J & B Steel Contractors, Inc. v. C. Iber & Sons, Inc.

617 N.E.2d 405, 246 Ill. App. 3d 523, 187 Ill. Dec. 197
CourtAppellate Court of Illinois
DecidedAugust 3, 1993
Docket3-92-0807
StatusPublished
Cited by13 cases

This text of 617 N.E.2d 405 (J & B Steel Contractors, Inc. v. C. Iber & Sons, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J & B Steel Contractors, Inc. v. C. Iber & Sons, Inc., 617 N.E.2d 405, 246 Ill. App. 3d 523, 187 Ill. Dec. 197 (Ill. Ct. App. 1993).

Opinion

JUSTICE BRESLIN

delivered the opinion of the court:

The plaintiff, J & B Steel Contractors, Inc., filed a four-count, second-amended complaint against the defendants, C. Iber & Sons, Inc., and Proctor Community Hospital. The trial court dismissed the plaintiff’s complaint with prejudice pursuant to section 2 — 615 of the Code of Civil Procedure (Ill. Rev. Stat. 1991, ch. 110, par. 2 — 615). The plaintiff appeals. We reverse and remand for further proceedings.

The facts pleaded in the plaintiff’s complaint indicate that Proctor Community Hospital hired defendant C. Iber & Sons, Inc. (hereinafter the defendant), as a general contractor to make certain improvements on property that the hospital owned in Peoria, Illinois. Around December 4, 1989, the defendant subcontracted with the plaintiff to perform certain work on that project which involved a parking structure. On August 31, 1990, the plaintiff suspended its performance under the contract and subsequently filed this lawsuit.

Counts I through III of the plaintiff’s complaint sought foreclosure on a mechanics’ lien claim. Count IV sought damages for a breach of contract. All four counts referred to a contract between the parties which was attached to the complaint as exhibit A. The various counts all contained the following allegations. An “understanding” between the parties provided that the agreed price for the plaintiff’s work was $220,799 and that based on that agreed price, the plaintiff was not obligated to perform work beyond July 31, 1990. The contract between the parties was in accordance with the terms of a telephone “proposal” made on December 4, 1989, by the plaintiff to the defendant, and was “confirmed” by the defendant’s “Purchase Order *** dated December 7,1989” (exhibit A).

Counts I, III, and IV alleged that in its role as general contractor, the defendant had an obligation to supervise and coordinate the construction to allow the plaintiff to complete its work on or before July 31, 1990. Additionally, count I alleged that the defendant breached obligations of good faith and fair dealing implied in the contract by failing to correct problems in the progress of the work.

Count II alleged in the alternative that the plaintiff incurred extra costs as a consequence of a change in the “scope” of its work due to the defendant’s change in the schedule of the job so that it could not be completed by July 31, 1990. Count II further alleged that under the contract, the defendant was obligated to issue a change order to compensate the plaintiff for additional costs resulting from a change in “the scope of [the plaintiff’s] work to the period beyond July 31, 1990.”

Count III, unlike counts I and II, did not seek recovery for extra work or costs incurred as a result of the defendant’s breach of contract, but only recovery for the amount earned under the original contract price. Count IV sought recovery for lost profits on work that the plaintiff did not perform because of the defendant’s breach of contract.

The defendant filed a motion to dismiss the plaintiff’s second amended complaint pursuant to section 2 — 615 of the Code of Civil Procedure. The defendant’s motion alleged four different grounds for dismissal. Specifically, it alleged that: (1) the plaintiff did not comply with the notice requirements of section 24 of the Mechanics Lien Act (Ill. Rev. Stat. 1991, ch. 82, par. 24); (2) the “no damage for delay” clause in the written contract precluded any recovery for the plaintiff; (3) the plaintiff could not recover because it breached the contract; and (4) counts I through III of the plaintiff’s complaint were redundant. After a hearing on the motion, the trial court entered a written order granting the defendant’s motion to dismiss the plaintiff’s complaint with prejudice.

As a preliminary matter, we must address the issue of whether the plaintiff satisfied the statutory notice requirements under the Mechanics Lien Act.

Section 24 of the Mechanics Lien Act provides that the 90-day notice required to perfect a subcontractor’s lien must be “sent by registered or certified mail, with return receipt requested, and delivery limited to addressee only, to or personally served on the owner of record or his agent.” (Emphasis added.) (Ill. Rev. Stat. 1991, ch. 82, par. 24.) Here, the certified mail receipt was not limited to addressee only. The receipt shows that Pat Anderson signed it. The record does not show what relationship the signatory had with the defendant hospital other than that he or she signed the certified receipt in the space for the signature of the agent.

Although Illinois case law provides that notice is required as a basis for bringing a cause of action under the Mechanics Lien Act, if the limited delivery language does not result in a lack of notification, then the lack of notice is not a basis for invalidating the plaintiff’s claim. Watson v. Auburn Iron Works, Inc. (1974), 23 Ill. App. 3d 265, 318 N.E.2d 508; Matthews Roofing Co. v. Community Bank & Trust Co. (1990), 194 Ill. App. 3d 200, 550 N.E.2d 1189; A.Y. McDonald Manufacturing Co. v. State Farm Mutual Automobile Insurance Co. (1992), 225 Ill. App. 3d 851, 587 N.E.2d 623.

The defendant argues that the plaintiff’s complaint should be dismissed because it does not specifically indicate that the defendant received actual notice.

We disagree. The defendant did not allege lack of actual notice and did not argue that it was prejudiced by a lack of actual notice. We find that it was incumbent on the defendant to assert that it did not receive actual notice. None of the cases cited by the parties allowed the dismissal of a complaint for lack of notice on a section 2— 615 motion to dismiss. Rather, the cited cases involved motions for summary judgment at which stage in the proceedings it could be conclusively determined whether the defendant received actual notice. Illinois courts interpret the strict requirements of notice by examining how effectively a party did in fact notify the other side rather than simply basing rights solely on whether every phrase of the statute was followed in exact detail. (See Matthews Roofing Co. v. Community Bank & Trust Co. (1990), 194 Ill. App. 3d 200, 550 N.E.2d 1189.) Accordingly, we hold that under the circumstance presented here, lack of notice was not a proper ground for dismissal on a section 2 — 615 motion to dismiss.

Turning to the merits, we note that the plaintiff first argues on appeal that the defendant had a duty to supervise the construction project so that the plaintiff could complete its work by July 31, 1990. While acknowledging that the written contract between the parties did not provide for a set completion date, the plaintiff argues that the written contract contemplated an “oral understanding” that the work would be completed by that date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National City Mortg. v. Hillside Lumber
966 N.E.2d 1076 (Appellate Court of Illinois, 2012)
National City Mortgage v. Hillside Lumber
2012 IL App (2d) 101292 (Appellate Court of Illinois, 2012)
IFC Credit Corp. v. Burton Industries, Inc.
536 F.3d 610 (Seventh Circuit, 2008)
Cordeck Sales v. Construction Systems
Appellate Court of Illinois, 2008
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Hessler v. Crystal Lake Chrysler-Plymouth, Inc.
Appellate Court of Illinois, 2003
Krautsack v. Anderson
768 N.E.2d 133 (Appellate Court of Illinois, 2002)
Prentice v. UDC Advisory Services, Inc.
648 N.E.2d 146 (Appellate Court of Illinois, 1995)
J&B Steel Contractors, Inc. v. C. Iber & Sons, Inc.
642 N.E.2d 1215 (Illinois Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
617 N.E.2d 405, 246 Ill. App. 3d 523, 187 Ill. Dec. 197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-b-steel-contractors-inc-v-c-iber-sons-inc-illappct-1993.