S.J. Groves & Sons Co. v. Midwest Steel Erection Co.

666 F. Supp. 129, 1986 U.S. Dist. LEXIS 16191
CourtDistrict Court, N.D. Illinois
DecidedDecember 19, 1986
Docket86 C 5982
StatusPublished
Cited by5 cases

This text of 666 F. Supp. 129 (S.J. Groves & Sons Co. v. Midwest Steel Erection Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.J. Groves & Sons Co. v. Midwest Steel Erection Co., 666 F. Supp. 129, 1986 U.S. Dist. LEXIS 16191 (N.D. Ill. 1986).

Opinion

MEMORANDUM OPINION AND ORDER

ROVNER, District Judge.

Plaintiff, SJ. Groves & Sons Company (“Groves”), filed this diversity action against Midwest Steel Erection Company, Inc. (“Midwest”) and Reliance Insurance Company (“Reliance”). Groves entered into a contract with the Illinois Department of Transportation (“IDOT”) for the construction of road and bridge improvements in Lasalle, Illinois (“the Lasalle Bridge Project”). Groves entered into a subcontract with Midwest for work on that project. Groves alleges that Midwest breached the subcontract and that Reliance breached its obligations under a performance bond obtained by Midwest for the benefit of Groves. Midwest filed a counterclaim, alleging breach of contract by Groves and establishing a lien, pursuant to Ill.Rev.Stat. ch. 82, 1123, on funds due Groves from IDOT.

Presently before the Court is Grove’s motion for partial summary judgment on Count I of the counterclaim, which constitutes the lien action. For the reasons noted below, that motion is granted and Count I of the counterclaim is dismissed with prejudice.

*130 I

Grove’s motion is premised upon paragraph 29 of the contract between Groves and Midwest, which states:

The Subcontractor agrees that it shall not at any time file any lien, or stop notice to a government agency, or notice of claim to a lien of any kind or nature whatsoever, nor permit the same to be filed for work performed or materials furnished pursuant to the terms of this Agreement or any modification hereof, or for any extra work performed or materials furnished or for any other reason or upon any ground whatsoever; and, Subcontractor does hereby waive and relinquish the right to any and all liens, stop notices, or claim of lines [sic] as may be permitted or provided for by any provisions of law.

Midwest argues, on several grounds, that this waiver provision should not prevent Midwest from pursuing its lien action. First, Midwest contends that, pursuant to public policy, the waiver provision is unenforceable under Illinois law. Midwest’s sole authority for this proposition is Central Lime & Cement Company v. Leyden-Ortseifen Company, 245 Ill.App. 48 (1st Dist.1927).

In Central Lime, the plaintiff, Central Lime, was a subcontractor of the defendant, Leyden-Ortseifen. The defendant, in turn, was the general contractor on a project for the Sanitary District of Chicago. At trial, the court found that Leyden-Ort-seifen and 12 subcontractors, including Central Lime, were owed various amounts by the Sanitary District. On appeal, the Sanitary District argued that a lien waiver found in the contract between the general contractor, Leyden-Ortseifen, and the Sanitary District precluded the subcontractors from attaching any liens. The Sanitary District cited Ill.Rev.Stat. ch. 82, ¶ 21, which, both at the time of the Central IAme decision and at present, allows a lien waiver executed by a general contractor to bind subcontractors if certain conditions are met.

The appellate court found paragraph 21 was not applicable, noting that the section applied to private construction contracts. Instead, it found the case to be brought under Ill.Rev.Stat. ch. 82, 1123, the lien provision for public construction contracts also at issue in the case at bar. In its analysis of the effect of the lien waiver, the Central Lime court began by noting that the waiver was found in the contract between the Sanitary District and the general contractor. The Court then noted that, unlike paragraph 21, paragraph 23 provides liens only for subcontractors, not general contractors. The Court also noted that, again unlike paragraph 21, paragraph 23 provides for a lien only on funds due from the governmental entity to the general contractor — no party, whether a general contractor or a subcontractor, may have a lien on the public improvement itself. Thus, there is no need for paragraph 23 to provide a lien in favor of a general contractor, for “it would be absurd to provide by law for a lien in favor of the contractor upon moneys to which he becomes entitled under his contract.” Id. at 53.

Based on this analysis, the Central Lime court found that the lien waiver executed by Leyden-Ortseifen was “in fact ineffectual.” Id. The basis for this conclusion was that, as the Central Lime court noted, Leyden-Ortseifen had no lien to begin with. It could not levy a lien against the public improvement and had no rights under paragraph 23 which it could waive because that section runs only in favor of subcontractors whose rights against the public beneficiary, unlike those of general contractors such as Leyden-Ortseifen, were not already protected by contract. Thus, the Central Lime court's implicit holding was that the lien waiver was a nullity that did not bind Ley-den-Ortseifen or the subcontractors. This conclusion would also draw support from the fact that, as noted previously, although paragraph 21 contains language which permits subcontractors to be bound by waivers executed by general contractors, paragraph 23 does not.

Thus, Central Lime provides no guidance concerning the ability of a party whose interests paragraph 23 is designed to protect — a subcontractor — to waive that *131 protection. In the absence of definitive Illinois case law construing waivers of liens under paragraph 23, the Court will look to Illinois case law construing waivers by subcontractors of other Mechanics’ Lien Act provisions. Illinois courts have repeatedly upheld waivers of mechanics’ liens by subcontractors. See, e.g., Faerber Electrical Company v. International Telephone and Telegraph Corp., 123 Ill.App.3d 704, 79 Ill.Dec. 266, 269-70, 463 N.E.2d 820, 823-24 (1st Dist.1984); Country Service & Supply Company v. Harris Trust & Savings Bank, 103 Ill.App.3d 161, 58 Ill.Dec. 599, 602-03, 430 N.E.2d 631, 634-35 (2d Dist.1981), William Aupperle & Sons, Inc. v. American National Bank & Trust Company of Chicago, 28 Ill.App.3d 573, 329 N.E.2d 458, 461-62 (3rd Dist.1975). Midwest has failed to convince this Court that public policy requires a different result when the underlying project happens to be a public project. The mechanics’ lien provisions concerning subcontractors, whether for private or public projects, are designed to ensure that subcontractors will have some recourse against the ultimate beneficiary of the subcontractors’ labors — the project owner — if the general contractor fails to meet its obligations to the subcontractor. The fact that the Illinois legislature’s understandable refusal to allow liens directly against public property necessitated paragraph 23’s specific procedures does not differentiate the protective intent behind paragraph 23 from the intent behind the provisions protecting subcontractors in private projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petroline Co. v. Advanced Environmental Contractors, Inc.
711 N.E.2d 1146 (Appellate Court of Illinois, 1999)
R.W. Dunteman Co. v. C/G Enterprises Inc.
692 N.E.2d 306 (Illinois Supreme Court, 1998)
Ramco Industries, Inc. v. BD. OF TRUSTEES, UNIV. OF ILL.
589 N.E.2d 672 (Appellate Court of Illinois, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
666 F. Supp. 129, 1986 U.S. Dist. LEXIS 16191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sj-groves-sons-co-v-midwest-steel-erection-co-ilnd-1986.