Raito, Inc. v. Cardi Corp.

CourtSuperior Court of Rhode Island
DecidedApril 5, 2010
DocketC.A. No. PB 07-3235
StatusPublished

This text of Raito, Inc. v. Cardi Corp. (Raito, Inc. v. Cardi Corp.) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raito, Inc. v. Cardi Corp., (R.I. Ct. App. 2010).

Opinion

DECISION
Defendant and Third-Party Plaintiff Cardi Corporation (Cardi) filed a motion for reconsideration of this Court's April 5, 2010 Decision which granted summary judgment to Third-Party Defendant Western Surety Company (Western), discharging Western from any liability under the parties' Performance Bond.See Raito, Inc. v. Cardi Corp., 2010 R.I. Super. WL 1422002 (April 5, 2010). In that Decision, this Court held that the language in Paragraph 3.1 of the Performance Bond created a condition precedent, obligating Cardi to notify *Page 2 Raito and Western that Raito's performance was unsatisfactory and Cardi was considering declaring a default and terminating the Subcontract.

I
Facts Travel
On or about August 1, 2003, Cardi, as general contractor, entered into a contract (the Contract) with the State of Rhode Island, acting through the Rhode Island Department of Transportation for the construction of a new arch-span bridge over the Providence River on Interstate I-95 (the Project). Cardi, in connection with the Project, entered into a subcontract (the Subcontract) with Raito to install a series of concrete foundation shafts for the new bridge. With regard to the Subcontract, Raito, as principal, and Western, as surety, executed Payment Bond No. 929298884 (Payment Bond) and Performance Bond No. 92929884 (Performance Bond).

Cardi alleges that during the course of the work, Raito failed to perform the work in a timely and acceptable manner which resulted in delays to the Project and costs and damages to Cardi. Despite the alleged delays, Cardi never gave notice that it was considering declaring a default or attempted to arrange a conference with Western and Raito, but rather "back-charged" any delay costs against amounts which would have been due to Raito for its work under the Subcontract. Raito then filed the instant action to recover monies allegedly due from Cardi in connection with work performed as a subcontractor on the Project. Cardi counterclaimed against Raito to recover damages caused by Raito's alleged failure to timely and effectively perform such work. Additionally, both Raito and Cardi have brought actions against each other's sureties. This Court granted Western summary judgment on April 5, 2010, and Cardi filed a timely motion for reconsideration on June 4, 2010. *Page 3

II
Standard of Review
The Rhode Island Superior Court Rules of Civil Procedure, similar to the Federal Rules of Civil Procedure, do not specifically provide for motions to reconsider. School Committee of City ofCranston v. Bergin-Andrews, 984 A.2d 629, 649 (R.I. 2009). However, the Supreme Court of Rhode Island applies a liberal interpretation of the rules, and the Court must "look to substance, not labels." Sarni v. Melocarro,113 R.I. 630, 636, 324 A.2d 648, 651 (1974). It is well settled that a motion to reconsider should be treated as a motion to vacate under Super. R. Civ. P. 60(b). School Committee of City ofCranston, 984 A.2d at 649 (citing Keystone ElevatorCo. v. Johnson Wales University,850 A.2d 912, 916 (R.I. 2004)). Rule 60(b) provides in relevant part that under certain circumstances "[o]n motion and upon such terms as are just, the court may relieve a party or a party's legal representative from final judgment, order, or proceeding. . . ." A motion to vacate under Rule 60(b) "is addressed to the trial justice's sound judicial discretion and `will not be disturbed on appeal, absent a showing of abuse of discretion.'" KeystoneElevator Co., 850 A.2d at 916 (quoting Crystal RestaurantManagement Corp. v. Calcagni, 732 A.2d 706, 710 (R.I. 1999)).

III
Discussion
In support of its motion for reconsideration, Cardi first asserts that § 6.1 and § 6.3 of the Performance Bond allow recovery without any action under § 4. However, the plain language of § 6 states that the Surety's responsibilities arise only "[a]fter the Owner has terminated the contractor's right to complete the Construction Contract, and if the Surety elects to act under §§ 4.1, 4.2, or 4.3." Cardi construes the preceding sentence as only applicable to actions arising under §§ 4.1, 4.2, or 4.3. It contends that actual termination is not required for relief under §§ 4.4, 5, *Page 4 or relief under § 1, which guarantees the entire contract. However, this Court finds such a reading unavailing since § 4.4 first requires the completion of the conditions enumerated in § 3, which includes the issuance of a default and termination pursuant to § 3.2. Here, Cardi never properly issued Raito a notice of default and termination as this Court deemed is required by the Performance Bond.

Further, § 5 states that "[i]f the Surety does not proceed as provided in Section 4 with reasonable promptness, the Surety shall be deemed to be in default on this Bond." Again, Cardi could only proceed under § 4 once it had satisfied the conditions specified in § 3. Moreover, § 1 of the Performance Bond states that "[t]he Contractor and the Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to the Owner for the performance of this Construction Contract, which is incorporated herein by reference." As the Court noted in its Decision, the language of the Construction Contract, "does not conflict with or negate Cardi's obligations under Paragraph 3." Under the Performance Bond, "there is a period, before Cardi decides whether or not to terminate, during which time if Cardi is dissatisfied with Raito's performance, it should give Raito the opportunity to improve and properly comply with the terms of the Subcontract." After nearly four years of delays and problems causing Cardi to assess backcharges in the amount of $2,802,191.39, Cardi did not give Raito notice that it was dissatisfied with the work product nor did it provide Raito with an opportunity to improve and properly comply with the terms of the Subcontract.

In addition, Cardi argues that the Court's refusal to give legal effect to a default notice that was issued after the completion of the work is not supported by the Bond or applicable law. Cardi cites case law where claims arose for defective work or latent defects after the given projects were completed. See AgGrow Oils,LLC v. Nat'l Union Fire Ins. Co. of Pittsburgh, PA

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sarni v. Meloccaro
324 A.2d 648 (Supreme Court of Rhode Island, 1974)
School Committee v. Bergin-Andrews
984 A.2d 629 (Supreme Court of Rhode Island, 2009)
Ins. Co. of No. Amer. v. Metro. Dade Co.
705 So. 2d 33 (District Court of Appeal of Florida, 1997)
Pickering v. American Employers Insurance
282 A.2d 584 (Supreme Court of Rhode Island, 1971)
Dragon Construction, Inc. v. Parkway Bank & Trust
678 N.E.2d 55 (Appellate Court of Illinois, 1997)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
Keystone Elevator Co. v. Johnson & Wales University
850 A.2d 912 (Supreme Court of Rhode Island, 2004)
Crystal Restaurant Management Corp. v. Calcagni
732 A.2d 706 (Supreme Court of Rhode Island, 1999)
School Board of Escambia County v. Tig Premier Insurance
110 F. Supp. 2d 1351 (N.D. Florida, 2000)
People v. Tru-Sport Publishing Co.
160 Misc. 628 (New York Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
Raito, Inc. v. Cardi Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/raito-inc-v-cardi-corp-risuperct-2010.