 (Indiana Court of Appeals, 1981)
Duncan v. George Moser Leather Co.
408 N.E.2d 1332 (Indiana Court of Appeals, 1980)
Riggins v. Sadowsky
403 N.E.2d 1152 (Indiana Court of Appeals, 1980)
Contech Architects & Engineers, Inc. v. Courshon
387 N.E.2d 464 (Indiana Court of Appeals, 1979)
Phillips v. State
386 N.E.2d 704 (Indiana Court of Appeals, 1979)
Lovko v. Lovko
384 N.E.2d 166 (Indiana Court of Appeals, 1978)
Capital Improvement Board of Managers v. Public Service Commission
375 N.E.2d 616 (Indiana Court of Appeals, 1978)
Stanray Corporation v. Horizon Construction, Inc.
342 N.E.2d 645 (Indiana Court of Appeals, 1976)
Van Wells v. Stanray Corporation
341 N.E.2d 198 (Indiana Court of Appeals, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
337 N.E.2d 585, 166 Ind. App. 521, 1975 Ind. App. LEXIS 1388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gooch-v-hiatt-indctapp-1975.