Mormat Electrical & Construction Services, LLC v. Hunter Construction Services, Inc.

2019 IL App (5th) 170316, 126 N.E.3d 728, 430 Ill. Dec. 640
CourtAppellate Court of Illinois
DecidedApril 18, 2019
DocketNO. 5-17-0316
StatusUnpublished
Cited by1 cases

This text of 2019 IL App (5th) 170316 (Mormat Electrical & Construction Services, LLC v. Hunter Construction Services, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mormat Electrical & Construction Services, LLC v. Hunter Construction Services, Inc., 2019 IL App (5th) 170316, 126 N.E.3d 728, 430 Ill. Dec. 640 (Ill. Ct. App. 2019).

Opinion

JUSTICE CATES delivered the judgment of the court, with opinion.

*641 ¶ 1 Plaintiff, Mormat Electrical & Construction Services, LLC (Mormat), an Illinois limited liability company, brought suit against defendant, Hunter Construction Services, Inc. (Hunter), an Illinois corporation, for breach of an oral contract related to electrical services performed during the construction of a Buffalo Wild Wings restaurant in Dickinson, North Dakota. After a bench trial in the circuit court of St. Clair County on December 20, 2016, the trial court ruled in favor of Mormat and awarded Mormat the principal sum of $ 59,400 plus interest. Hunter appeals contending the court did not properly interpret the oral contract between Mormat and Hunter and erred in awarding Mormat $ 58,000 of the total sum due under the contract. Hunter also contends the court erred in disregarding a November 21, 2014, unconditional lien waiver and release. We affirm.

¶ 2 The evidence reveals that in July 2014, Hunter entered into a general contract to construct a Buffalo Wild Wings restaurant in Dickinson, North Dakota. Hunter, owned by Hunter Yung and his wife, had built 14 similar stand-alone Buffalo Wild Wings prior to the North Dakota project. After receiving a contract from the owner of the Buffalo Wild Wings project, *730 *642 Hunter advised the electrical subcontractor he originally had chosen that the project was ready to proceed. The subcontractor unfortunately backed out of the bid. At this point, Hunter reached out to Mormat, owned by Christopher Carney and his wife, Denise, to see if Mormat could perform the electrical work for the restaurant. Mormat had worked on other Buffalo Wild Wing projects and understood the general scope and labor requirements even though this particular project was a little larger than most. Mormat agreed, and Hunter entered into an oral subcontract with Mormat for the electrical work. The electrical budget, per the general contract for the electrical scope of work, was $ 135,000. Under the contract, Mormat was responsible for all the electrical labor and wiring over 120 volts, including the wiring and installation of all light fittings and fixtures as well as all equipment connections related to heating and cooling, kitchen appliances, and mechanical equipment. In order to timely perform, the expected scope of work necessitated a four to five man electrical crew.

¶ 3 Prior to entering into the oral contract, Mormat, a nonunion contractor, informed Hunter it could not acquire a North Dakota electrical permit because it did not employ an electrician capable of being licensed in North Dakota. Hunter and Mormat agreed that a local contractor would be needed to pull the necessary electrical permits, perform inspections, and be on site throughout the project. Integrity Electrical, owned by Brandon Dimmick, a licensed North Dakota electrician, was hired on a time and material basis to provide the electrical permit and supervision for the project to meet North Dakota code requirements. Integrity was paid directly by Hunter.

¶ 4 In early August 2014, the electrical work began on the restaurant. Both Mormat and Integrity had two electricians on site. After some issues arose on the job, however, Integrity pulled its permit. For an extended period of time, little electrical work was done. During this "shut down," Hunter directed Mormat to work at night or at times when inspectors were not present. Eventually Integrity came back to the job. By the end of the project, Integrity had submitted 10 invoices covering one to two employees for services between August 22 and December 8, 2014, totaling approximately $ 72,715. No back-charge was tendered to Mormat for Integrity's work.

¶ 5 By the time Integrity returned to the project, the job was significantly behind schedule. Mormat worked overtime in order to help get the project completed and performed substantial extra work beyond its original scope. Some of the items included extra labor and materials for installation of a fire alarm, trenching for electrical wire, carpentry work, and correcting others' work, in addition to extra costs incurred during the downtime when the permit was pulled, all of which increased Mormat's overhead. While Integrity performed some of Mormat's base contract work, the cost savings compared to Mormat's extra work was, according to Mormat, a wash. Mormat performed and completed its work on the project during the period of August 1, 2014, through December 8, 2014. Mormat submitted invoices to Hunter totaling $ 145,731.25 of which Hunter paid Mormat $ 77,000. Given that the contract price was $ 135,000, Mormat believed it was owed $ 58,000, even though the difference was in fact higher. Hunter did admit that Mormat was entitled to an additional $ 1400 for materials for a low voltage fire alarm, which is not a part of this appeal, but otherwise did not believe Mormat was entitled to any additional monies. Rather, Hunter claimed a right of setoff or credit for work performed *731 *643 within the scope of the subcontract by other electricians.

¶ 6 The trial court ultimately held that the electrical subcontract did not include the costs of Integrity's work, consequently the costs associated with Integrity were not chargeable against the $ 135,000 contract price and Mormat was not responsible for Integrity's expenses. The court therefore awarded Mormat $ 58,000 that was still due under the oral contract, plus interest.

¶ 7 Hunter argues on appeal that the trial court erred in interpreting the oral subcontract between Hunter and Mormat to exclude any labor and materials for electrical services provided by Integrity that were within the scope of the electrical subcontract. Hunter points out the court failed to assess whether Mormat fully performed under the contract and further failed to issue Hunter a credit for Mormat's partial performance. Additionally, Hunter contends the trial court failed to acknowledge the effect of the unconditional lien waiver, dated November 19, 2014, and signed by Mormat.

¶ 8 Generally the construction or interpretation of a contract is a matter to be determined by the trial court as a question of law with de novo review by this court. See Avery v. State Farm Mutual Automobile Insurance Co. , 216 Ill. 2d 100 , 129, 296 Ill.Dec. 448 , 835 N.E.2d 801 (2005). When an oral contract is involved, however, the standard of review is different because the trial court is required to observe the conduct and determine the credibility of the witnesses when making findings of fact about the existence and terms of an oral contract (see Emmenegger Construction Co. v. King

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mormat Electrical & Construction Services, LLC v. Hunter Construction Services, Inc.
2019 IL App (5th) 170316 (Appellate Court of Illinois, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2019 IL App (5th) 170316, 126 N.E.3d 728, 430 Ill. Dec. 640, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mormat-electrical-construction-services-llc-v-hunter-construction-illappct-2019.