This text of 66 N.E. 37 (West Chicago Park Commissioners v. Western Granite Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Chicago Park Commissioners v. Western Granite Co., 66 N.E. 37, 200 Ill. 527 (Ill. 1902).

Opinions

Mr. Justice Cartwright

delivered the opinion of the court:

On October 4, 1898, appellant entered into a contract in writing with John Sargent, by which he was to furnish material and construct sidewalks along certain streets under control of appellant. Appellee agreed to furnish Sargent with the crushed granite for such sidewalks at a price agreed upon between them. Sargent constructed the sidewalks and appellee furnished him the crushed granite, and on June 21, 1899, there was due appellee from Sargent, under said contract, §1070.10. On June 23, 1899, appellee gave a written notice to appellant, claiming a lien to the extent of said sum upon the money, bonds or warrants due or to become due to Sargent under his contract, and notifying appellant to withhold all payments from Sargent or his assigns under the contract for the improvement until said sum should be paid to appellee. This notice was served on the secretary of appellant, and at a meeting of its officers held on said June 23, 1899, the notice was brought before the board, when a statement of it was spread upon the records and the notice ordered to be placed on file. The bill in this case was filed by appellee in the circuit court of Cook county on June 26, 1899, against appellant and Sargent, to enforce a lien upon the money, bonds and warrants due or to become due to Sargent. Appellant was served with summons June 26, 1899, and appeared in the action. Appellant and Sargent filed joint and several demurrers to the bill, which were overruled, and afterwards they filed separate answers. On October 14, 1899, a final estimate under the contract was made, by which it was certified that there was due Sarg-ent from the appellant §2630.70. Appellant disregarded the claim of lien by the notice and bill, and on November 10, 1899, issued warrants to its treasurer payable to the order of Sargent for the balance due him, including the money on which appellee had a lien, and they were paid. On May 24, 1902, appellant, h;?- leave of court, amended its answer, setting up the fact that there had become due from appellant to Sargent said sum of §2630.70, which had been paid to Sargent. The cause had been referred to a master in chancery, who reported the evidence, with his finding that there was due appellee §1070.10, with interest thereon from June 10, 1899, and that appellee was entitled to a decree for that amount, together with a solicitor’s fee, amounting to §107. During the pendency of the suit Sargent was discharged in bankruptcy. The cause was heard on exceptions to the master’s report, and they were overruled and a decree was entered in accordance with the report. Prom that decree this appeal was taken directly to this court.

The ground of direct appeal to this court from the circuit court is, that section 24 of the act to revise the law in relation to mechanics’ liens, in force June 26, 1895, is unconstitutional and void, for the reason that it gives to those furnishing material or labor to contractors with municipal corporations, rights and remedies not given to other citizens of the State.

Section 24 is as follows: “Any person who shall furnish material, apparatus, fixtures, machinery or labor to any contractor for a public improvement in this State, shall have a lien on the money, bonds or warrants due or to become due such contractor for such improvement: Provided, such person shall, before any payment or delivery thereof is made to such contractor, notify the officials of this State, county, township, city or municipality whose duty it is to pay such contractor, of his claim by a written notice and the full particulars thereof. It shall be the duty of such officials so notified to withhold a sufficient amount to pay such claim until it is admitted, or by law established, and thereupon to pay the amount thereof to such person, and such payment shall be a credit on the contract price to be paid to such contractor. Any officer violating the duty hereby imposed upon him shall be liable on his official bond to the person serving such notice for the damages resulting from such violation, which may be recovered in an action at law in any court of competent jurisdiction. There shall be no preference between the persons serving such notice, but all shall be paid pro rata in proportion to the amount due under their respective contracts.” (2 Starr & Cur. Stat. 1896, p. 2572.)

This section of the statute was before us in Spalding Lumber Co. v. Brown, 171 Ill. 487, and Young v. Jones, 180 id. 216, and' was treated as a valid enactment, but its validity was not challenged in these cases and was not considered. It is not contended that the section is void simply because it extends to that class of persons who furnish material, apparatus, fixtures, machinery or labor for an improvement, since if that were the objection it would apply to all laws allowing mechanics’ liens, and it is not claimed that all such laws are void. The objection is, that the section makes an unwarranted distinction between persons in practically the same situation in giving a privilege to a sub-contractor which the contractor does not enjoy. It is said that there is no difference, except in name, between the situation of a person who has put his own labor and material into a public improvement under a contract directly with a municipality, and one who has put the same labor and material into a public improvement under a contract with the original contractor, and that the lien and the remedy should be equally available to both. The section gives no lien upon the improvement to any one, but only gives a lien to the sub-contractor as against the contractor. The lien is only on the money, bonds or warrants provided by the municipal corporation for the payment of the contractor. The parties are not in the same situation, and it would be absurd to provide by law for a lien in favor of the contractor upon money, bonds or warrants to which he has become entitled under his contract. He is entitled to such money, bonds or warrants, and not a mere lien on them. It is against the policy of the law that liens should be established against the property of municipal corporations created and exercising their functions for the public good, under the authority of the State, and the act does not purport to create such a lien. The objection to the section in question is without merit.

The next proposition is, that the only remedy of the sub-contractor is an action upon the official bonds of the officers for violation of duty in not withholding an amount sufficient to pay the sub-contractor. The section provides for such a remedy, but it is not a remedy for the enforcement of a lien. The provision for a lien on the money, bonds or warrants would be of no effect unless it could be enforced. There is no provision of the section for the enforcement of the lien by a proceeding in equity, and it is insisted that there is none in the entire act directly applicable to its enforcement. If that is so, a court of equity has jurisdiction to enforce 'the lien. The legislature, of course, intended that the benefits of the lien should be secured to the sub-contractor, and statutory liens are enforcible in equity unless the law has provided some other mode. (Cairo and Vincennes Railroad Co. v. Fackney, 78 Ill. 116; Knapp, Stout & Co. v. McCaffrey, 178 id. 107.) One of the ordinary remedies administered by courts of equity is the establishment and enforcement of liens, and this statute gives the sub-contractor a lien which equity will make effective by enforcing it. National Bank of LaCrosse v. Petterson, (ante, p. 215.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Concrete Structures v. Clark
2023 IL App (1st) 230015-U (Appellate Court of Illinois, 2023)
Northwest Water Commission v. Carlo v. Santucci, Inc.
516 N.E.2d 287 (Appellate Court of Illinois, 1987)
Wilbur Waggoner Equipment Rental & Excavating Co. v. Johnson
342 N.E.2d 266 (Appellate Court of Illinois, 1975)
WILBUR WAGGONER EQUIPMENT RENTAL v. Johnson
342 N.E.2d 266 (Appellate Court of Illinois, 1975)
Romain v. Fink
125 N.E.2d 298 (Appellate Court of Illinois, 1955)
Goldberg v. Minerva Automobiles, Inc.
278 Ill. App. 217 (Appellate Court of Illinois, 1934)
Smith v. Texas Co.
53 S.W.2d 774 (Texas Commission of Appeals, 1932)
County of Lake v. Southern Surety Co.
265 Ill. App. 286 (Appellate Court of Illinois, 1932)
New Erie Coal Co. v. H. McMullen & Sons
247 Ill. App. 515 (Appellate Court of Illinois, 1928)
Standard Oil Co. of Indiana v. Vanderboom
158 N.E. 151 (Illinois Supreme Court, 1927)
Central Lime & Cement Co. v. Leyden-Ortseifen Co.
245 Ill. App. 48 (Appellate Court of Illinois, 1927)
Municipal Engineering & Contracting Co. v. City of Farmer City
193 Ill. App. 457 (Appellate Court of Illinois, 1915)
Haynes & Lyons v. County of Coles
84 N.E. 747 (Illinois Supreme Court, 1908)
County of Coles v. Goehring
70 N.E. 610 (Illinois Supreme Court, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
66 N.E. 37, 200 Ill. 527, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-chicago-park-commissioners-v-western-granite-co-ill-1902.