Riddle v. Newton Crane Service, Inc.

661 N.E.2d 6, 1996 Ind. App. LEXIS 42, 1996 WL 34052
CourtIndiana Court of Appeals
DecidedJanuary 31, 1996
Docket49A02-9507-CV-435
StatusPublished
Cited by6 cases

This text of 661 N.E.2d 6 (Riddle v. Newton Crane Service, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riddle v. Newton Crane Service, Inc., 661 N.E.2d 6, 1996 Ind. App. LEXIS 42, 1996 WL 34052 (Ind. Ct. App. 1996).

Opinion

OPINION

BARTEAU, Judge.

Harold Riddle appeals the trial court’s entry of judgment in favor of Newton Crane Services (Newton) on Newton’s Complaint to Foreclose Mechanic’s Lien and on Riddle’s counterclaims for slander of title and abuse of process. The dispositive issue presented on appeal is: at what point is a contractor’s *8 work complete so as to trigger the 60-day period for recording a notice of intent to hold mechanic’s lien?

FACTS

Riddle contracted with Citadel Contracting Corporation for the construction of a truck service center in Indianapolis. On July 9, 1993, Citadel entered into a subcontract with Blue Jay Erectors, Inc. (Blue Jay) for the placement of concrete wall panels. Blue Jay, in turn, subcontracted with Newton for crane service to lift the concrete wall panels into place.

Newton moved a 140-ton crane onto the job site on October 1, 1993, and work was conducted with that crane from October 4 through October 8. The 140-ton crane was removed on October 12, 1993. On October 28, 1993, Newton moved an 80-ton crane to the site, which was used to lift wall panels on October 28, 1993. The 80-ton crane was removed from the site on November 6, 1993.

On January 3, 1994, Newton recorded in the office of the Marion County Recorder its sworn statement and notice of intention to hold a mechanic’s lien against Riddle’s real estate in the amount of $12,420.89, describing the work done oh the property as “crane service.” Thereafter, Newton filed its Complaint to Foreclose Mechanic’s Lien, and Riddle filed counterclaims alleging slander of title and abuse of process.

DISCUSSION

Judgment was entered after a bench trial in which the trial court made special findings of fact and conclusions of law pursuant to Riddle’s motion under Ind.Trial Rule 52(A). When the trial court has made special findings, this court on appeal applies a two-tiered standard of review. First we must determine whether the evidence supports the findings. Then, we must determine whether the findings support the judgment. If the findings support the judgment and are not clearly erroneous, the judgment must be affirmed. We will consider only the evidence in the record which supports the judgment, along with the reasonable inferences to be drawn from the evidence. McCorry v. G. Cowser Const., Inc., 636 N.E.2d 1273, 1276 (Ind.Ct.App.1994), adopted, 644 N.E.2d 550 (Ind.1994) (citing United Farm Bureau Mut. Ins. Co. v. Ira, 577 N.E.2d 588, 592 (Ind.Ct.App.1991), trans. denied).

The parties do not dispute the trial court’s findings that Newton worked on Riddle’s property with the 140-ton crane from October 4 through October 8, and removed the crane on October 12, 1993, or that Newton used the 80-ton crane only on October 28, 1993, and removed that crane from the site on November 6. Riddle challenges the trial court’s finding that the last date Newton provided labor and equipment under its contract was November 6, and the trial court’s conclusion that Newton timely filed its notice of intention to hold mechanic’s lien within 60 days of completing the work.

A notice of intention to hold mechanic’s lien must be filed with the county Recorder within 60 days after performing labor or furnishing materials or machinery. Ind. Code 32-8-3-3(a). Newton recorded its notice of intention to hold mechanic’s lien on January 3,1994, 58 days after it removed the 80-ton crane from the job site, but 67 days after it completed lifting wall panels at the site. Riddle argues that Newton’s work was complete when it finished lifting wall panels on October 28, 1993. Newton counters that its work was not complete until the crane was removed from the site, and points to its invoice specifically charging for removing the crane from the property. 1

The Indiana statute governing filing of a notice of intention to hold mechanic’s Hen is in derogation of common law, and its provisions must be strictly construed. Wavetek Indiana, Inc. v. K.H. Gatewood Steel Co., Inc., 458 N.E.2d 265 (Ind.Ct.App.1984). The fifing of a notice of intention to hold mechanic’s lien by a subcontractor is timely if the lien is filed within 60 days of the date when *9 the last work is done by the subcontractor. McCorry, 636 N.E.2d at 1281 (citing Gooch v. Hiatt, 166 Ind.App. 521, 526, 337 N.E.2d 585, 588 (1975)). The 60-day period may not be extended through the performance of an act incidental to the contract. Gooch, 166 Ind.App. at 525, 337 N.E.2d at 588 (citing Miller Monuments, Inc. v. Asbestos Insulating & Roofing Co., 134 Ind.App. 48, 185 N.E.2d 533 (1962); Ellis v. Auch, 124 Ind.App. 454, 118 N.E.2d 809 (1954); Chapman-Stein Co. v. Lippincott Glass Co., 87 Ind.App. 411, 161 N.E. 645 (1928)). The resolution of this appeal turns upon whether removing the crane from the job site constituted work on the part of Newton, or was merely incidental to its task of lifting the wall panels into place.

The parties have not cited to this Court any authority directly on point, and our research has not uncovered prior Indiana decisions controlling in this matter. We note, however, that the Michigan Court of Appeals considered similar situations in Superior Steel Systems, Inc. v. Nature’s Nuggets, Inc., 174 Mich.App. 368, 435 N.W.2d 492 (1989) and Blackwell v. Bornstein, 100 Mich.App. 550, 299 N.W.2d 397 (1980).

In Blackwell, a subcontractor returned to a job site to pick up tools left behind and claimed that such was the last work done at the site causing the filing period to commence. The Michigan Court of Appeals found that the Michigan Mechanic’s Lien Act made no distinction between “actual work” and picking up tools or “last minute cleanup.” 299 N.W.2d at 399. The Court concluded that, under the required liberal construction of Michigan’s Mechanic’s Lien Act, 2 the last minute cleanup was sufficiently related to the labor and materials supplied by the subcontractor because it was an integral part of the work the subcontractor had done. Id.

In Superior Steel, however, the Michigan Court of Appeals reached a different result. In that case, a subcontractor completed work in 1985, but left a concrete compactor on the job site until August 23, 1986.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richard A. Clem v. Paul J. Watts
27 N.E.3d 789 (Indiana Court of Appeals, 2015)
Dinsmore v. Lake Elec. Co., Inc.
719 N.E.2d 1282 (Indiana Court of Appeals, 1999)
Abbey Villas Development Corp. v. Site Contractors, Inc.
716 N.E.2d 91 (Indiana Court of Appeals, 1999)
Jones v. Harner
Indiana Supreme Court, 1998
Jones v. Harner
684 N.E.2d 560 (Indiana Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
661 N.E.2d 6, 1996 Ind. App. LEXIS 42, 1996 WL 34052, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riddle-v-newton-crane-service-inc-indctapp-1996.