County of Dauphin v. Fid. & Deposit Co. of Md.

770 F. Supp. 248, 1991 U.S. Dist. LEXIS 10126, 1991 WL 136354
CourtDistrict Court, M.D. Pennsylvania
DecidedJanuary 16, 1991
DocketCiv. A. 1:CV-89-0573
StatusPublished
Cited by16 cases

This text of 770 F. Supp. 248 (County of Dauphin v. Fid. & Deposit Co. of Md.) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Dauphin v. Fid. & Deposit Co. of Md., 770 F. Supp. 248, 1991 U.S. Dist. LEXIS 10126, 1991 WL 136354 (M.D. Pa. 1991).

Opinion

MEMORANDUM

RAMBO, District Judge.

This case is before the court on the motion of defendant, Fidelity and Deposit Company of Maryland (“Fidelity”), for summary judgment, partial summary judgment, judgment on the pleadings or partial *249 judgment on the pleadings, and for the sanctions of dismissal or evidentiary preclusion. Plaintiff, County of Dauphin (“the County”), instituted this action against Fidelity in the Dauphin County Court of Common Pleas, on March 31, 1989. Fidelity removed the action to this court on April 19,1989, on the basis of diversity of citizenship. The parties have had ample time for discovery, this court having granted two extensions of the discovery deadlines, which allowed the parties a total of sixteen (16) months within which to conduct discovery. Fidelity filed the present motion on October 15, 1990, with supporting documents. The parties have briefed the motion and it is now ripe for the court’s decision.

FACTUAL BACKGROUND

The undisputed facts pertinent to this motion are as follows. In February, 1984, the County entered into a contract with a prison equipment contractor, Harry C. Partridge, Jr. & Sons, Inc. (“Partridge”), for the supply and installation of security equipment to a project for new construction and renovation of the Dauphin County Prison. The Partridge contract was one of five prime contracts awarded by the County for work related to the prison project. The other four prime contracts were for general construction, electrical work, plumbing, and heating, ventilation and air conditioning.

As surety for Partridge, Fidelity issued a performance bond that named Partridge as its principal and the County as its obligee. In September, 1984, before it completed its obligations under the contract, Partridge filed for Chapter 11 bankruptcy protection and, subsequently, was found to have rejected the contract with the County. Thereafter, Fidelity, with the agreement of the County, arranged for Roanoke Iron and Bridgework Company (“Roanoke”) to complete Partridge’s contractual obligations. Due to Roanoke’s difficulty in obtaining the required performance bond, the County and Roanoke did not enter into a new contract. Instead, Fidelity and the County agreed that Fidelity would stand behind Roanoke as the completing contractor under the Partridge contract and Fidelity reinstituted its performance bond. Insofar as they are relevant to this motion, Roanoke’s obligations under the contract were the same as those of Partridge.

The contract documents were provided by the County. The contractual provisions relevant to this dispute concern the times for commencement and completion of the contractual work (Article 3, Contract and Paragraph 9, Supplemental General Conditions); liquidated damages (Article 3, Contract, and Paragraph 9, Supplemental General Conditions); final payment (Paragraph 9, General Conditions); and mutual responsibility (Paragraph 6, General Conditions).

In accordance with the time for completion of the work set forth in the contract and the notice to proceed issued by the County on February 10, 1984, Roanoke’s contractual completion date was May 25, 1985. The overall project completion date set by the County was also May 25, 1985. However, it is undisputed that Roanoke did not substantially complete the work on the project until January, 1986. The County issued Roanoke a certificate of substantial completion effective January 24, 1986, which certified that Roanoke’s work under the contract was sufficiently complete to allow the County to occupy or utilize the work as provided for in the contract. An occupancy permit was issued for that portion of the project that constituted new construction on July 27, 1986. By letter dated October 21, 1987, the County’s architect recommended that final payment be made to Roanoke, which payment the County executed by check, dated December 3, 1987.

The County, as noted, instituted this action against Fidelity on March 31, 1989. The County alleges, and Fidelity does not deny, that there was a 244-day delay beyond the 465 days allowed in the contract for completion of Roanoke’s work. The delay is measured as the time between the issuance to Partridge of the Notice to Proceed and the issuance to Roanoke of the Certificate of Substantial Completion. The County claims Roanoke’s delay engendered delay to the overall completion of the *250 project, which caused the County to incur damages totalling $1,182,686.91, mostly in the form of administrative payments to the other contractors on the prison project. While Fidelity agrees that Roanoke’s work was not performed on time, it denies that Roanoke’s delay caused the overall delay in the project, or the expenses the County claims as damages.

Fidelity provided this court with documents indicating that at various stages of the project, the County encountered timeliness and other problems with other prime contractors on the project. Those documents, Fidelity argues, demonstrate that the responsibility for the overall delay in the project cannot be attributed to Roanoke. Fidelity argues, further, that even if Roanoke’s delay period caused some damages, under Paragraph 9 of the General Conditions to the contract, the County waived its right to damages by making final payment. In the alternative, Fidelity argues that the County is limited to liquidated damages of $100.00 per day for the 244 days of Roanoke’s delay, as provided for in Article 3 of the contract, and Paragraph 9 of the Supplemental General Conditions.

DISCUSSION

Fidelity’s motion requests summary judgment or judgment on the pleadings. Since the parties relied upon, and the court has considered, matters that are outside of the pleadings, the motion will be treated as one for summary judgment. Fed.R.Civ.P. 12(c); Nottingham v. Peoria, 709 F.Supp. 542, 545 (M.D.Pa.1988).

Rule 56(c) of the Federal Rules of Civil Procedure requires the entry of summary judgment

after adequate time for discovery and upon motion, against a party who fails to make a showing sufficient to establish the existence of an element essential to that party’s case, on which that party will bear the burden of proof at trial. In such a situation, there can be ‘no genuine issue as to any material fact,’ since a complete failure of proof concerning an essential element of the non-moving party’s case necessarily renders all other facts immaterial.

Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986). The party seeking summary judgment satisfies his burden under Rule 56 by “ ‘showing’—that is, pointing out to the district court—that there is an absence of evidence to support the nonmoving party’s case.” Id., 477 U.S. at 325, 106 S.Ct. at 2554. The nonmoving party has the burden of demonstrating to the court that there exists a genuine issue of material fact by reference to affidavits, or depositions, answers to interrogatories, admissions on file or similar evidentiary materials. Fed.R.Civ.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Asaro v. Abernathy
M.D. Pennsylvania, 2025
HILTON v. PORCH.COM
W.D. Pennsylvania, 2020
Accurso v. Infra-Red Services, Inc.
119 F. Supp. 3d 316 (E.D. Pennsylvania, 2015)
Synthes, Inc. v. Emerge Medical, Inc.
25 F. Supp. 3d 617 (E.D. Pennsylvania, 2014)
In Re Garman
413 B.R. 215 (E.D. Pennsylvania, 2009)
Heffron v. Adamar of New Jersey, Inc.
270 F. Supp. 2d 562 (D. New Jersey, 2003)
Sunshine Shopping Center, Inc. v. Kmart Corp.
85 F. Supp. 2d 537 (Virgin Islands, 2000)
Pacitti v. Macy's
Third Circuit, 1999
Hullett v. Towers, Perrin, Forster & Crosby, Inc.
38 F.3d 107 (Third Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
770 F. Supp. 248, 1991 U.S. Dist. LEXIS 10126, 1991 WL 136354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-dauphin-v-fid-deposit-co-of-md-pamd-1991.