Environmental Energy Partners, Inc. v. Siemens Building Technologies, Inc.

178 S.W.3d 691, 2005 Mo. App. LEXIS 1568, 2005 WL 2741452
CourtMissouri Court of Appeals
DecidedOctober 25, 2005
Docket26521, 26702
StatusPublished
Cited by16 cases

This text of 178 S.W.3d 691 (Environmental Energy Partners, Inc. v. Siemens Building Technologies, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Energy Partners, Inc. v. Siemens Building Technologies, Inc., 178 S.W.3d 691, 2005 Mo. App. LEXIS 1568, 2005 WL 2741452 (Mo. Ct. App. 2005).

Opinion

JOHN E. PARRISH, Presiding Judge.

This is an appeal by Siemens Building Technologies, Inc., (Siemens) and St. John’s Regional Medical Center and Mercy Lifecare Systems, Inc., (collectively referred to as St. John’s) and a cross-appeal by Environmental Energy Partners, Inc. (EEP). The action that produced the judgment that is appealed began with a petition filed by Siemens against EEP and St. John’s. The petition sought damages for work Siemens performed on property owned by St. John’s pursuant to a subcontract with EEP and enforcement of a mechanic’s hen on St. John’s property. St. John’s filed a cross-claim against EEP seeking damages for attorneys’ fees and costs incurred “in defending the Mechanic’s Lien Claim of Siemens.”

EEP filed a cross-petition against St. John’s for breach of contract seeking the balance of the contract amount that remained unpaid pursuant to its contract with St. John’s. EEP later filed a four-count counterclaim against Siemens. The claims against Siemens were actions for breach of contract (Count I), interference with contract (Count II), malicious prosecution (Count III), and abuse of process (Count IV). Count I sought damages for any amount “awarded [St. John’s] ... on [St. John’s] cross-claim.” Counts II, III, and IV each sought actual and punitive damages, attorneys’ fees, and costs.

The factual background and initial stages of the procedural background of this case are stated in Siemens Building Technologies, Inc. v. St. John’s Regional Medical Center, 124 S.W.3d 3 (Mo.App. 2004) (Siemens I). Siemens I may be reviewed for a complete statement of facts and a recitation of procedural events that occurred prior to the circumstances that produced this appeal. Facts related to issues addressed in this opinion are set forth in the discussions that follow regarding the points for determination by this appeal.

The first trial in this matter began August 15, 2000. Prior to its start, Siemens dismissed its action against St. John’s for enforcement of a mechanic’s hen. Siemens proceeded with its claim against EEP for breach of contract. St. John’s dismissed its cross-claim against EEP. Verdict was returned in favor of Siemens on its breach of contract action against EEP, but the damages the jury assessed for breach of contract were reduced by an “offset” for liquidated damages to which the jury found EEP entitled due to late completion of work by Siemens. Judgment was rendered on November 28, 2000. The judgment states, as applicable to this appeal:

*696 A. Cross-Claim of [St. John’s] against [EEP] be and is hereby dismissed ■without prejudice pursuant to § 429.140, R.S.Mo.
B. [Siemens’] Amended Petition to Enforce its Mechanic’s Lien as to the real estate and improvements owned by [St. John’s] be and is hereby dismissed with prejudice; all claims of [Siemens’] Mechanic’s Lien rights respecting Lien No. 3597 be and are hereby satisfied in all respects; and,
[[Image here]]
D. Counterclaim [Count I] of [EEP] against [Siemens] be and is hereby dismissed with prejudice; and,
E. On the claim of [Siemens] against [EEP], Judgment is granted in favor of [Siemens] and against [EEP] on [Siemens’] Amended Petition For Breach of Contract. The Jury finding respecting the off-set of [EEP] in the amount of $154,250.00 is herewith credited as an off-set to the Jury finding in favor of [Siemens] for $52,703.75 and the Court Orders that [Siemens] take nothing from [EEP] by reason of said offset and that [EEP] take nothing from [Siemens] by reason of said off-set; [1] and,
[[Image here]]
G. Pursuant to Rule 74.01(b) the Court finds there is no just reason for delay in entering this Judgment and this Judgment is final and appeal-able.

The judgment was not appealed.

EEP’s claim against St. John’s for breach of contract and its remaining claims against Siemens (counterclaim Counts II, III, and IV) were tried before a jury at a later date. Trial began June 7, 2004. Verdicts were returned in favor of EEP on its claim against St. John’s and on all its claims against Siemens as follows:

VERDICT A — EEP’s action against St. John’s for breach of contract: the jury found for EEP and assessed damages owed EEP, as instructed by the trial court, in the amount of $101,546.25.
VERDICT B — EEP’s action against Siemens for malicious prosecution: the jury found for EEP, awarded no actual damages but awarded $3,000,000 punitive damages.
VERDICT C — EEP’s action against Siemens for abuse of process: the jury found for EEP, awarded no actual damages but awarded $201,175 punitive damages.
VERDICT D — EEP’s action against Siemens for interference with contracts: the jury found for EEP, awarded $26,100 actual damages and $500,000 punitive damages.

Siemens filed a motion for Judgment Notwithstanding the Verdict and Alternative Motion for Remittitur directed to the punitive damages verdicts. The trial court granted the motion in part and denied it in part. It granted the motion with respect to punitive damages awarded in Verdicts B and C. It entered judgment on counterclaims II and III, awarding EEP nothing for the reason that no actual damages were awarded. The trial court observed that it was setting aside the two punitive damages awards “only because the law *697 appears to disallow punitive damages when no actual damages are awarded.”

Judgment was entered as follows:
It is hereby Ordered, Adjudged and Decreed, that Judgment be entered on Verdict A in favor of EEP on its Cross-Petition against St. John’s and that EEP have and recover from St. John’s damages in the amount of $101,546.25, prejudgment interest thereon in the amount of $70,108.64 from August 8, 2000, through June 9, 2004, with interest at a rate of 18% per annum from June 10, 2004, on the sum of $101,546.25, and with interest at a rate of 9.0% per an-num from June 10, 2004, on the sum of $70,108.64.
It is hereby Ordered, Adjudged and Decreed, that Judgment be entered on Verdict B in favor of Siemens on EEP’s counterclaim for malicious prosecution and the [sic] EEP shall recover nothing thereon.
It is hereby Ordered, Adjudged and Decreed, that Judgment be entered on Verdict C in favor of Siemens on EEP’s counterclaim for abuse of process and EEP shall take nothing thereon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kansas City Live Block 139 Retail, LLC v. Fran's K.C. Ltd.
504 S.W.3d 725 (Missouri Court of Appeals, 2016)
Coverdell v. Countrywide Home Loans, Inc.
375 S.W.3d 874 (Missouri Court of Appeals, 2012)
Marquis Financial Services of Indiana Inc. v. Peet
365 S.W.3d 256 (Missouri Court of Appeals, 2012)
ALLSTATE INSURANCE COMPANY v. Diana Lynn TARRANT Et Al.
363 S.W.3d 508 (Tennessee Supreme Court, 2012)
Agnello v. Walker
306 S.W.3d 666 (Missouri Court of Appeals, 2010)
Davis v. Chatter, Inc.
270 S.W.3d 471 (Missouri Court of Appeals, 2008)
Carter v. White
241 S.W.3d 357 (Missouri Court of Appeals, 2007)
Taylor v. Compere
230 S.W.3d 606 (Missouri Court of Appeals, 2007)
Walsh v. Al West Chrysler, Inc.
211 S.W.3d 673 (Missouri Court of Appeals, 2007)
Atkins v. McPhetridge
213 S.W.3d 116 (Missouri Court of Appeals, 2006)
Brady v. Curators of the University of Missouri
213 S.W.3d 101 (Missouri Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
178 S.W.3d 691, 2005 Mo. App. LEXIS 1568, 2005 WL 2741452, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-energy-partners-inc-v-siemens-building-technologies-inc-moctapp-2005.