Gerstner Electric, Inc. v. American Insurance Company

520 F.2d 790, 1975 U.S. App. LEXIS 13233
CourtCourt of Appeals for the Eighth Circuit
DecidedAugust 8, 1975
Docket74-2001
StatusPublished
Cited by21 cases

This text of 520 F.2d 790 (Gerstner Electric, Inc. v. American Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gerstner Electric, Inc. v. American Insurance Company, 520 F.2d 790, 1975 U.S. App. LEXIS 13233 (8th Cir. 1975).

Opinion

KILKENNY, Circuit Judge.

Appellant Gerstner appeals from the district court’s judgment of dismissal notwithstanding a jury verdict and asks for alternative relief which we need not consider. The verdict in favor of appellant, including compensatory and punitive damages, was substantial. We affirm.

FACTS

On September 7, 1971, appellant entered into a Contract Agreement (Contract) with the Missouri State Highway Commission under which appellant agreed to furnish, at its own expense, all labor, materials and equipment required in the proposed construction of a sector of Route 61 in Lincoln County, Missouri, according to the plans and specifications of the highway project. As part of the Contract, Gerstner agreed to and did furnish to the Highway Commission a Contract Bond (Bond) with the appellee as surety. Under the terms of the Bond, appellant and appellee were firmly bound unto the State of Missouri in the penal sum of $2,067,853.90, to secure faithful performance of the Contract. The Bond provided, among other things, that it would be and remain in full force and effect unless appellant properly and promptly completed the work in accordance with the provisions of the Contract, and its plans and specifications. Appellant agreed to furnish all the labor and materials required by the Contract and to “ * * * pay for all materials, lubricants, fuels, coal and coke, repairs on machinery, groceries and foodstuff, equipment and tools consumed or used in connection with the construction of such *792 work, * * * and for all labor performed in said work, whether by subcontractor or claimant in person, or by employee, agent, servant, bailee or bailor * * [Emphasis added.]

Prior to the award of the contract to appellant, it and others signed an indemnity agreement by which they agreed to indemnify appellee as surety against any liability, loss, damages, and expenses which it might sustain by reason of having thereafter executed any Bond. The indemnity agreement contained provisions (1) authorizing appellee, in the event of any failure to pay for labor and materials used in the prosecution of the Contract, to “take any action it might deem appropriate,” and (2) in the event of such failure, assigning as collateral security (effective as of the date of such Bond) all rights of the indemnitors under the Contract referred to in the Bond, and all sums due or which might thereafter become due under such Contract.

Appellant subcontracted the asphalt work to B & K Construction Company for an amount in excess of $779,000.00. Under the subcontract, B & K was required to pay for all labor, materials and equipment. Appellant received periodic payments from the Highway Commission based on engineers’ pay estimates furnished to the Commission and on the amount of work completed and accepted by the Commission engineers subsequent to the last estimate. These estimates included work done by appellant and by all subcontractors, including B & K.

Appellant and B & K were in continuous conflict over charges and arrearages from a time shortly after the commencement of the work. Appellant had been withholding substantial payments from B & K for labor performed and materials used by the latter in the performance of its subcontract. Appellee first acquired knowledge of the dispute and B & K’s claim thereon in mid-September, 1973, by a phone call from it to Donk, a bond claim manager for appellee. Shortly thereafter, Donk contacted appellant by phone and received further information on B & K’s claim and appellant’s counterclaim for back charges. Appellant’s president told Donk that payment would be withheld from B & K to the extent of its claim for arrearages of $207,000.00.

In mid-September, the Highway Commission paid appellant $49,151.51 under an estimate. Of that amount, $42,523.00 was for work and labor performed and materials furnished by B & K. No part of this sum was paid by appellant to B & K.

Being greatly concerned over the possibility of B & K making a direct claim against appellant under the terms and requirements of the Bond, Donk sent a telegram to the Highway Commission requesting and directing it to withhold further payments to appellant. He then spoke to counsel for the Highway Commission and advised him of B & K’s unpaid claim for labor and materials. After reviewing the Contract, the Bond contract, and a copy of the indemnity agreement, the Commission counsel advised the Commission to withhold payment of any additional funds to appellant.

On October 15th, the Highway Commission issued another estimate in the sum of $67,168.51 for labor and materials furnished in connection with the construction. Of that amount, $62,773.00 was for work and labor performed and materials furnished by B & K.

Claiming back charges due, appellant continued in refusing to pay B & K for work and labor performed and materials furnished. Appellant spent, for its own purposes, the money it received from the Highway Commission based on estimates for work and labor performed and materials furnished by B & K. It is undisputed that if appellant had received the $91,000.00 withheld by the Highway Commission, it would not have paid B & K but instead would have used the money to pay its own indebtedness.

In November, 1973, B & K filed an action in the circuit court of the City of St. Louis against appellant and appellee. Under Count I, it sought $245,460.59 for work and labor performed and materials *793 furnished and expended under the contract with appellant. Under Count II, it sought $135,160.19 for additional work. Appellant filed a counterclaim for back charges. Appellee entered its appearance and is currently defending its interest in that suit. It is agreed that until the pending litigation in the circuit court of the City of St. Louis is terminated, the dispute between appellant and B & K will remain unresolved. At the time of the instant arguments there were approximately $230,000.00 in earned estimates held by the Highway Commission. If B & K is successful in its suit, it will receive all the money in the hands of the Highway Commission.

ISSUE

Did the trial court err in sustaining appellee’s motion and entering a judgment against appellant notwithstanding the jury verdict?

DISCUSSION

The fundamental question before us is whether on the present record the appellee, by its action in requesting the Highway Commission to withhold progress payments to appellant which otherwise would be paid to it, did wrongfully and without justification or excuse interfere with the contractual relationship between appellant and the Highway Commission.

Briefly reviewing the Contract documents, we find that 5% of the cost of the work performed was retained by the Highway Commission and could not be released without the consent of appellee. The Bond with appellant as principal and appellee as surety, which was made part of the Contract, guaranteed, inter alia, that appellant would pay for all materials, supplies, labor and equipment required to perform the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Colorado Structures, Inc. v. Insurance Co. of the West
161 Wash. 2d 577 (Washington Supreme Court, 2007)
Hess v. Sanofi-Synthelabo Inc.
503 F. Supp. 2d 1178 (E.D. Missouri, 2007)
National Sur. Corp. v. Prairieland Const. Inc.
354 F. Supp. 2d 1032 (E.D. Missouri, 2004)
Gott v. First Midwest Bank of Dexter
963 S.W.2d 432 (Missouri Court of Appeals, 1998)
Maberry v. Said
911 F. Supp. 1393 (D. Kansas, 1995)
Morton v. Hearst Corp.
779 S.W.2d 268 (Missouri Court of Appeals, 1989)
Minnesota Mining & Manufacturing Co. v. Williamson
675 S.W.2d 951 (Missouri Court of Appeals, 1984)
City of Warrensburg, Mo. v. RCA Corp.
571 F. Supp. 743 (W.D. Missouri, 1983)
City of Warrensburg v. RCA Corp.
550 F. Supp. 1364 (W.D. Missouri, 1982)
Francisco v. Kansas City Star Co.
629 S.W.2d 524 (Missouri Court of Appeals, 1981)
Lambert v. Maryland Cas. Co.
403 So. 2d 739 (Louisiana Court of Appeal, 1981)
C & M DEVELOPERS, INC. v. Berbiglia, Inc.
585 S.W.2d 176 (Missouri Court of Appeals, 1979)
Salomon v. Crown Life Insurance
536 F.2d 1233 (Eighth Circuit, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
520 F.2d 790, 1975 U.S. App. LEXIS 13233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gerstner-electric-inc-v-american-insurance-company-ca8-1975.