L & A Contracting Co. v. Southern Concrete Services, Inc.

17 F.3d 106, 1994 WL 71564
CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 24, 1994
Docket93-07171
StatusPublished
Cited by16 cases

This text of 17 F.3d 106 (L & A Contracting Co. v. Southern Concrete Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L & A Contracting Co. v. Southern Concrete Services, Inc., 17 F.3d 106, 1994 WL 71564 (5th Cir. 1994).

Opinion

WISDOM, Circuit Judge:

This case turns on the legal distinction between “breach” and “default”.

A primary contractor sued its bonded subcontractor and the bonding agent for damages arising from the subcontractor’s breach of the subcontract. The district court held the subcontractor and surety liable to the contractor. On this appeal, the subcontractor and surety challenge the district court’s judgment. We AFFIRM the district court’s judgment against the subcontractor. We VACATE the judgment against the surety and RENDER judgment in the surety^ favor.

I.

L & A Construction Company (“L & A”), the general contractor on a project to build a bridge in Apalachicola, Florida, subcontracted with Southern Concrete Services (“Southern”) to provide concrete for the project. Southern, as required by the subcontract, obtained a performance bond from Fidelity & Deposit Company of Maryland (“F & D”). Southern began supplying concrete to L & A in early 1987.

We need not chronicle the ensuing deterioration in business relations between L & A and Southern. It suffices for this opinion to say that Southern failed to provide sufficient concrete to L & A in a timely manner and breached the subcontract in numerous other particulars. L & A repeatedly complained to Southern about its slow delivery rates and the poor quality of the concrete Southern supplied. On May 29, 1987, L & A sent Southern a letter stating that Southern had breached the contract and giving Southern five days to cure the deficiencies in its performance. L & A sent a copy of the letter to F & D. Southern’s performance apparently improved after the May 29 letter. In response to a routine inquiry from F & D on August 3, 1987, L & A stated that Southern was performing satisfactorily.

Southern’s improved performance did not last long, and L & A soon resumed its periodic complaints. On January 12, 1988, L & A sent another letter to Southern and F & D in which it requested “that the Bonding Company take the necessary steps to fulfill this contract to prevent any further delays and costs to L & A”. F & D did not respond to the letter and took no action. Southern completed its obligations under the subcontract on May 27,1988. At no time did L & A refuse to accept Southern’s performance.

L & A sued Southern and F & D for breach of contract in Mississippi state court on August 19,1988. The defendants prompt *109 ly removed the case to the United States District Court for the Southern District of Mississippi on the basis of diversity of citizenship. 1 Southern counterclaimed against L & A alleging various breaches of the subcontract.

The district court conducted a six-day bench trial beginning on August 17, 1992. On September 22, 1992, the district court, applying Florida law, 2 held that both Southern and L & A had breached the subcontract. The district court, after offsetting the award from Southern’s counterclaim, held that L & A was entitled to recover damages of $642,-269 plus postjudgment interest from Southern and F & D. 3 After the district court overruled their posttrial motions, the defendants appealed to this Court. L & A cross-appealed from the district court’s judgment but later dismissed its cross-appeal. Only the defendants’ appeals remain for us to decide.

This case turns on the language of the subcontract and Southern’s performance bond. “A bond is a contract, and, therefore, a bond is subject to the general law of contracts”. 4 We review de novo questions involving the construction or interpretation of contracts. 5

II.

A F & D’s Liability Under its Bond

We turn first to F & D’s appeal. As a surety, F & D’s liability is governed by the terms of its bond with L & A. While Southern is, of course, directly liable for its own breach of contract, the bond in this case imposes liability on F & D for Southern’s breach only if two conditions exist. First, Southern must have been in default of its performance obligations under the subcontract. Second, L & A must have declared Southern to be in default. 6 The main focus of our inquiry is on the declaration requirement, although we shall also briefly address the type of default that is required.

We first must consider whether the bond term “declared ... to be in default” is ambiguous. 7 While the construction of unambiguous contracts is a matter of law, resolving ambiguous contracts requires a fact-specific inquiry to ascertain the parties’ intent. That inquiry is best performed by the district court, and its factual determinations *110 of the parties’ intent will be reversed on appeal only if clearly erroneous. 8

A contractual term is ambiguous if it is reasonably subject to more than one meaning. 9 Although the bond does not define the terms “declare” or “default”, we consider the term “declared in default” unambiguous; the definition L & A offers is unreasonable. The only authority L & A offers for its view is Webster’s Ninth New Collegiate Dictionary. Webster’s defines “declare” as “to make clear; to make known formally or explicitly; to make evident; to state emphatically” and “default” as “to fail to fulfill a contract, agreement, or duty”. Therefore, L & A concludes, any communication that “[made] it clear that [Southern] failed to fulfill a contract or duty” constituted a legal declaration of default.

Three factors counsel rejection of L & A’s popular dictionary authority. First, L & A’s proffered definition misapprehends the legal nature of the “default” that is required before the obligee’s claim against the surety matures. Athough the terms “breach” and “default” are sometimes used interchangeably, 10 their meanings are distinct in construction suretyship law. Not every breach of a construction contract constitutes a default sufficient to require the surety to step in and remedy it. To constitute a legal default, there must be a (1) material breach or series of material breaches (2) of such magnitude that the obligee is justified in terminating the contract. 11 Usually the principal is unable to complete the project, leaving termination of the contract the obligee’s only option. 12 The definition of “default” implicit in L & A’s dictionary analogy impermissibly blurs the distinct concepts of “breach” and “default”. 13

Second, L & A’s definition is impractical.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mohamed v. Bondi
Second Circuit, 2026
Singh v. Garland
Second Circuit, 2024
Western Surety Co. v. T & L Zarda Investments
Court of Appeals of Kansas, 2019
Raito, Inc. v. Cardi Corp.
Superior Court of Rhode Island, 2010
Gray v. Sage Telecom Inc.
253 F. App'x 402 (Fifth Circuit, 2007)
Colorado Structures, Inc. v. Insurance Co. of the West
161 Wash. 2d 577 (Washington Supreme Court, 2007)
Lyndon Property Insurance v. Eastern Kentucky University
200 F. App'x 409 (Sixth Circuit, 2006)
DCC CONSTRUCTORS v. Randall Mech., Inc.
791 So. 2d 575 (District Court of Appeal of Florida, 2001)
Central Louisiana Electric Co. v. Dolet Hills Mining Venture
116 F. Supp. 2d 726 (W.D. Louisiana, 2000)
Cates Construction, Inc. v. Talbot Partners
980 P.2d 407 (California Supreme Court, 1999)
Hernandez v. Reno
91 F.3d 776 (Fifth Circuit, 1996)
Morse/Diesel, Inc. v. Trinity Industries, Inc.
875 F. Supp. 165 (S.D. New York, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
17 F.3d 106, 1994 WL 71564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-a-contracting-co-v-southern-concrete-services-inc-ca5-1994.