Fred Howland, Inc. v. Gore

13 So. 2d 303, 152 Fla. 781, 1942 Fla. LEXIS 751
CourtSupreme Court of Florida
DecidedDecember 18, 1942
StatusPublished
Cited by13 cases

This text of 13 So. 2d 303 (Fred Howland, Inc. v. Gore) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fred Howland, Inc. v. Gore, 13 So. 2d 303, 152 Fla. 781, 1942 Fla. LEXIS 751 (Fla. 1942).

Opinions

BUFORD, J.:

On June 9, 1936, R. H. Gore as Trustee for R. H. Gore Company, an Illinois corporation, who will be hereinafter referred to as the owner, entered into a contract with Fred Howland, Inc., a Florida corporation, who will be hereinafter referred to as the contractor, under which the contractor was to furnish all of the labor and materials and perform all the work necessary to be done for the completion of the exterior masonry walls, roof and structure repairs on a certain building in Fort Lauderdale, Florida, for the sum of $29,000.00 The building had been partly constructed back in 1925 or 1926 but it stood uncompleted for at least ten intervening years.

The work contemplated under this contract appears to have been performed with the exception of two minor items, and was paid for with exception of those items amounting to $170.00, and thereafter, on August 17, 1936, another contract was entered into between the same parties for the completion of the building for the sum of $125,500.00. It was provided in the contract that the building should be completed on or before November 15, 1936, and it was further provided:

“In the event said construction work is not completed on or before November 15, 1936, the contractor agrees to pay to the owner as liquidated damages for delay in completing said construction work the sum of One Hundred Fifty ($150.00) Dollars per each calendar day for each day’s delay in completing said construction work. The owner shall be authorized to apply so much of the monies retained under this contract as may be necessary to pay the said liquidated damages.”

Prior to November 15, 1936, the time for the completion of the building was extended to November 25, 1936.

*784 It appears from the record that the building was substantially completed on November 25, 1936, but was not fully completed because the owner and the proposed tenant of certain store space in the building were in a controversy as to how that space should be finished. The record shows that it required about four weeks to furnish and equip the building for use as a first class hotel after the completing of the contract, and the record shows that the hotel was furnished and opened as such on December 24, 1936.

During the progress of the work the contractor claimed that he furnished and constructed numerous items in the building which he was not required to furnish under the terms of the contract but which he furnished and constructed at the specific request of the owner who agreed to pay for the same, and claimed a balance due under the two contracts, together with extras furnished, in the sum of $21,000.00. The owner refused to pay the bill. The contractor filed his notice of claim'of lien in the office of the clerk of the circuit court on March 22, 1937, and thereafter, on June 24, 1937, filed his bill of complaint to foreclose his alleged lien for the sum of $21,000.00.

On October 20, 1937, the contractor filed his amended bill of complaint. Prior to the filing of the amended bill of complaint, defendant had filed his answer, and counter-claim and motion to dismiss. In the counter-claim the owner, inter alia, prayed:

“(b) That an accounting be had between the plaintiff and the defendant, and that it be adjudicated, and determined that plaintiff is indebted to- the: defendant for. the following sums of money, to-wit:
1. Deduction for Walgreen Store .......................... $ 3,000,00
2. Liquidated damages for delay in completion of the building from November 15 to December 24, 1936, at $150.00 per day........................ 5,850.00
3. Indemnification for and reimbursement of all sums paid for labor and materials furnished as alleged in Paragraph XVIII hereof.............. 3,163.29
*785 4. The amount necessary to complete the building in accordance with the construction contract with M. E. Hoffman.................................. 16,922.58
5. Attorney’s fees to be allowed defendant’s solicitors .................................................................... 7,250.00
$36,185.87
that a credit be allowed on the foregoing in the following sums, to-wit:
1. Amount due plaintiff on first contract (completed by defendant at plaintiff’s expense), shown as plaintiff’s Exhibit A,............................ 170.00
2. Amount due plaintiff on second contract partially shown as plaintiff’s Exhibit B (completed by defendant at plaintiff’s expense) .................. 6,370.00
3. Amount due plaintiff on extras (Venetian channel guides) .............................................................. 570.07
$7,110.07
and that a money judgment be entered against the plaintiff in favor of the defendant for the sum of $29,075.80, together with interest on the said sum from the date said sum became due to the defendant, and that the defendant have execution thereon.”

Motion to dismiss the amended bill of complaint contained the following:

“1. The amended bill of complaint fails to. show that plaintiff has complied with the various provisions of Chapter 17097, General Acts of 1935, (Uniform Mechanics’ Lien Act), so as to be entitled to a lien.” and also the following:
“9. It affirmatively appears from the amended bill of complaint that plaintiff failed to perfect its alleged lien, as required by law, and, therefore, the Equity Court is without jurisdiction.
“10. Plaintiff’s alleged claim of lien shown by Exhibit E, when considered in the light of the allegations of the *786 amended bill of complaint, affirmatively shows that it was not filed within the time required by law.”

Voluminous testimony was taken, some 2000 pages in all, and after a part of this testimony was taken, on the 6th day of July, 1940, the court entered its final decree, as follows:

“This cause came on for final hearing upon the pleadings filed herein, the testimony and proofs submitted, and the argument of counsel. The finding of fact and conclusions of law made by the court are fully set forth in an opinion filed herewith. The motion to dismiss the bill of complaint should be granted for the reasons given but on equitable grounds the items claimed by the plaintiff and allowed by the court should be allowed as a set-off to the counter claim of the defendant as set out in the opinion.
“Thereupon It Is Ordered, Adjudged and Decreed as follows :
“1. That the motion to dismiss the bill of complaint as amended be and the same is hereby granted.
“2. That the following items claimed under the defendant’s counterclaim be allowed:
Deduction for Walgreen Store ................................ $ 1,136.00

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Orix Capital Markets v. Park Avenue Assoc.
881 So. 2d 646 (District Court of Appeal of Florida, 2004)
Scottsdale Ins. Co. v. Haynes
793 So. 2d 1006 (District Court of Appeal of Florida, 2001)
Bidon v. DEPT. OF PRO. REGULATION, FLA. REAL ESTATE COMM.
596 So. 2d 450 (Supreme Court of Florida, 1992)
JM Beeson Co. v. Sartori
553 So. 2d 180 (District Court of Appeal of Florida, 1989)
Saul v. Basse
399 So. 2d 130 (District Court of Appeal of Florida, 1981)
Kendall East Estates, Inc. v. Banks
386 So. 2d 1245 (District Court of Appeal of Florida, 1980)
Maurice Fox v. City of West Palm Beach
383 F.2d 189 (Fifth Circuit, 1967)
Bradford Builders, Inc. v. Department of Water & Sewers of Miami
142 So. 2d 137 (District Court of Appeal of Florida, 1962)
Moore v. Crum
68 So. 2d 379 (Supreme Court of Florida, 1953)
Hardee v. Richardson
47 So. 2d 520 (Supreme Court of Florida, 1950)
Little v. Kendrick
12 So. 2d 899 (Supreme Court of Florida, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
13 So. 2d 303, 152 Fla. 781, 1942 Fla. LEXIS 751, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fred-howland-inc-v-gore-fla-1942.