Standard Oil Co. v. Kapschull, Davis Co.

276 Ill. App. 281, 1934 Ill. App. LEXIS 274
CourtAppellate Court of Illinois
DecidedMarch 12, 1934
DocketGen. No. 8,496
StatusPublished
Cited by1 cases

This text of 276 Ill. App. 281 (Standard Oil Co. v. Kapschull, Davis Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Oil Co. v. Kapschull, Davis Co., 276 Ill. App. 281, 1934 Ill. App. LEXIS 274 (Ill. Ct. App. 1934).

Opinion

Mr. Justice Dove

delivered the opinion of the court.

This cause comes to this court upon an appeal from a decree of the circuit court of Will county, awarding appellee a lien in the amount of $1,706.96 upon moneys due from the State of Illinois upon a contract for the construction of section 145 of State Highway Route 176 in Lake and McHenry counties.

Upon the hearing, the parties stipulated that on October 22, 1928, Kapschull, Davis Company entered into a contract with the State of Illinois to construct said section for a consideration of $162,672.91, and at that time Kapschull, Davis Company, with the Columbia Casualty Company, appellant, as surety, gave a bond to the State for the contract price of said improvement ; that on October 30,1928, Kapschull, Davis Company commenced work under said contract and completed it on or about October 30, 1929; that on July 1, 1929, the contractor, Kapschull, Davis Company, entered into an oral contract with Edward J. Peacock, doing business under the name of Peacock Cartage Company, to haul mixed batches of concrete and various other materials from certain points to the place of construction, Peacock to receive therefor a stated price per batch or load; that on August 1, 1929, Peacock entered into a verbal contract with appellee, whereby appellee agreed to furnish to Peacock such quantities of grease, oil and gasoline as Peacock might require in the operation of his trucks and that these commodities were so furnished and that $1,541.57, together with interest thereon, remains due and unpaid appellee therefor. It was further stipulated that proper statutory claims were duly filed by appellee and the only questions presented for determination upon this record are first: whether appellee is entitled to a lien under section 23 of the Liens Act,. Cahill’s St. ch. 82, H 23, upon, the money' due under the contract which was originally entered into by the State of Illinois and Kapschull, Davis Company; second: whether the amount due appellee bears interest; and third: whether appellant, the Columbia Casualty Company, is liable on its bond in this proceeding.

First: Section 23 of chapter 82, Cahill’s Illinois Revised Statutes, If 23, in force at the time of these transactions, provided, among other things, that any person who shall furnish material, apparatus, fixtures, machinery or labor to any contractor having a contract for public improvement for the State, may have a lien on the money, bonds or warrants due or about to become due such contractor under the contract.

Appellant contends that the statute expressly restricts the right to a lien to persons furnishing material directly to the principal contractor and does not include appellee who furnished materials to a subcontractor. On the other hand, it is the contention of appellee that the provisions of the statute are broad enough to include one who furnished lienable materials indirectly to the original contractor by furnishing the same to a subcontractor.

In Alexander Lumber Co. v. Coberg, 356 Ill. 49, our Supreme Court had under consideration the construction of the first paragraph of this same section 23 which provides that any person who shall furnish material, apparatus, fixtures, machinery or labor to any contractor having a contract for public improvement for any county, township, school district, city or municipality in this State shall have a lien on the money, bonds or warrants due or to become due such contractor under such contract. In that case it appeared that contracts for the construction and erection of two school buildings had been entered into by and between the Board of Education of School District No. 46 in Du Page county and John C. Goberg. Subsequently Co-berg sublet a portion thereof to one McDonald and he in turn contracted with the lumber company for certain materials which went into the construction of the buildings and the lumber company sought to enforce a lien for the balance due on its contract. In sustaining the decree of the circuit court, which denied a lien to the lumber company, the Supreme Court said: “By reference to the relevant part of section 23, we find that the legislature has specifically mentioned only three parties: First, the municipality; second, the contractor; and third, the ‘person who shall furnish material, apparatus, fixtures, machinery or labor to any contractor having a contract for public improvement,’ etc. Nowhere does a pertinent part of the section contain any language including material-men, such as were the appellees here, who furnished materials to a subcontractor. The language used by the legislature is plain, specific, and not all-inclusive. Under the authorities cited, and the well known rule that the expression of one thing is the exclusion of all others, this court has no right to read into this section words not found therein.”

In the instant case .the pertinent provisions of section 23 are identical with those provisions of the same section which the court construed in the Alexander Lumber Co. case, supra, and while it is true that appellee furnished lienable materials to Peacock, a subcontractor, with the knowledge and consent of the original contractor and notwithstanding these materials were used and consumed in the making of a public improvement and helped bring it to a satisfactory completion, still the statute says that in order to have a lien therefor, such materials must be furnished to the contractor. Appellee was not, therefore, entitled to a lien and the chancellor erred in not so holding.

The second and third questions may be considered together. The decree of the lower court found that the contractor had assigned to the casualty company all moneys due it from the State under its contract and provided that in the event the sum found due complainant, which included $165.39 interest, was not paid within 30 days, then the Director of the Department of Public Works and Buildings shall pay the same, provided there is a sufficient amount available therefor and that if the money in the hands of the Director of the Department of Public Works and Buildings is insufficient to pay the amount found due complainant, “that the complainant report and make proof to this court the amount of such deficiency, and on the coming in and confirmation of this report, the court shall thereupon adjudge the amount decreed to be paid by the said Kapsehull, Davis Company, Inc. and said Columbia Casualty Company, the court hereby ordering, adjudging and decreeing that the terms of said bond of the said Kapsehull, Davis Company, Inc., and said Columbia Casualty Company include the payment of the lien hereby established, . . . that the complainant report to this court as soon as practicable, the amount of such deficiencies, if any, and the court hereby retains jurisdiction of this cause for the purpose of ascertaining such deficiencies if any, and entering such orders or decrees relative thereto as equity may require. ’ ’

The surety bond was in the sum of $162,672.91, and recited the award of the contract to Kapsehull, Davis Company, Inc., and the execution by it of a written contract with the State of Illinois, acting through the Department of Public Works. The condition of the bond was that the contractor shall hold the People of the State of Illinois and the Department of Public Works and Buildings harmless and shall perform the work according to the terms of the contract and should pay all sums of money due for any labor, material, apparatus, fixtures or machinery furnished to them for the purpose of such construction or improvement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wise v. Jerome
125 N.E.2d 292 (Appellate Court of Illinois, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
276 Ill. App. 281, 1934 Ill. App. LEXIS 274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-oil-co-v-kapschull-davis-co-illappct-1934.