Walker v. Statzer

284 N.E.2d 127, 152 Ind. App. 544, 1972 Ind. App. LEXIS 1010
CourtIndiana Court of Appeals
DecidedJune 23, 1972
Docket1271A270
StatusPublished
Cited by14 cases

This text of 284 N.E.2d 127 (Walker v. Statzer) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walker v. Statzer, 284 N.E.2d 127, 152 Ind. App. 544, 1972 Ind. App. LEXIS 1010 (Ind. Ct. App. 1972).

Opinion

Sullivan, J.

This appeal involves a judgment foreclosing plaintiff-appellee’s (Contractor) mechanic’s lien and awarding him the sum of $3,500.00 bearing 8% interest per annum from the date of judgment, together with attorney’s fees.

The record discloses that the parties herein entered into an oral agreement on December 15, 1967 pursuant to which the Contractor agreed to repair defendants-appellants’ (Owners) home which was damaged by fire. The Contractor submitted a bid of between $8,735.00 and $9,350.00 for the repair work which bid was accepted by the Owners upon the condition that the house was “to be in at least equal if not better condition than before the fire * * ”. Thereafter, work commenced.

With $3,500.00 ostensibly due and owing on November 22, 1968, the Contractor filed “notice of intention to hold a mechanic’s lien” — the basis for this action.

For the purpose of discovering whether work and materials had been furnished within sixty days preceding the date of filing of the lien, 1 Owners filed interrogatories to determine *546 what labor and materials were furnished on September 26, 1968 as alleged by Contractor. Contractor answered the interrogatories indicating the nature of the materials furnished and the work completed as of September 28, 1968. The Ow;ners subsequently moved for summary judgment with supporting affidavits to the effect that work had been completed on March 1, 1968 as opposed to the later September date relied upon by the Contractor. The court overruled the motion and the cause was submitted' for trial to the court without jury.

At trial, the Contractor, Statzer, testified that work continued over a period of time and that in June and September of 1968, the Owners gave him two additional lists of work to be completed; that the last work completed on the house was done on September 26, 1968; that the Owners had paid all but $8,500.00; and that a notice of intention to hold a lien was filed on November 22, 1968.

Appellant-Owner, William Walker, testified that he entered into the oral agreement with the Contractor; that he refused to pay until the work was completed; and that he and his wife did prepare lists of additional work to be completed by the Contractor.

Upon the latter premise, the Contractor argues that the owners are estopped from asserting that the mechanic’s lien was not timely filed within sixty days of work completed.

After judgment had been entered in favor of plaintiff - Contractor the Owners’ motion to correct errors was overruled. The following specifications are assigned as error:

1. The trial court erred in overruling appellants’ (Owners’) motion for summary judgment.
2. The last work performed was incidental work done to extend the time for asserting a mechanic’s lien.
3. The trial court erred in allowing the Contractor to testify as to the value of work done.
4. The awarded damages were excessive.
*547 5. The trial court abused its discretion by failing to find the Contractor’s work to be inferior in light of certain pictorial evidence.
6. The trial court erred in admitting into evidence the Contractor’s Exhibit A which was the bid estimating repair work submitted to Owners’ insurance company.

FAILURE TO FILE AFFIDAVITS IN OPPOSITION TO MOTION FOR SUMMARY JUDGMENT DOES NOT OF ITSELF WARRANT GRANTING OF JUDGMENT TO MOVING PARTY

Summary judgment may be entered only where there is no material issue of fact to be litigated, thereby entitling the moving party to judgment as a matter of law. Mayhew v. Deister (1969), 144 Ind. App. 111, 244 N. E. 2d 448. In the instant cause, appellant-Owners argue that plaintiff-Contractor’s failure to oppose the motion for summary judgment by counter-affidavit reflects the absence of any material issue, thus rendering improper the trial court’s decision to overrule the motion. There is no merit to this contention. No such explication is made by Rule TR. 56(C), which as pertinent reads:

“(C) * * * Summary judgment shall not be granted as of course because the opposing party fails to- offer opposing affidavits or evidence, but the court shall make its determination from the affidavits and testimony offered upon the matters placed in issue by the pleadings or such evidence.” (Emphasis supplied.)

Accord: Hunter v. Cook (1971), 149 Ind. App. 657, 274 N. E. 2d 550.

Prior to the filing of the motion, the plaintiff-Contractor answered interrogatories stating that on September 26, 1968 a ground rod, wire and clamp were installed as a part of the original contract. Subsequently, the motion for summary judgment was filed in which the Owners alleged that no work was done by the Contractor after *548 March 1, 1968. As we have stated, upon a motion for summary judgment, all doubts are resolved in favor of the non-moving party. Lows v. Warfield (1971), 149 Ind. App. 569, 274 N. E. 2d 553. In Lows, we held that the absence of counter-affidavits does not establish prima facie that the movant is entitled to summary judgment. Instead, the trial court must consider pleadings, depositions, answers to interrogatories as well as affidavits to determine whether a genuine issue of material fact exists. Accordingly we find in the case before us that the pleadings and answers to the interrogatories, together with substantive regard given to the Owners’ affidavits, raise a factual issue — namely, whether or not work was performed on or after September 23, 1968, i.e., within sixty days preceding November 22, 1968, the date of filing of the notice of intention to hold a lien. We conclude, therefore, that the trial court properly overruled the Owners’ motion for summary judgment.

OWNERS ESTOPPED FROM ASSERTING THAT WORK WAS COMPLETED AT EARLIER DATE IN LIGHT OF REFUSAL TO MAKE PAYMENT UNTIL ADDITIONAL WORK DONE

The appellant-Owners next argue that work on the contract terminated on March 1, 1968, but that additional work was done by the Contractor as late as September 26, 1968, solely to revive or extend the limitation period for filing the notice of intention to hold a mechanic’s lien. The record indicates that in June and September, 1968, Owners prepared and submitted additional lists of work to be completed before payment would be made to the Contractor. The additional work was completed on September 26, 1968 and the lien was filed on November 22, 1968. Since they refused to pay the plaintiff-Contractor for his services pending completion of the additional work, the Owners are estopped from here asserting that no work had *549 been done after March 1, 1968, or that the contract had been completed as of that earlier date. Miller Monuments, Inc. v. Asbestos Insulating & Roofing Co., Inc. (1962), 134 Ind. App. 48, 185 N. E. 2d 533.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farah, LLC v. Architura Corp.
952 N.E.2d 328 (Indiana Court of Appeals, 2011)
Korellis Roofing, Inc. v. Stolman
645 N.E.2d 29 (Indiana Court of Appeals, 1995)
Nicoll v. Community State Bank
529 N.E.2d 386 (Indiana Court of Appeals, 1988)
CF BROUGHTON, DMD, PC v. Riehle
512 N.E.2d 1133 (Indiana Court of Appeals, 1987)
Charles F. Broughton, D.M.D., P.C. v. Riehle
512 N.E.2d 1133 (Indiana Court of Appeals, 1987)
Nationwide Mutual Insurance Co. v. Neville
434 N.E.2d 585 (Indiana Court of Appeals, 1982)
General Bargain Center v. American Alarm Co.
430 N.E.2d 407 (Indiana Court of Appeals, 1982)
Lenard v. Adams
425 N.E.2d 211 (Indiana Court of Appeals, 1981)
Sears, Roebuck & Co.(Auto Dept.) v. Roque
414 N.E.2d 317 (Indiana Court of Appeals, 1980)
Riggins v. Sadowsky
403 N.E.2d 1152 (Indiana Court of Appeals, 1980)
Levy Co. v. State Board of Tax Commissioners
365 N.E.2d 796 (Indiana Court of Appeals, 1977)
Letson v. Lowmaster
341 N.E.2d 785 (Indiana Court of Appeals, 1976)
Gooch v. Hiatt
337 N.E.2d 585 (Indiana Court of Appeals, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
284 N.E.2d 127, 152 Ind. App. 544, 1972 Ind. App. LEXIS 1010, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walker-v-statzer-indctapp-1972.