Boise Junior College District v. Mattefs Construction Co.

450 P.2d 604, 92 Idaho 757, 1969 Ida. LEXIS 225
CourtIdaho Supreme Court
DecidedFebruary 7, 1969
Docket10200
StatusPublished
Cited by20 cases

This text of 450 P.2d 604 (Boise Junior College District v. Mattefs Construction Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boise Junior College District v. Mattefs Construction Co., 450 P.2d 604, 92 Idaho 757, 1969 Ida. LEXIS 225 (Idaho 1969).

Opinion

SPEAR, Justice.

The issue presented is whether, under the circumstances of this case, a contractor is entitled to the equitable relief of rescission when it has submitted a bid which contains a material clerical mistake. We conclude that such relief is available.

Mattefs Construction Company (hereinafter termed respondent) was one of ten bidders on a construction contract to be let by Boise Junior College District (hereinafter referred to as appellant). Along with its bid respondent submitted the customary bid bond containing a promise to pay the difference between its bid and the next higher bid actually accepted if respondent refused to enter into a contract with appellant. Contract specifications also provided that the bid could not be withdrawn for 45 days after it was opened.

The architect’s estimate of costs on the building project was $150,000, but when the bids were opened seven of them ran in excess of $155,000 while three of them were less than $150,000. Fulton Construction Company bid $134,896. The respondent bid $141,048. The third bid by Cain and Hardy, Inc., was $148,915. When Fulton refused to sign a contract it was tendered to respondent who likewise refused to sign it. Ultimately the contract was awarded to Cain and Hardy, Inc., the third lowest bidder and appellant proceeded to attempt collection on respondent’s bid bond.

One who errs in preparing a bid for a public works contract is entitled to the equitable relief of rescission if he can establish the following conditions: (1) the mistake is material; (2) enforcement of a contract pursuant to the terms of the erroneous bid would be unconscionable; (3) the mistake did not result from violation of a positive legal duty or from culpable negligence; (4) the party to whom the bid is submitted will not be prejudiced except by the loss of his bargain; and (5) prompt notice of the error is given. These principles are established by substantial authority, i. e., Annot., 52 A.L.R.2d 792, § III; City of Baltimore v. De Luca-Davis Construction Co., 210 Md. 518, 124 A.2d 557 (1956); M. F. Kemper Const. Co. v. City of Los Angeles, 37 Cal.2d 696, 235 P.2d 7 (1951); State Highway Commission v. State Construction Company, 203 Or. 414, 280 P.2d 370, 380, 52 A.L.R.2d 779 (1955); President & Coun. of Mount St. Mary’s. Col. v. Aetna Cas. & Sur. Co., 233 F.Supp. 787, 794 (D.Md.1964); Conduit & Foundation Corporation v. Atlantic City, 2 N.J. Super. 433, 64 A.2d 382 (1949). That appellant recognizes these principles is evident, because it has raised questions as to-the existence of each one of these elements by its assignments of error. Therefore, we- *759 shall consider each of these conditions necessary for equitable relief, in the context of the objections raised.

I

Appellant contends that the trial court erred in determining that omission of the glass bid was a material mistake. The trial court found:

“This was the second largest sub bid item in the whole contract, only the mechanical sub bid being larger. It amounted to about 14% of the contract and was thus a material item.”

Thus, the issue is whether, as a matter of law, a 14% error in bid is a material error. We have no difficulty in reaching the conclusion that omission of an item representing 14% of the total bid submitted is substantial and material. Appellant cites a number of cases wherein courts have directly or indirectly determined that material error was not involved, in spite of mistakes which ranged up to 50%, i. e., Modany Bros. v. State Public School Building Authority, 417 Pa. 39, 208 A.2d 276 (1965); Tony Amodeo Company v. Town of Woodward, 192 Iowa 535, 185 N.W. 94 (1921); A. J. Colella, Inc. v. County of Allegheny, 391 Pa. 103, 137 A.2d 265 (1958); Gregory Ferend Company v. State, 251 App.Div. 13, 295 N.Y.S. 715 (1937). However, we are persuaded we should adopt a rule which is not so harsh and turn instead to authority such as Elsinore Union Elementary School Dist. v. Kastorff, 54 Cal.2d 380, 6 Cal.Rptr. 1, 353 P.2d 713 (1960), in which the court stated:

“Plaintiff suggests that in any event the amount of the plumbing bid omitted from the total was immaterial. The bid as submitted was in the sum of $89,994, and whether the sum for the omitted plumbing was $6,500 or $9,285 (the two sub bids), the omission of such a sum is plainly material to the total. In Lemoge (Lemoge Electric v. County of San Mateo (1956), supra, 46 Cal.2d 659, 661-662, 297 P.2d 638) the error which it was declared would have entitled plaintiff to rescind was the listing of the cost of certain materials as $104.52, rather than $10,452, in a total bid of $172,421. Thus the percentage of error here was larger than in Lemoge, and was plainly material.”

II

An error in the computation of a bid may be material, representing a large percentage of the total bid submitted, and yet requiring compliance with the bid may not be unconscionable. Thus, omission of a $25,000 item in a $100,000 bid would be material, but if the $100,000 bid included $50,000 in profit, no hardship would be created by requiring the contractor to comply with the terms of his bid.

This does not represent the case at bar. Here the record reveals that if respondent were forced to comply with the terms of its bid it would lose at least $10,000. Respondent’s costs, including the omitted item, would be roughly $151,000 while the total amount of its bid was only $141,000. Enforcement of the bid is deemed unconscionable as working a susbtantial hardship on the bidder where it appears he would incur a substantial pecuniary loss. Donaldson v. Abraham, 68 Wash. 208, 122 P. 1003 (1912). This is particularly so where, as here, no injury is caused by withdrawal of the bid. (See sec. IV, infra.)

III

One who seeks equitable relief from error must establish that such error does not result from violation of a positive legal duty or from culpable negligence.

“ * * * [This] generally means carelessness or lack of good faith in calculation which violates a positive duty in making up a bid, so as to amount to gross negligence, or wilful negligence, when it takes on a sinister meaning and will furnish cause, if established, for holding a mistake of the offending bidder to be one not remediable in equity. It is thus distinguished from a clerical *760 or inadvertent error in handling items of a bid either through setting them down or transcription.” (emphasis added) Annot., 52 A.L.R.2d 792, 794.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johannsen v. Utterbeck
196 P.3d 341 (Idaho Supreme Court, 2008)
National Fire Insurance v. Brown & Martin Co.
726 F. Supp. 1036 (D. South Carolina, 1989)
Powder Horn Constructors, Inc. v. City of Florence
754 P.2d 356 (Supreme Court of Colorado, 1988)
Marana Unified School District No. 6 v. Aetna Casualty & Surety Co.
696 P.2d 711 (Court of Appeals of Arizona, 1984)
Pope v. Intermountain Gas Co.
646 P.2d 988 (Idaho Supreme Court, 1982)
Rosecrans v. Intermountain Soap & Chemical Co.
605 P.2d 963 (Idaho Supreme Court, 1980)
R. J. Taggart, Inc. v. Douglas County
572 P.2d 1050 (Court of Appeals of Oregon, 1977)
Hollandsworth v. Cottonwood Elevator Company
511 P.2d 285 (Idaho Supreme Court, 1973)
Reardon v. Union Pacific Railroad
475 P.2d 370 (Idaho Supreme Court, 1970)
Smith v. Daniels
471 P.2d 571 (Idaho Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
450 P.2d 604, 92 Idaho 757, 1969 Ida. LEXIS 225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boise-junior-college-district-v-mattefs-construction-co-idaho-1969.