Powder Horn Constructors, Inc. v. City of Florence

754 P.2d 356, 12 Brief Times Rptr. 661, 1988 Colo. LEXIS 79, 1988 WL 36094
CourtSupreme Court of Colorado
DecidedApril 25, 1988
Docket85SC502
StatusPublished
Cited by32 cases

This text of 754 P.2d 356 (Powder Horn Constructors, Inc. v. City of Florence) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Powder Horn Constructors, Inc. v. City of Florence, 754 P.2d 356, 12 Brief Times Rptr. 661, 1988 Colo. LEXIS 79, 1988 WL 36094 (Colo. 1988).

Opinions

KIRSHBAUM, Justice.

In City of Florence v. Powder Horn Constructors, Inc., 716 P.2d 143 (Colo.App.1985), the Court of Appeals affirmed a trial court judgment ordering forfeiture of a bid bond executed for the benefit of the City of Florence (the City) by the petitioners, Powder Horn Constructors, Inc. (Powder Horn) and Powder Horn’s surety, St. Paul Fire and Marine Insurance Co. (St. Paul). The City filed a civil action requesting the forfeiture as damages for Powder Horn’s refusal, as low bidder, to accept the City’s award of a public improvement construction contract. Powder Horn asserted as a defense a right to equitable relief from the provisions of the bond on the ground that it had rescinded its bid; the trial court rejected this claim. The Court of Appeals held that under certain circumstances a low bidder for a public construction contract may rescind its bid, but affirmed the trial court’s judgment. Having granted certio-rari to review that decision, we reverse and remand with directions.

I

On December 24, 1981, the City published an advertisement for sealed bids for construction work on a water treatment facility. The bids were initially due on January 14, 1982, but that date was subsequently extended to January 19, 1982. On January 6, 1982, Powder Horn obtained a set of documents from, the City detailing the engineering specifications for the project.

On January 19, 1982, Powder Horn submitted a bid of $699,500 for the project. As required by the terms of the bid documents, it also submitted a bid bond in the [358]*358sum of five percent of its total bid.1 When the bids were publicly opened late that same day, Powder Horn was identified as the low bidder. The second lowest bid price was $754,330.

The next day, January 20, Paul Gilbert, the City’s consulting engineer in charge of administering the project, telephoned Michael O’Clair, a Powder Horn estimator, and advised him that in tabulating the bids he had found one item in Powder Horn’s bid that appeared to be substantially low in view of the other bids submitted. Gilbert suggested that Powder Horn might want to review that particular item.

On January 21, Powder Horn’s president, Cletus Donahue, informed Gilbert by telephone that Powder Horn had mistakenly omitted from its bid the sum of $66,660, representing the cost of one major item, and that the bid was therefore being withdrawn. On that same day, Donahue also wrote a letter to Gilbert’s engineering firm in which he stated that a subtotal from one worksheet inadvertently had been omitted from the final bid amount, advised that the bid and the bid security were being withdrawn and offered to meet with the consulting engineers, the City attorney or other officials to demonstrate that the omission was an honest error.

On February 1, 1982, the City, through its city council, voted to award the contract to Powder Horn for the amount of $699,-500. On February 4, Donahue sent a letter to Gilbert’s engineering firm stating that Powder Horn would not accept the award of the contract. The City then awarded the contract to the second lowest bidder. That bidder accepted the contract and commenced work.

The City filed this action against Powder Horn and St. Paul, asserting a right to the amount of the bid bond as liquidated damages for Powder Horn’s failure to execute the construction contract. The complaint alleged that although the City’s actual damages equaled $54,830, the difference between Powder Horn’s bid and the second lowest bid, Powder Horn's liability was limited to the amount of the bid bond. Powder Horn asserted as a defense that it had rescinded its bid and therefore could not be held liable under the terms of the bid bond.

The trial court found that Powder Horn had not exercised reasonable care in preparing its bid. Based on this finding, it determined that Powder Horn was liable to the City in the amount of the bid bond. The trial court also determined that Powder Horn’s conduct constituted a unilateral mistake, that the mistake was material, that requiring Powder Horn to perform the contract would be unconscionable, and that Powder Horn had failed to establish that the City would not be prejudiced by the withdrawal of Powder Horn’s bid.

In affirming the trial court’s judgment, the Court of Appeals recognized that in some circumstances a bidder may be permitted to rescind a bid submitted for a public construction contract because of a mistake in calculating the bid. The Court of Appeals concluded that such a remedy is available only when the bidder proves by a preponderance of the evidence that: “(1) the mistake relates to a material feature of the contract; (2) it occurred despite the exercise of reasonable care; and (3) the public authority can be placed in status quo.” City of Florence v. Powder Horn Constructors, Inc., 716 P.2d 143, 144 (Colo.App.1985). It held that Powder Horn could not rescind the bid because it had not exercised reasonable care in preparing it. The Court of Appeals also observed that a public entity which has not changed its position in reliance on a mistaken bid has suffered no actual damages and is able to maintain the status quo merely by accepting the second lowest bid “since it has lost only what it sought to gain by taking advantage of the mistake.” Id. at 145.

We agree with the conclusion of the Court of Appeals that under certain circumstances a bidder submitting a bid for a public construction contract may be permitted to rescind the bid prior to its acceptance if it reflects a material mistake of fact. We do not agree, however, that the exercise of reasonable care is an appropriate [359]*359factor upon which to condition this right of rescission.

II

This case falls into that narrow class of public construction bid cases in which an issue of mistaken bid arises when, prior tó the public entity’s acceptance of the bid, the parties discover that the bid contains a material mathematical or clerical error. Powder Horn argues that under such circumstances the bidder should be allowed to withdraw its bid automatically without penalty. A substantial body of law supports Powder Horn’s argument, in effect concluding that where a bidder submits a bid containing a material mistake of fact and the bid is apparently accepted there has not been any meeting of the minds because the bid accepted by the public entity is not the bid intended by the bidder. E.g., Moffett, Hodgkins & Clarke Co. v. Rochester, 178 U.S. 373, 20 S.Ct. 957, 44 L.Ed. 1108 (1900); Marana Unified School Dist. No. 6 v. Aetna Cas. & Sur. Co., 144 Ariz. 159, 696 P.2d 711 (Ariz.App.1984); Regional School Dist. No. 4 v. United Pac. Ins. Co., 4 Conn.App. 175, 493 A.2d 895, certif. denied, 196 Conn. 813,494 A.2d 907 (1985); Baltimore County v. John K. Ruff, Inc., 281 Md. 62, 375 A.2d 237 (1977); Mississippi State Bldg. Comm’n v. Becknell Constr., Inc., 329 So.2d 57 (Miss.1976); City of Syracuse v. Sarkisian Bros., Inc., 87 A.D.2d 984, 451 N.Y.S.2d 945, aff'd, 57 N.Y.2d 618, 454 N.Y.S.2d 71, 439 N.E.2d 880 (1982); Arcon Constr. Co. v. State, 314 N.W.2d 303 (S.D.1982); State Highway Comm’n v. Camion, 250 S.W.2d 439 (Tex.Civ.App.1952); see also D. Dobbs, Handbook on the Law of Remedies

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jefferson Solar, LLC v. FuelCell Energy, Inc.
224 Conn. App. 710 (Connecticut Appellate Court, 2024)
Tatonka Capital Corp. v. Connelly
390 F. Supp. 3d 1289 (D. Colorado, 2019)
People v. Bondsteel
2015 COA 165 (Colorado Court of Appeals, 2015)
East Porter County School Corp. v. Gough, Inc.
965 N.E.2d 684 (Indiana Court of Appeals, 2012)
PurCo Fleet Services, Inc. v. Koenig
240 P.3d 435 (Colorado Court of Appeals, 2010)
Sumerel v. Goodyear Tire & Rubber Co.
232 P.3d 128 (Colorado Court of Appeals, 2009)
City of Raton v. ARKANSAS RIVER POWER AUTHORITY
760 F. Supp. 2d 1132 (D. New Mexico, 2009)
Denver Foundation v. Wells Fargo Bank, N.A.
163 P.3d 1116 (Supreme Court of Colorado, 2007)
No. 03-1295
375 F.3d 1054 (Tenth Circuit, 2004)
Shoels v. Klebold
375 F.3d 1054 (Tenth Circuit, 2004)
Carr-Gottstein Properties, Ltd. Partnership v. Benedict
72 P.3d 308 (Alaska Supreme Court, 2003)
Board of County Commissioners v. City & County of Denver
40 P.3d 25 (Colorado Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
754 P.2d 356, 12 Brief Times Rptr. 661, 1988 Colo. LEXIS 79, 1988 WL 36094, Counsel Stack Legal Research, https://law.counselstack.com/opinion/powder-horn-constructors-inc-v-city-of-florence-colo-1988.