Westway Construction, Inc. v. Idaho Transportation Department

73 P.3d 721, 139 Idaho 107, 2003 Ida. LEXIS 115
CourtIdaho Supreme Court
DecidedJuly 11, 2003
Docket28464, 28484
StatusPublished
Cited by19 cases

This text of 73 P.3d 721 (Westway Construction, Inc. v. Idaho Transportation Department) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westway Construction, Inc. v. Idaho Transportation Department, 73 P.3d 721, 139 Idaho 107, 2003 Ida. LEXIS 115 (Idaho 2003).

Opinion

*110 EISMANN, Justice.

This is an appeal from a judgment upholding the forfeiture of a bid bond submitted by a bidder on a public works contract and holding the surety liable for the face amount of the bond. We vacate the judgment because the parties did not exhaust their administrative remedies.

I. FACTS AND PROCEDURAL HISTORY

On May 10, 2000, the Idaho Transportation Department (ITD) advertised for bids for a federal-aid highway project to be constructed in Bonner County, Idaho. The time for opening the bids was scheduled for 2:00 p.m. on June 8, 2000. During the morning of June 8, 2000, Westway Construction, Inc. (Westway) submitted a bid, which was accompanied by a bid bond 1 that had been issued by United States Fidelity and Guaranty Company (USF & G). Prior to submitting its bid, Westway had received bids from two asphalt subcontractors, namely, Interstate Concrete & Asphalt Co. (Interstate) and Acme Materials & Construction Co. (Acme). It based its bid calculations upon the bid it had received from Interstate because its total bid was lower than Acme’s total bid.

After Westway had submitted its bid, Interstate faxed it a revised subcontractor bid, changing the prices on several items in its bid. One of the items entitled “Plant Mix Pavement Class I” was increased from $690,750.00 in Interstate’s original bid to $825,750.00 in its revised bid. That same item in the Acme bid was listed as $684,000.00. Westway contends that it then prepared a revised, lower bid using some figures from the Interstate bid and some from the Acme bid. Westway submitted its revised bid prior to the bid opening, and it was the low bid.

On June 9, 2000, Westway sent the ITD a letter asking to withdraw its revised bid based upon a mistake. It contends that it had misread Acme’s bid for the plant mix pavement. Acme had listed the bid item as “Plant Mix Pavement Class I (plus rock).” Acme intended the words “plus rock” to mean that the mineral aggregate (rock) was excluded from the bid. Obtaining the necessary mineral aggregate would cost Westway approximately $210,150.00.

On June 14, 2000, the ITD responded by letter advising Westway that “there appears to be no question that a mistake was made and therefore withdrawal of the bid is allowed.” The letter added, however, ‘Your letter and attachments will be turned over to our legal staff for a determination as to relief from bond forfeitures.” On August 14, 2000, the ITD’s counsel sent Westway a letter stating that Idaho Code § 54-1904C only permitted return of the bid security if the bidder made a clerical or mathematical mistake; that Westway’s mistake cannot be classified as a clerical mistake because it was a judgmental error; and that if Westway paid $538,240.95 within thirty days, its bid bond would be returned.

On September 14, 2000, a roadway design engineer for the ITD sent a letter entitled “Final Report” which was written “to document the facts concerning problems with the bid of Westway Construction, Inc. and the existence of each element required in Idaho code 54-1904C in order to qualify for relief from bids allowed by Idaho code 54-1904B.” After reciting various facts, he stated, “We therefore have not been provided enough information to determine that a clerical mistake was made.” He concluded, “The Idaho Transportation Department finds that all elements have not been met for relief from forfeiture of bond per Idaho code 54-1904C.”

On December 4, 2000, Westway filed this action against the ITD seeking a declaratory judgment that it had made a clerical mistake in its bid and was therefore entitled to the return of its bid bond. The ITD answered and then filed a third-party complaint against USF & G seeking a judgment in the sum of $538,241.32, the face amount of the bid bond. Westway and USF & G both moved for summary judgment, and after oral argument the district court issued a memorandum deci *111 sion denying both motions. The district court found that the ITD had not abused its discretion in determining that Westway was not entitled to relief from the forfeiture of its bid bond. The district court then entered judgment declaring the bid bond forfeited and awarding the ITD damages against USF & G in the sum of $538,241.32. Both West-way and USF & G timely appealed.

After oral argument, this Court asked the parties to submit additional briefing on two issues: (1) Whether or not the Idaho Administrative Procedures Act (APA) applies to this case; and (2) If it does, whether or not a final order has been issued under the APA. Both Westway and the ITD submitted post-argument briefs.

II. ANALYSIS

A. Does the APA Govern the Determination of Whether Westway Is Entitled to Relief from Its Bid and the Return of Its Bid Security?

Idaho Code § 54-1904B provides that a public works contractor, who has submitted a bid to a public entity in competitive bidding for the construction, alteration, repair, or improvement of public works construction, may obtain relief from the bid because of a mistake. A bidder who claims a mistake in the bid submitted is entitled to relief from the bid and the return of any bid security if the bidder satisfies all of the conditions of Idaho Code § 54-1904C. IDAHO CODE § 54-1904B(b) (2000). If the bidder does not satisfy those conditions, then the bid security is forfeited. Id. Idaho Code § 54-1904C provides as follows:

The bidder shall establish to the satisfaction of the public entity that:
(a) A clerical or mathematical mistake was made;
(b) The bidder gave the public entity written notice within five (5) calendar days after the opening of the bids of the mistake, specifying in the notice in detail how the mistake occurred; and
(e) The mistake was material.

Because the doctrine of exhaustion of administrative remedies generally requires that a case run the full gamut of administrative proceedings before an application for judicial review may be considered, McVicker v. City of Lewiston, 134 Idaho 34, 37, 995 P.2d 804, 807 (2000), we must decide whether the APA governs the determination of whether a bidder has satisfied the conditions set forth in Idaho Code § 54-1904C.

The APA governs that determination if it is a “contested case,” which is defined as a “proceeding by an agency, other than the public utilities commission or the industrial commission, that may result in the issuance of an order.” IDAHO CODE § 67-5240 (2001).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kootenai County v. Harriman-Sayler
293 P.3d 637 (Idaho Supreme Court, 2012)
Vickers v. Lowe
247 P.3d 666 (Idaho Supreme Court, 2011)
Laughy v. ConocoPhillips Co.
Idaho Supreme Court, 2010
Laughy v. Idaho Department of Transportation
243 P.3d 1055 (Idaho Supreme Court, 2010)
Potlatch Education Ass'n v. Potlatch School District No. 285
226 P.3d 1277 (Idaho Supreme Court, 2010)
In Re Schroeder
210 P.3d 584 (Idaho Court of Appeals, 2009)
Schroeder v. State, Department of Transportation
210 P.3d 584 (Idaho Court of Appeals, 2009)
Lochsa Falls, L.L.C. v. State
207 P.3d 963 (Idaho Supreme Court, 2009)
Hayden Lake Fire Protection District v. Alcorn
111 P.3d 73 (Idaho Supreme Court, 2005)
Gibson v. Bennett
108 P.3d 417 (Idaho Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
73 P.3d 721, 139 Idaho 107, 2003 Ida. LEXIS 115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westway-construction-inc-v-idaho-transportation-department-idaho-2003.