Whiting-Turner Contracting Co. v. Guarantee Company of North America USA

2019 COA 44, 440 P.3d 1282
Colorado Court of Appeals·Decided March 21, 2019·No. 17CA2160·Published·Cited by 9 cases

Opinion

The summaries of the Colorado Court of Appeals published opinions constitute no part of the opinion of the division but have been prepared by the division for the convenience of the reader. The summaries may not be cited or relied upon as they are not the official language of the division. Any discrepancy between the language in the summary and in the opinion should be resolved in favor of the language in the opinion.

SUMMARY March 21, 2019

2019COA44

No. 17CA2160, Whiting-Turner v. Guarantee Co. of N. Am. USA — Construction Law — Suretyship and Guaranty — Performance Bonds; Contracts — Condition Precedent

For the first time in Colorado, a division of the court of appeals

applies to surety bonds cases the contract law principles governing

a party’s satisfaction of conditions precedent. In addition, the

division considers the proper calculation of the “Balance of the

Contract Price,” which is a key term in the standard form of surety

bond used throughout the construction industry. The division

affirms the trial court’s finding that the general contractor satisfied

the conditions precedent in the surety bond and thus triggered the

surety’s obligation to perform. COLORADO COURT OF APPEALS 2019COA44

Court of Appeals No. 17CA2160 City and County of Denver District Court No. 14CV34166 Honorable Andrew P. McCallin, Judge

Whiting-Turner Contracting Company,

Third-Party Plaintiff-Appellee,

v.

Guarantee Company of North America USA,

Third-Party Defendant-Appellant.

JUDGMENT AFFIRMED

Division II Opinion by JUDGE LIPINSKY Dailey and Furman, JJ., concur

Announced March 21, 2019

Husch Blackwell LLP, Jeffrey D. Whitney, Jeffrey M. Van der Veer, Denver, Colorado, for Third-Party Plaintiff-Appellee

Woods & Aitken LLP, Kory D. George, Colin P. Baumchen, Denver, Colorado, for Third-Party Defendant-Appellant ¶1 Performance bonds, like other forms of surety bonds, are

critical to managing the risk inherent in construction projects. If a

subcontractor fails to complete its work at a construction site, the

surety that underwrote the performance bond assumes

responsibility for the subcontractor’s obligations. Without

performance bonds, a construction project could come to a halt if a

single subcontractor walked off the job.

¶2 Performance bonds specify the actions that will trigger the

surety’s obligations. In this appeal, a surety, Guarantee Company

of North America USA (GCNA), and a general contractor, Whiting-

Turner Contracting Company, dispute whether Whiting-Turner

triggered GCNA’s obligations under a performance bond after a

subcontractor, Klempco Construction (2013) Inc., stopped work at

Whiting-Turner’s construction project. The parties’ disagreement

centers on whether Whiting-Turner paid GCNA the “Balance of the

Contract Price,” a key term in the performance bond, thereby

satisfying one of the bond’s conditions precedent.

¶3 Following a bench trial, the trial court entered judgment in

favor of Whiting-Turner and against GCNA. The trial court found

1 that Whiting-Turner had complied with the condition precedent set

forth in section 3.3 of the performance bond and that GCNA had

failed to perform its obligations under the bond.

¶4 On appeal, GCNA contends that the trial court applied the

wrong legal standard in determining whether Whiting-Turner

complied with section 3.3 of the performance bond, erred in finding

that GCNA had waived its argument regarding Whiting-Turner’s

compliance with section 3.3, erroneously found that Whiting-Turner

satisfied the condition precedent in section 3.3, awarded duplicative

damages to Whiting-Turner, and improperly awarded attorney fees

to Whiting-Turner.

¶5 We affirm.

I. Whiting-Turner’s Disputes with Klempco and GCNA

A. Klempco Signs a Subcontract for Work at Whiting-Turner’s Project

¶6 Whiting-Turner served as the general contractor for an office

building construction project in Denver (the Project). Whiting-

Turner and Klempco entered into an agreement (the Subcontract)

for Klempco’s construction of an anchor system at the Project’s

underground parking garage. The anchor system was necessary to

2 keep the sides of the excavated site from collapsing during the

initial phases of construction. Klempco’s work included the

installation of sprayed concrete, known as shotcrete, to support the

anchoring system. Whiting-Turner and Klempco agreed to a

Subcontract price of $1,785,783.00.

B. GCNA Provides a Performance Bond and a Payment Bond

¶7 Whiting-Turner required Klempco to furnish a performance

bond and a payment bond. (A surety that underwrites a payment

bond is obligated to pay the sub-subcontractors if the

subcontractor fails to do so.) Klempco obtained the bonds from

GCNA. The bonds, which followed American Institute of Architects

form A312, incorporated the Subcontract by reference. See 4A

Philip L. Bruner & Patrick J. O’Connor, Jr., Bruner & O’Connor on

Construction Law § 12:16, Westlaw (database updated June 2018)

(explaining that the A312 surety bond is a standard form in the

construction industry).

¶8 Section 3 of the performance bond specified the three

conditions precedent that Whiting-Turner would need to satisfy to

trigger GCNA’s obligations as surety:

3 • provide notice to Klempco and GCNA that Whiting-

Turner was considering declaring Klempco in default

(section 3.1);

• declare Klempco in default, terminate the Subcontract,

and notify GCNA of these actions (section 3.2); and

• “pay the Balance of the Contract Price in accordance

with the terms of the [Subcontract] to [GCNA] or to a

contractor selected to perform the [Subcontract]”

(section 3.3).

¶9 The performance bond defined “Balance of the Contract Price”

as “[t]he total amount payable by [Whiting-Turner] to [Klempco]

under the [Subcontract] after all proper adjustments have been

made, . . . reduced by all valid and proper payments made to or on

behalf of [Klempco] under the [Subcontract].” (Emphases added.)

C. Klempco Stops Work at the Project

¶ 10 Klempco fell behind schedule almost immediately and stopped

paying its sub-subcontractors. Klempco subsequently directed

Whiting-Turner to assume responsibility for the shotcrete

4 installation and to work directly with two of Klempco’s sub-

subcontractors.

¶ 11 Whiting-Turner sent Klempco and GCNA a letter declaring

Klempco in default under the Subcontract. In the letter, Whiting-

Turner stated that Klempco was incapable of completing its work at

the Project and “is apparently unable to complete payments to its

sub-subcontractors for previously completed work, and by its own

admissions is unable to cure such default.” Whiting-Turner

requested a meeting with Klempco representatives “to discuss the

details of Klempco’s request that Whiting-Turner take over its

work.” Whiting-Turner asked GCNA to attend the meeting “to

advise Whiting-Turner on how [GCNA] wishes for Whiting-Turner to

proceed in connection with the completion of Klempco’s work and

payment of its vendors.”

¶ 12 Representatives of Whiting-Turner, Klempco, and GCNA met

on April 30, 2014, to discuss, among other issues, Klempco’s

Free access — add to your briefcase to read the full text and ask questions with AI

Whiting-Turner Contracting Co. v. Guarantee Company of North America USA, 2019 COA 44, 440 P.3d 1282 (Colo. Ct. App. 2019).

2019 COA 44 (Whiting-Turner Contracting Co. v. Guarantee Company of North America USA) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Western Development v. Lionshead Inn
Colorado Court of Appeals, 2026
Kingsford v. Northern Lights
Colorado Court of Appeals, 2026
Green v. US Anesthesia
Colorado Court of Appeals, 2026
Frosh v. Alexia
Colorado Court of Appeals, 2026
Leventhal v. Jensen
Colorado Court of Appeals, 2025
Estate of Willis
Colorado Court of Appeals, 2025
Marriage of Athow
Colorado Court of Appeals, 2025
Marriage of Dyar
Colorado Court of Appeals, 2025
Nichele Giron v. Justin Hice
Colorado Court of Appeals, 2022
Parental Responsibilities Concerning D.P.G
2020 COA 115 (Colorado Court of Appeals, 2020)
v. Knox
2019 COA 152 (Colorado Court of Appeals, 2019)
23 LTD v. Herman
2019 COA 113 (Colorado Court of Appeals, 2019)