Emmenegger Construction Co. v. King

431 N.E.2d 738, 103 Ill. App. 3d 423, 59 Ill. Dec. 237, 1982 Ill. App. LEXIS 1387
CourtAppellate Court of Illinois
DecidedJanuary 29, 1982
Docket80-603
StatusPublished
Cited by43 cases

This text of 431 N.E.2d 738 (Emmenegger Construction Co. v. King) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Emmenegger Construction Co. v. King, 431 N.E.2d 738, 103 Ill. App. 3d 423, 59 Ill. Dec. 237, 1982 Ill. App. LEXIS 1387 (Ill. Ct. App. 1982).

Opinion

PRESIDING JUSTICE KARNS

delivered the opinion of the court:

Emmark Collaborative, Inc., and Emmenegger Construction Company, Inc., instituted separate proceedings to foreclose mechanics’ liens in the Circuit Court of St. Clair County against the owners and lien claimants of a construction project known as the Oak Hill Racquet Club. Emmark claimed sums were due it for the design and construction of the improvements, and Emmenegger claimed money was due it as a subcontractor for concrete work, carpentry labor, common labor and landscaping as well as other work. Jerry Ames, d/b/a Jerry Ames Construction Company, a lien claimant, was named a defendant in both actions. Ames filed counterclaims against Emmenegger and Emmark seeking damages incurred as a result of a breach of an alleged oral contract in failing to pay for certain concrete work furnished by Ames. All other matters were disposed of, and Ames’ claims were tried before the court after the two actions were consolidated for trial. The court entered judgment against Emmenegger in the amount of $16,172.55 and in favor of Emmark. In addition, the court, finding the refusal to pay the claim to be unreasonable, awarded prejudgment interest to Ames at the statutory rate. (Ill. Rev. Stat. 1979, ch. 74, par. 2.) Only Emmenegger Construction appeals.

The following issues are raised on appeal: whether the finding of the trial court as to the existence of a contract between Ames and Emmenegger was against the manifest weight of the evidence; whether the job superintendent on the construction site had authority, actual or apparent, to bind Emmenegger to the alleged contract, and whether the trial court’s finding that the failure to pay the claim was unreasonable as to justify an award of prejudgment interest was against the manifest weight of the evidence.

A detailed recitation of the facts is necessary. In June of 1973, Frank King and John J. Vassen, co-trustees of Oak Hill Racquet Club Land Trust No. 1, contracted with Emmark Collaborative, Inc., for the design, construction and construction management of the Oak Hill project. Emmark then entered into a subcontract with Emmenegger Construction Company, Inc. Emmenegger was to do the concrete work on the project. At the time these contracts were entered into and at all other times relevant to this litigation, Russell Emmenegger was the sole shareholder in Emmark and the sole or majority shareholder in Emmenegger. During the same period, Leo Kuntz was either corporate secretary or president of Emmark, depending on whether we credit his testimony or his verification of the sworn complaint filed by Emmark, and also served as vice-president of Emmenegger.

As stated, Emmark was the construction manager for the Oak Hill project. Fred Alsbach was the job superintendent for the project and directed activities on the job site. There is some dispute as to Alsbach’s employer. Kuntz testified that Alsbach was an employee of Emmenegger, but that for the purposes of the project was working for Emmark. However, the record reveals that Alsbach was paid by Emmenegger.

Labor and contract problems arose for Emmenegger in late 1973. Pursuant to the suggestion of John Yock, a representative of Concrete, Inc., Ames approached Alsbach concerning the possibility of doing some of the concrete work. It is undisputed that Alsbach hired Ames to do this work. Ames testified that the agreement between himself and Alsbach called for the work to be performed in January and February of 1974. The exact dates Ames was to pour the concrete were unknown because this work depended on the progress of other subcontractors and was dictated somewhat by weather conditions. This agreement was never reduced to a writing.

There is some indication that Ames was not certain for whom he was working. He dealt exclusively with Alsbach and did not meet or talk to either Russell Emmenegger or Leo Kuntz. Ames testified that the trailer at the construction site had a large sign labeled “Emmenegger Construction Company” and that he assumed that he was working for Emmenegger.

Ames testified that, by the terms of the agreement with Alsbach, he was to present a bill for the work completed at the end of the month and that payment would be forthcoming sometime between the 10th and 20th day of the following month. It should be noted that Alsbach did not testify at the trial and there was no other evidence submitted with regard to the terms of the agreement.

Ames completed approximately one-half of the work during January and on January 31,1974, he presented a bill for $7,516.20 to Alsbach. The bill was presented on a work order form to “Emmenegger Const., Inc.” and was approved for payment by Leo Kuntz. The bill was approved on an Emmenegger Construction Company, Inc., purchase order form which was signed by Alsbach. This bill was never paid. Ames continued to work until he had completed performance on the contract. When he returned to the jobsite on approximately March 1,1974, to present his bill for the February work, he could not find Alsbach and noticed that the Emmenegger trailer was gone. The February bill was for $8,656.35.

Ames testified that after going to the jobsite on or about March 1, 1974, he called the office of Emmenegger Construction Company, Inc. and was referred to Leo Kuntz. When Ames inquired as to when he would be paid, Kuntz responded that he would be paid when the company received payment for work completed. It is unclear whether Kuntz was referring to monies owing to Emmenegger or Emmark.

Kuntz testified that Ames was a subcontractor of Emmark and not of Emmenegger. He stated that Emmenegger subcontracted to do the concrete work, and Ames subcontracted to do the flat work. Kuntz further stated that it was not uncommon to divide the concrete work in this manner. A thorough search of the record reveals that Ames was not listed as a subcontractor of Emmark on any of the numerous documents submitted. This includes documents dated January 31, 1974, and February 28,1974.

There is also a dispute as to when Emmark and Emmenegger terminated work on the job. Ames testified that he performed his work between January 22, 1974, and February 22, 1974. He stated that Alsbach was on the job throughout this period as was Emmenegger’s trailer. Ames further testified that there were many other tradespersons working throughout this period. Kuntz testified that Emmark pulled off the job on February 11,1974; although, in Emmark’s complaint to foreclose, verified by Kuntz, it was averred that Emmark performed work through February 28, 1974. In so stating, he places primary reliance on a daily log kept by Alsbach in which the last entry was made on that date. Kuntz further testified that he visited the jobsite after February 11, 1974, and saw tradespersons working. The construction trailer was removed from the jobsite on February 28, 1974. Kuntz testified that he informed all of the subcontractors by telephone, including Ames, that Emmark was pulling off the job. Kuntz was uncertain as to the date the calls were made. On March 21,1974, a form letter was sent to all the subcontractors, including Ames, that Emmark was terminating work. This letter is the only written acknowledgement of Ames’ claimed status as a subcontractor of Em-mark.

Emmenegger asserts that Ames failed to prove the existence of a contract between itself and Ames by a preponderance of the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Marriage of Dave
2023 IL App (5th) 220114-U (Appellate Court of Illinois, 2023)
Mormat Electrical & Construction Services, LLC v. Hunter Construction Services, Inc.
2019 IL App (5th) 170316 (Appellate Court of Illinois, 2019)
Curto v. Illini Manors, Inc.
940 N.E.2d 229 (Appellate Court of Illinois, 2010)
Opp, Shelley v. Wheaton Van Lines
231 F.3d 1060 (Seventh Circuit, 2000)
Presley v. P & S Grain Co., Inc.
683 N.E.2d 901 (Appellate Court of Illinois, 1997)
Presley v. P&S Grain Co.
Appellate Court of Illinois, 1997
H & H PRESS, INC. v. Axelrod
638 N.E.2d 333 (Appellate Court of Illinois, 1994)
Ratliff v. Safeway Insurance
628 N.E.2d 937 (Appellate Court of Illinois, 1993)
Consolidated Freightways Corp. of Delaware v. Peacock Engineering Co.
628 N.E.2d 300 (Appellate Court of Illinois, 1993)
Mulliken v. Lewis
615 N.E.2d 25 (Appellate Court of Illinois, 1993)
In Re Marriage of Mosher
612 N.E.2d 838 (Appellate Court of Illinois, 1993)
Boyd v. United Farm Mutual Reinsurance Co.
596 N.E.2d 1344 (Appellate Court of Illinois, 1992)
Merrill Lynch Mortgage Corporation v. Narayan
908 F.2d 246 (Seventh Circuit, 1990)
Merrill Lynch Mortgage Corp. v. Narayan
908 F.2d 246 (Seventh Circuit, 1990)
Woll v. Loeb
541 N.E.2d 809 (Appellate Court of Illinois, 1989)
Frank Novak & Sons, Inc. v. Sommer & MacA Industries, Inc.
538 N.E.2d 700 (Appellate Court of Illinois, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
431 N.E.2d 738, 103 Ill. App. 3d 423, 59 Ill. Dec. 237, 1982 Ill. App. LEXIS 1387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emmenegger-construction-co-v-king-illappct-1982.