Matteo Construction Co. v. Teckler Blvd Development Site, LLC

2020 IL App (2d) 190766
Appellate Court of Illinois·Decided August 4, 2020·No. 2-19-0766·Published·Cited by 1 cases

Opinion

No. 2-19-0766

Opinion filed August 4, 2020

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT

MATTEO CONSTRUCTION COMPANY, ) Appeal from the Circuit Court ) of McHenry County.

Plaintiff-Appellant, )

)

)

v. ) No. 17-CH-433 )

TECKLER BLVD DEVELOPMENT SITE, ) LLC; FIRST BANK; KING KONCRETE, ) INC.; GESKE AND SONS, INC.; IRISH ) TONY II, INC.; STORAGE STRUCTURES, ) INC.; HELSONS GARAGE DOORS; AURIS ) CONSTRUCTION AND DEVELOPMENT, ) INC.; HAMBY BLAST AND SEAL, INC.; ) JANUS INTERNATIONAL GROUP, LLC; ) ANCHOR PLUMBING, INC.; AIR BLUE ) HEATING AND COOLING, INC.; ALARM ) SPECIALTIES AND PROTECTION, INC.; ) 3 DIMENSION CONSTRUCTION ) MANAGEMENT, INC.; UNKNOWN ) OWNERS and NONRECORD CLAIMANTS, )

)

Defendants )

) Honorable,

(Teckler Blvd Development Site, LLC, ) Michael J. Chmiel Defendant-Appellee). ) Judge, Presiding.

JUSTICE BRENNAN delivered the judgment of the court, with opinion.

Justices Jorgensen and Bridges concurred in the judgment and opinion.

OPINION

¶1 Plaintiff, Matteo Construction Company, appeals the trial court’s dismissal of its complaint seeking to foreclose a subcontractor’s lien under section 28 of the Mechanics Lien Act (Act) (770 ILCS 60/28 (West 2014)) against defendant, Teckler Blvd Development Site, LLC (Teckler), the owner of the property. The trial court found that plaintiff did not properly perfect its lien because it failed to wait 10 days after giving Teckler notice before recording it. We reverse and remand for further proceedings.

¶2 I. BACKGROUND

¶3 On February 23, 2016, plaintiff sent a copy of its claim of lien to Teckler’s owner by certified mail. The claim provided the (1) parties’ names, (2) property description, (3) work performed, and (4) amount due. The lien was for excavation and grading services that plaintiff, pursuant a November 2014 contract, provided in the construction of a self-storage facility owned by Teckler. Plaintiff recorded its claim of lien on February 25, 2016. Teckler received the mailed notice of claim the next day, on February 26, 2016.

¶4 On June 1, 2017, plaintiff filed its complaint to foreclose its lien. Plaintiff’s operative complaint included three counts: count I was brought against all defendants—including the general contractor, 3 Dimension Construction Management, Inc. (3DCM)—to foreclose the lien; count II alleged breach of contract against 3DCM; and count III was brought against Teckler, alleging quantum meruit. Plaintiff alleged that (1) all work was substantially complete on December 19, 2015; (2) as of February 25, 2016, 3DCM was wrongfully withholding a balance due on the contract; and (3) it was entitled to a lien on the premises.

¶5 Teckler moved to dismiss plaintiff’s complaint. First, Teckler claimed that plaintiff failed to perfect its lien under the Act by failing to wait 10 days from the date of notice to Teckler to record the claim of lien. Second, Teckler argued that a subcontractor has no cause of action based

on quantum meruit against the property owner. Plaintiff responded that it complied with the Act but conceded that it could not recover on a theory of quantum meruit.

¶6 On May 15, 2019, the trial court granted the motion to dismiss count I, finding that, under the plain language of the Act, plaintiff was required to wait 10 days from the date of notice to Teckler before recording the claim of lien. Because plaintiff did not do so, the lien was not properly perfected. The court also dismissed count III (quantum meruit).

¶7 Plaintiff’s motion to reconsider was denied. Plaintiff voluntarily dismissed count II against 3DCM and now appeals.

¶8 II. ANALYSIS

¶9 A. Timing of Recording of the Lien

¶ 10 Plaintiff contends that the trial court erred in determining that the plain language of the Act required, for perfection of plaintiff’s lien, that plaintiff wait 10 days after sending notice of its claim of lien before recording the claim. Teckler defends the trial court’s interpretation, arguing that the lien was improperly perfected, because it was prematurely recorded. The matter is one of statutory construction. We review de novo matters of statutory construction. People ex rel. Madigan v. Kinzer, 232 Ill. 2d 179, 184 (2009).

¶ 11 As it applies to subcontractors, section 24 of the Act requires any person furnishing labor or materials to give written notice of that person’s claim to the owner within 90 days of the final delivery of the material or labor. 770 ILCS 60/24(a) (West 2014). Service of such written notice is a condition precedent to obtaining and perfecting a mechanic’s lien claim. See Suddarth v. Rosen, 81 Ill. App. 2d 136, 139 (1967).

¶ 12 The parties’ dispute concerns the timing requirements found in section 28 of the Act for enforcement of a lien after notice is given. That section is specific to subcontractors and provides:

“If any money due to the laborers, materialmen, or sub-contractors be not paid within 10 days after his notice is served as provided in sections 5, 24, and 25, then such person may file a claim for lien or file a complaint and enforce such lien within the same limits as to time and in such other manner as hereinbefore provided for the contractor in section 7 and sections 9 to 20 inclusive, of this Act, or he may sue the owner and contractor jointly for the amount due in the circuit court, and a personal judgment may be rendered therein, as in other cases.” (Emphasis added.) 1 770 ILCS 60/28 (West 2014).

¶ 13 Section 7, which is generally applicable to contactors, provides:

“No contractor shall be allowed to enforce such lien against or to the prejudice of any other creditor or incumbrancer or purchaser, unless within 4 months after completion, *** he or she shall either bring an action to enforce his or her lien therefor or shall file in the office of the recorder of the county in which the building, erection or other improvement to be charged with the lien is situated, a claim for lien, verified by the affidavit of himself or herself, or his or her agent or employee, which shall consist of a brief statement of the claimant’s contract, the balance due after allowing all credits, and a sufficiently correct description of the lot, lots or tracts of land to identify the same. Such claim for lien may be filed at any time after the claimant’s contract is made, and as to the owner may be filed at any time after the contract is made and within 2 years after the completion of the contract,

1 Plaintiff did not seek a personal judgment against Teckler’s owners. It did request, in the

alternative, a personal judgment against the owners of 3DCM should foreclosure of the lien be insufficient to pay the balance due.

*** and as to such owner may be amended at any time before the final judgment.”

(Emphasis added.) Id. § 7(a).

¶ 14 Section 9 provides that a contractor holding a lien may bring suit to enforce the lien if payment is not complete when payment becomes due. Id. § 9. Such suit shall be commenced within two years after contract completion. Id.

¶ 15 “The purpose of the Mechanics Lien Act is to protect those who in good faith furnish labor or materials for construction of buildings or public improvements.” Premier Electrical Construction Co. v. American National Bank of Chicago, 276 Ill. App. 3d 816, 821 (1995). The Act balances the owner’s benefit of its bargain with the subcontractor’s right to be paid for labor and materials that he or she furnishes in good faith. Id. “The Act’s technical and procedural requirements must be strictly construed because mechanic’s liens are a statutory creation. Id. at 821-22. “Once the statutory requirements are met, however, the Act should be liberally construed to carry out its remedial purpose.” Id. at 822.

Free access — add to your briefcase to read the full text and ask questions with AI

Matteo Construction Co. v. Teckler Blvd Development Site, LLC, 2020 IL App (2d) 190766 (Ill. Ct. App. 2020).

2020 IL App (2d) 190766 (Matteo Construction Co. v. Teckler Blvd Development Site, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Matteo Construction Co. v. Teckler Blvd Development Site, LLC
2020 IL App (2d) 190766 (Appellate Court of Illinois, 2020)