Concrete Structures/Sachi, J.V. v. Clark/Bulley/OVC/Power

2024 IL App (1st) 240082, 251 N.E.3d 481
CourtAppellate Court of Illinois
DecidedSeptember 3, 2024
Docket1-24-0082
StatusPublished
Cited by1 cases

This text of 2024 IL App (1st) 240082 (Concrete Structures/Sachi, J.V. v. Clark/Bulley/OVC/Power) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concrete Structures/Sachi, J.V. v. Clark/Bulley/OVC/Power, 2024 IL App (1st) 240082, 251 N.E.3d 481 (Ill. Ct. App. 2024).

Opinion

2024 IL App (1st) 240082 SECOND DIVISION September 3, 2024 No. 1-24-0082 ________________________________________________________________________

IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________ CONCRETE STRUCTURES/SACHI, J.V.; CONCRETE ) Appeal from the Circuit Court STRUCTURES OF THE MIDWEST, INC.; and SACHI ) of Cook County. CONSTRUCTION, INC., ) ) Plaintiffs-Appellants, ) ) v. ) No. 2017 CH 13778 ) CLARK/BULLEY/OVC/POWER; PRAIRIE DISTRICT3 ) PARTNERS; THE METROPOLITAN PIER AND ) EXPOSITION AUTHORITY; CLARK ) CONSTRUCTION GROUP, LLC; BULLEY & ) Honorable ANDREWS; OLD VETERAN CONSTRUCTION, INC.; ) Anthony C. Kyriakopoulos, McKISSACK & McKISSACK MIDWEST, INC.; ) Judge Presiding. GOETTSCH PARTNERS, INC.; MOODY NOLAN, ) INC.; POWERS AND SONS CONSTRUCTION ) COMPANY, INC.; TRAVELERS CASUALTY AND ) SURETY COMPANY OF AMERICA; FEDERAL ) INSURANCE COMPANY; FIDELITY AND DEPOSIT ) COMPANY OF MARYLAND; ZURICH AMERICAN ) INSURANCE COMPANY; CONTINENTAL ) CASUALTY COMPANY, and UNKNOWN ) NECESSARY PARTIES, ) ) Defendants-Appellees. )

PRESIDING JUSTICE VAN TINE delivered the judgment of the court, with opinion. Justices Reyes and D.B. Walker concurred in the judgment and opinion. 1-24-0082

OPINION

¶1 This construction dispute arises from a general contractor’s failure to pay a subcontractor

for concrete work that the subcontractor performed during the construction of a large hotel

connected to Chicago’s McCormick Place convention center. The construction project was funded

by a local government entity existing under the laws of the state of Illinois. After the general

contractor ignored multiple requests for payment from the subcontractor, the subcontractor

recorded a public lien in the amount outstanding against the general contractor, local government

entity, and other parties and filed suit against them shortly thereafter. The circuit court ordered

arbitration. At arbitration, the panel awarded the subcontractor the amount outstanding on the

invoice along with other compensation and found that the subcontractor was the prevailing party.

The circuit court affirmed this award. Subsequently, the subcontractor requested the circuit court

to grant it prejudgment interest and attorney fees under section 23 of the Mechanics Lien Act (770

ILCS 60/23 (West 2022)). The circuit court denied this request, and we affirmed. Concrete

Structures/Sachi, J.V. v. Clark/Bulley/OVC/Power, 2023 IL App (1st) 230015-U, ¶ 22. The

subcontractor then sought prejudgment interest under section 2 of the Interest Act (815 ILCS 205/2

(West 2022)) and under section 2 of the Public Construction Bond Act (Bond Act) (30 ILCS 550/2

(West 2022)), as well as attorney fees under the language of the bond at issue. The circuit court

denied both, and the subcontractor appealed. For the following reasons, we affirm.

¶2 BACKGROUND

¶3 In January 2015, the Metropolitan Pier and Exposition Authority (MPEA), a local

government entity, contracted with Prairie District3 Partners (PD3) to design and build a 41-story

2 1-24-0082

hotel on land owned by MPEA. 1 PD3 hired Clark/Bulley/OVC/Power (CBOP) to act as the general

contractor for the project. PD3 also provided payment and performance bonds issued by several

insurance companies (hereinafter “sureties”). 2 The terms of the payment bond at issue in this case

provide, in relevant part, as follows:

“§ 7 When a Claimant has satisfied [certain procedures], the Surety shall promptly

and at the Surety’s expense take the following actions:

§ 7.1 Send an answer to the Claimant, with a copy to the Owner, within sixty (60)

days after receipt of the Claim, stating the amounts that are undisputed and the basis for

challenging any amounts that are disputed; and

§ 7.2 Pay or arrange for payment of any undisputed amounts.

§ 7.3 The Surety’s failure to discharge its obligations under Section 7.1 or Section

7.2 shall not be deemed to constitute a waiver of defenses the Surety or Contractor may

have or acquire as to a Claim, except as to undisputed amounts for which the Surety and

Claimant have reached agreement. If, however, the Surety fails to discharge its obligations

under Section 7.1 or Section 7.2, the Surety shall indemnify the Claimant for the reasonable

attorney’s fees the Claimant incurs thereafter to recover any sums found to be due and

owing to the Claimant.”

1 We take the majority of the background and procedural posture from our prior decision in Concrete Structures/Sachi, J.V., 2023 IL App (1st) 230015-U, as it provides context germane to this appeal. 2 “A payment bond generally provides that if the contractor does not pay its subcontractors and material suppliers, the surety will pay them.” Lake County Grading Co. v. Village of Antioch, 2014 IL 115805, ¶ 7 (citing Western Waterproofing Co. v. Springfield Housing Authority, 669 F. Supp. 901, 903 (C.D. Ill. 1987)). “In contrast, a ‘completion bond’ (also known as a ‘performance bond’) provides that if the contractor does not complete a project, the surety will pay for its completion.” Id.

3 1-24-0082

¶4 In June 2015, CBOP hired Concrete Structures/Sachi, J.V. (Concrete Structures) to perform

concrete work on the project, which it did perform. CBOP did not pay Concrete Structures for its

work. Concrete Structures filed a bond claim, and CBOP responded as follows:

“The information you have provided to date is not sufficient to establish liability under the

bond. Therefore, we must inform you that at this time we consider no portion of the amount

claimed to be undisputed. The basis for challenging the disputed amount is lack of

substantiation. Therefore, to facilitate our independent investigation of the claim, we

request that you fill out and return the enclosed claim form, attaching copies of all

documents requested in the claim form.”

¶5 After multiple unsuccessful payment demands, Concrete Structures served a mechanic’s

lien in the amount of $9,247,203 against the hotel project, MPEA, PD3, and CBOP, pursuant to

section 23 of the Mechanics Lien Act. On October 13, 2017, Concrete Structures filed a four-count

complaint against those parties and others. Count I requested an accounting under section 23 of

the Act; count II alleged a breach of contract claim against CBOP; count III asserted a bond claim

against Concrete Structures’ insurers; and count IV alleged an unjust enrichment claim against

MPEA, PD3, CBOP, and those parties’ joint venture partners. Under the arbitration clause in its

contract with Concrete Structures, CBOP moved to compel arbitration on counts II and IV. The

circuit court granted CBOP’s motion and stayed counts I and III pending arbitration.

¶6 The matter proceeded to arbitration before a three-member panel of the American

Arbitration Association. By that time, CBOP had paid the balance of what it owed Concrete

Structures down to $2,178,720. However, Concrete Structures requested more than $28 million in

damages, which included the outstanding balance, plus approximately $10 million in labor

productivity damages and increased subcontractor costs, among others. CBOP counterclaimed

4 1-24-0082

more than $3.5 million in damages due primarily to the extended duration of the concrete work.

On June 19, 2019, the arbitration panel issued Concrete Structures an interim award of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2024 IL App (1st) 240082, 251 N.E.3d 481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concrete-structuressachi-jv-v-clarkbulleyovcpower-illappct-2024.