Matteo Construction Co. v. Teckler Blvd Development Site, LLC

2020 IL App (2d) 190766
Appellate Court of Illinois·Decided August 4, 2020·No. 2-19-0766·Published·Cited by 1 cases

Opinion

2020 IL App (2d) 190766 No. 2-19-0766 Opinion filed August 4, 2020 ______________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT ______________________________________________________________________________

MATTEO CONSTRUCTION COMPANY, ) Appeal from the Circuit Court ) of McHenry County. Plaintiff-Appellant, ) ) ) v. ) No. 17-CH-433 ) TECKLER BLVD DEVELOPMENT SITE, ) LLC; FIRST BANK; KING KONCRETE, ) INC.; GESKE AND SONS, INC.; IRISH ) TONY II, INC.; STORAGE STRUCTURES, ) INC.; HELSONS GARAGE DOORS; AURIS ) CONSTRUCTION AND DEVELOPMENT, ) INC.; HAMBY BLAST AND SEAL, INC.; ) JANUS INTERNATIONAL GROUP, LLC; ) ANCHOR PLUMBING, INC.; AIR BLUE ) HEATING AND COOLING, INC.; ALARM ) SPECIALTIES AND PROTECTION, INC.; ) 3 DIMENSION CONSTRUCTION ) MANAGEMENT, INC.; UNKNOWN ) OWNERS and NONRECORD CLAIMANTS, ) ) Defendants ) ) Honorable, (Teckler Blvd Development Site, LLC, ) Michael J. Chmiel Defendant-Appellee). ) Judge, Presiding. ______________________________________________________________________________

JUSTICE BRENNAN delivered the judgment of the court, with opinion. Justices Jorgensen and Bridges concurred in the judgment and opinion.

OPINION 2020 IL App (2d) 190766

¶1 Plaintiff, Matteo Construction Company, appeals the trial court’s dismissal of its complaint

seeking to foreclose a subcontractor’s lien under section 28 of the Mechanics Lien Act (Act) (770

ILCS 60/28 (West 2014)) against defendant, Teckler Blvd Development Site, LLC (Teckler), the

owner of the property. The trial court found that plaintiff did not properly perfect its lien because

it failed to wait 10 days after giving Teckler notice before recording it. We reverse and remand for

further proceedings.

¶2 I. BACKGROUND

¶3 On February 23, 2016, plaintiff sent a copy of its claim of lien to Teckler’s owner by

certified mail. The claim provided the (1) parties’ names, (2) property description, (3) work

performed, and (4) amount due. The lien was for excavation and grading services that plaintiff,

pursuant a November 2014 contract, provided in the construction of a self-storage facility owned

by Teckler. Plaintiff recorded its claim of lien on February 25, 2016. Teckler received the mailed

notice of claim the next day, on February 26, 2016.

¶4 On June 1, 2017, plaintiff filed its complaint to foreclose its lien. Plaintiff’s operative

complaint included three counts: count I was brought against all defendants—including the general

contractor, 3 Dimension Construction Management, Inc. (3DCM)—to foreclose the lien; count II

alleged breach of contract against 3DCM; and count III was brought against Teckler, alleging

quantum meruit. Plaintiff alleged that (1) all work was substantially complete on December 19,

2015; (2) as of February 25, 2016, 3DCM was wrongfully withholding a balance due on the

contract; and (3) it was entitled to a lien on the premises.

¶5 Teckler moved to dismiss plaintiff’s complaint. First, Teckler claimed that plaintiff failed

to perfect its lien under the Act by failing to wait 10 days from the date of notice to Teckler to

record the claim of lien. Second, Teckler argued that a subcontractor has no cause of action based

-2- 2020 IL App (2d) 190766

on quantum meruit against the property owner. Plaintiff responded that it complied with the Act

but conceded that it could not recover on a theory of quantum meruit.

¶6 On May 15, 2019, the trial court granted the motion to dismiss count I, finding that, under

the plain language of the Act, plaintiff was required to wait 10 days from the date of notice to

Teckler before recording the claim of lien. Because plaintiff did not do so, the lien was not properly

perfected. The court also dismissed count III (quantum meruit).

¶7 Plaintiff’s motion to reconsider was denied. Plaintiff voluntarily dismissed count II against

3DCM and now appeals.

¶8 II. ANALYSIS

¶9 A. Timing of Recording of the Lien

¶ 10 Plaintiff contends that the trial court erred in determining that the plain language of the Act

required, for perfection of plaintiff’s lien, that plaintiff wait 10 days after sending notice of its

claim of lien before recording the claim. Teckler defends the trial court’s interpretation, arguing

that the lien was improperly perfected, because it was prematurely recorded. The matter is one of

statutory construction. We review de novo matters of statutory construction. People ex rel.

Madigan v. Kinzer, 232 Ill. 2d 179, 184 (2009).

¶ 11 As it applies to subcontractors, section 24 of the Act requires any person furnishing labor

or materials to give written notice of that person’s claim to the owner within 90 days of the final

delivery of the material or labor. 770 ILCS 60/24(a) (West 2014). Service of such written notice

is a condition precedent to obtaining and perfecting a mechanic’s lien claim. See Suddarth v.

Rosen, 81 Ill. App. 2d 136, 139 (1967).

¶ 12 The parties’ dispute concerns the timing requirements found in section 28 of the Act for

enforcement of a lien after notice is given. That section is specific to subcontractors and provides:

-3- 2020 IL App (2d) 190766

“If any money due to the laborers, materialmen, or sub-contractors be not paid within 10

days after his notice is served as provided in sections 5, 24, and 25, then such person may

file a claim for lien or file a complaint and enforce such lien within the same limits as to

time and in such other manner as hereinbefore provided for the contractor in section 7 and

sections 9 to 20 inclusive, of this Act, or he may sue the owner and contractor jointly for

the amount due in the circuit court, and a personal judgment may be rendered therein, as

in other cases.” (Emphasis added.) 1 770 ILCS 60/28 (West 2014).

¶ 13 Section 7, which is generally applicable to contactors, provides:

“No contractor shall be allowed to enforce such lien against or to the prejudice of any other

creditor or incumbrancer or purchaser, unless within 4 months after completion, *** he or

she shall either bring an action to enforce his or her lien therefor or shall file in the office

of the recorder of the county in which the building, erection or other improvement to be

charged with the lien is situated, a claim for lien, verified by the affidavit of himself or

herself, or his or her agent or employee, which shall consist of a brief statement of the

claimant’s contract, the balance due after allowing all credits, and a sufficiently correct

description of the lot, lots or tracts of land to identify the same. Such claim for lien may be

filed at any time after the claimant’s contract is made, and as to the owner may be filed at

any time after the contract is made and within 2 years after the completion of the contract,

1 Plaintiff did not seek a personal judgment against Teckler’s owners. It did request, in the

alternative, a personal judgment against the owners of 3DCM should foreclosure of the lien be

insufficient to pay the balance due.

-4- 2020 IL App (2d) 190766

*** and as to such owner may be amended at any time before the final judgment.”

(Emphasis added.) Id. § 7(a).

¶ 14 Section 9 provides that a contractor holding a lien may bring suit to enforce the lien if

payment is not complete when payment becomes due. Id. § 9. Such suit shall be commenced within

Free access — add to your briefcase to read the full text and ask questions with AI

Matteo Construction Co. v. Teckler Blvd Development Site, LLC, 2020 IL App (2d) 190766 (Ill. Ct. App. 2020).

2020 IL App (2d) 190766 (Matteo Construction Co. v. Teckler Blvd Development Site, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Matteo Construction Co. v. Teckler Blvd Development Site, LLC
2020 IL App (2d) 190766 (Appellate Court of Illinois, 2020)